HomeMy WebLinkAboutEx_07_Construction_MitigationPreliminary Construction Mitigation Plan
For
Haevin Ridge Short Plat
Proposed Construction Dates (begin and end dates):
Based on this preliminary short plat application date, we anticipate construction permits for
utilities and plat infrastructure (roads, sidewalks, etc.) to be finalized in the fourth quarter of 2018
with utility and plat infrastructure construction possibly beginning in late 2018 or early 2019.
Home construction on the lots should begin during the summer of 2019 and run through at least
the winter of 2019 and possibly longer, depending on lot sales.
Hours and Days of Operation:
Construction activities will be limited to the hours between 7:00am and 8:00pm, Monday through
Friday and 9:00am and 8:00pm Saturday. In addition, haul hours are limited to the hours between
8:30am and 3:30pm on Saturdays, unless approved in writing in advance by the development
services division. No work permitted on Sundays.
Proposed Hauling/Transportation Routes:
The site is accessible from two main directions. From the south via 116th Ave SE / SE 192nd Street
/ 108th Ave SE (Benson) / SE 208th – 212th Street / I-167. From the north via 116th Ave SE / SE
176th Street (Petrovitsky – Carr Road) / I-167.
Measures to be implemented to minimize dust, traffic and transportation impact, erosion,
mud, noise and other noxious characteristics:
Water Truck, Temporary Erosion Control Plan, BMPs, construction proposed during City of
Renton permitted work hours.
Any special hours proposed for construction or hauling (i.e. weekends, late nights):
No special hours for construction or hauling are anticipated or proposed at this time.
Preliminary Traffic Control Plan:
Site is located along 116th Ave SE (classified minor arterial) just south of Benson Hill Elementary.
Anticipate “construction ahead” warning signs north / south of the project along 116th Ave SE.
Flaggers and additional signage will be provided when work is required in either right-of-way.
Construction staging will be limited to on-site with parking on-site and along 116th Ave SE only
as permitted.
Final Traffic Control Plan will be provided at the time of Engineering approval.