FIELD REPORT
Date Project Name Project No. Report No.
07/01/2022 Renton Elementary School 16 20180398E003 034
Location Municipality AESI Project Manager AESI Field Rep
1075 Duvall Ave NE Renton Bruce Guenzler, L.E.G. Bruce Guenzler
Permit No. Client/Owner Attn Requested By
B21004604 Renton School District No. 403 Ed Thomson Client
Engineer/Architect General Contractor Grading Contractor Weather
CPL / Hutteball + Oremus Cornerstone/Kyle Continental Dirt Contractors/ Jerry Jr. Cloudy, 60’s
THE FOLLOWING WAS NOTED:
AESI arrived mid-morning at the request of the contractors in order to observe the aeration and compaction of lifts in the North
grading area. Water main progress continued as detailed below. TESC weekly checklist was completed and submitted separately.
North Grading Area:
Aeration progress slowed substantially today due to overcast and cool temperatures. No additional fill was placed during our visit.
Water Line:
Water line progress to the south continued. A segment of water line excavated yesterday was backfilled with a combination of ballast
rock and native soil that was too coarse for densometer testing. Fill was placed in lifts and qualitatively observed with a hand probe
and visually and appears adequate to support the planned fire lane in our opinion.