HomeMy WebLinkAboutPN_Project_Narrative_220627_v2
Project Narrative
City of Renton Senior Center Bocce Court Improvements
Submitted to:
City of Renton
Planning/Building/Economic Development Division
Renton, Washington
On Behalf of Applicant:
City of Renton, Parks Planning & Natural Resources
Renton, Washington
16 June 2022, revised 07 July 2022
Submitted by
WSP USA
33301 Ninth Avenue South, Suite 300
Federal Way, Washington
30901826.000
City of Renton WSP USA, 30901826.000
Senior Center Bocce Court Improvements 16 June 2022
Renton, Washington Page i of i
PROJECT NARRATIVE
CITY OF RENTON SENIOR CENTER BOCCE COURT IMPROVEMENTS
TABLE OF CONTENTS
SECTION PAGE
1.0 SHORELINE NARRATIVE ............................................................................................. 1
1.1 Proposed Action ............................................................................................... 1
1.2 Duration of Activities ........................................................................................ 1
1.3 Additional Site Information .............................................................................. 2
1.3.1 Zoning Designation ............................................................................... 2
1.3.2 Current Use ............................................................................................ 2
1.3.3 Special Site Features ............................................................................ 2
1.3.4 Soil Type and Drainage Conditions ..................................................... 2
1.3.5 Project Cost ........................................................................................... 2
1.3.6 Fill and Excavation ................................................................................ 2
1.3.7 Trees ...................................................................................................... 2
1.3.8 Adjacent Water Area and Nature of Existing Shoreline ...................... 3
2.0 REFERENCES ............................................................................................................... 3
LIST OF TABLES
Table 1. Required Permits ....................................................................................................... 1
1.0 SHORELINE NARRATIVE
The City of Renton (City) Parks Planning & Natural Resources Department proposes
a project at the Renton Senior Activity Center fitness area, which is located at 211
Burnett Avenue N, Renton, King County, Washington 98057. The project area is
within the Township 23N, Range 5E, Section 18 and is just northeast of the Cedar
River. The project includes the removal of existing synthetic turf comprising the
bocce court area. The gravel underlaying the bocce court area will be lowered several
inches and rubberized surfacing will be poured in place to bring the rubberized
surface level with the existing surrounding surface. A corn hole court, ping pong
table, pour-in-place checkerboard, and exercise equipment including a cardio stepper,
health hand beat cycler, balance steps, assisted row/push up, and stretch equipment
will be added to the new rubberized surface area. Additional proposed improvements
include the removal and replacement of existing shrubs, new concrete pads for
benches, and the replacement of existing benches.
The purpose of this project narrative is to meet the requirements set forth under
Renton Municipal Code 4-8-120C (Submittal Requirements – Specific to Application
Type: Land Use Applications). All permits required for this project are listed below in
Table 1.
Table 1. Required Permits
Permit Agency
Shoreline Substantial Development Permit City of Renton
1.1 PROPOSED ACTION
The purpose of the project is to improve a bocce court for senior citizens at the
Renton Senior Activity Center (Sheet 1). The bocce court is located along Cedar
River in Renton, Washington.
Proposed improvements include the removal and replacement of existing shrubs,
replacement of existing benches and concrete pads for benches, the addition of a corn
hole court and metal tennis table, pour-in-place rubberized surfacing, a pour-in-place
checkerboard, and improvements to make the court flush with existing concrete
pavement. The existing synthetic turf will be removed and the gravel underlaying the
bocce court area will be lowered several inches. Rubberized surfacing will be poured
in place to bring the bocce court area level with the existing surrounding surface. The
existing concrete pads that support benches will be broken up to remove the existing
benches. New concrete will be poured within the same area and new benches will be
positioned within the replaced concrete pads.
1.2 DURATION OF ACTIVITIES
Construction for the proposed action would begin November 01, 2022 and will be
completed by December 31, 2022.
1.3 ADDITIONAL SITE INFORMATION
The purpose of this section is to provide the remaining project narrative information
listed in the City of Renton’s Submittal Requirements – Shoreline Substantial
Development Permit (City of Renton 2022).
1.3.1 Zoning Designation
The City of Renton Maps list the current zoning designation for the project site as
Residential High Density or Residential 10 DU/Acre.
1.3.2 Current Use
The project area is currently used by the Renton Senior Activity Center as a bocce
court for senior citizens.
1.3.3 Special Site Features
There are no special site features, such as wetlands, water bodies, and steep slopes,
within the project area. A portion of the project lies within the 100-year floodplain of
the Cedar River. No work will occur within the regulatory floodway. The only work
that will occur within the floodway is the installation of two benches on concrete
pads. The concrete pads will be installed to match the existing grade and will not
reduce the storage volume within the floodplain. No compensatory storage will be
required.
1.3.4 Soil Type and Drainage Conditions
The Natural Resources Conservations Service Web Soil Survey mapper lists the soils
in the project area as Type UR – Urban land.
Topography slopes towards Cedar River and drainage at the project site goes directly
to the river. No pollution-generating surfaces are located within the project area.
1.3.5 Project Cost
The approximate construction cost and fair market value of the proposed project is
$50,000.00.
1.3.6 Fill and Excavation
Excavation for this proposal will be of minimal depth and within a small footprint
(2,567 square feet). Excavation will take place within an existing developed footprint.
The existing synthetic turf will be removed and the gravel underlaying the bocce
court area will be lowered several inches. Rubberized surfacing will be poured in
place to bring the bocce court area level with the existing surrounding surface.
Poured-in-place rubberized surfacing will be placed in an approximately 2,560-
square-foot area. Two new benches will have a 12-square-foot concrete pad.
1.3.7 Trees
No trees will be removed as a result of the proposed project.
1.3.8 Adjacent Water Area and Nature of Existing Shoreline
Cedar River is adjacent to the project area. The shoreline is a low bank and consists
of sand, gravel, and rocks with no bulkheading. The proposed project will not
obstruct any views from neighboring structures.
2.0 REFERENCES
City of Renton. 2022. Maps of Your Community. Accessed at
http://rp.rentonwa.gov/HTML5Public/Index.HTML?viewer=CORMaps
Accessed on 25 April 2022.
City of Renton. 2022. Submittal Requirements – Shoreline Exemption. Department of
Community and Economic Development. Planning Division. Revised April
2022.