HomeMy WebLinkAboutNOA_Project_Acceptance_Mailer_220728DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059044 LUA22-000272
Current Resident
710 Rainier Ave S
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be notified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center s ite located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059053 LUA22-000272
Current Resident
720 Rainier Ave S
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center s ite located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in th e Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
3340402670 LUA22-000272
Current Resident
101 SW Grady Way
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be notified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059102 LUA22-000272
Current Resident
355 S Grady Way
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059032 LUA22-000272
Current Resident
205 S 7th St LOT
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059073 LUA22-000272
Current Resident
765 Rainier Ave S
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059073 LUA22-000272
Current Resident
765 Rainier Ave S UNIT B
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059054 LUA22-000272
Current Resident
301 S Grady Way
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059027 LUA22-000272
Current Resident
707 Rainier Ave S
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059027 LUA22-000272
Current Resident
739 Rainier Ave S
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 100
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 101
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 110
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 115
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 120
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 200
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 240
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 243
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 245
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 248
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 249
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 250
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 250A
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 250B
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 250C
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 250D
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 251
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 300
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 310
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 312
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 321
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 330
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 331
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 332
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 333
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 336
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 400
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 408
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 409
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 410
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 417
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 420
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 424
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 433
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 434
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 436
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 500
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 509
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 514
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 517
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 519
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 520
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 522
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 524
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 526
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 527
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 528
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 533
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 534
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 535
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 600
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 610
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 620
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 621
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 625
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 627
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 628
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 631
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 633
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite 634
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite LL14
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite LL16
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite LL18
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite LL19
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite LL24
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite LL25
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite LL27
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite LL30
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite LL32
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite LL33
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
15 S Grady Way Suite LL36
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
Current Resident
311 S Grady Way LOT
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059031 LUA22-000272
Current Resident
201 S 7th St
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059103 LUA22-000272
Current Resident
375 S Grady Way
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059063 LUA22-000272
Current Resident
101 S Grady Way
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059048 LUA22-000272
Current Resident
743 Rainier Ave S
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059017 LUA22-000272
Current Resident
105 SW 7th St
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059104 LUA22-000272
Current Resident
225 SW 7th St
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059104 LUA22-000272
Current Resident
241 SW 7th St
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059104 LUA22-000272
Current Resident
735 Hardie Ave SW
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059104 LUA22-000272
Current Resident
741 Rainier Ave S
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
3340401630 LUA22-000272
Current Resident
1 S Grady Way
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059029 LUA22-000272
Current Resident
757 Rainier Ave S UNIT 1
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059029 LUA22-000272
Current Resident
757 Rainier Ave S UNIT 2
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059029 LUA22-000272
Current Resident
757 Rainier Ave S UNIT 3
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059029 LUA22-000272
Current Resident
757 Rainier Ave S UNIT 4
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059029 LUA22-000272
Current Resident
757 Rainier Ave S UNIT 5
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059029 LUA22-000272
Current Resident
757 Rainier Ave S UNIT 6
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059029 LUA22-000272
Current Resident
757 Rainier Ave S UNIT 6A
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059029 LUA22-000272
Current Resident
757 Rainier Ave S UNIT 7
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059029 LUA22-000272
Current Resident
757 Rainier Ave S UNIT 8
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059029 LUA22-000272
Current Resident
757 Rainier Ave S UNIT 9
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059101 LUA22-000272
Current Resident
365 S Grady Way Suite A
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059101 LUA22-000272
Current Resident
365 S Grady Way Suite B
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059101 LUA22-000272
Current Resident
365 S Grady Way Suite C
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059101 LUA22-000272
Current Resident
365 S Grady Way Suite D
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059101 LUA22-000272
Current Resident
365 S Grady Way Suite E
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059101 LUA22-000272
Current Resident
365 S Grady Way Suite F
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059101 LUA22-000272
Current Resident
365 S Grady Way Suite G
Renton WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059044 LUA22-000272
SFP-A LIMITED PARTNERSHIP
PO BOX 5350
BEND OR 97708
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059053 LUA22-000272
AIR LOCKER INC
4810 D STREET NW #103
AUBURN WA 98001
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059074 LUA22-000272
(CPSRTA) SOUND TRANSIT
401 S JACKSON STREET
SEATTLE WA 98104
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
3340402670 LUA22-000272
AZULE PROPERTIES L L C
5411 154TH AVE SE
BELLEVUE WA 98006
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059021 LUA22-000272
RENTON PROPERTY HOLDING LLC
200 SW GRADY WY
RENTON WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059068 LUA22-000272
(CPSRTA) SOUND TRANSIT
401 S JACKSON STREET
SEATTLE WA 98104
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059102 LUA22-000272
RVA LAND LLC
15 S GRADY WAY #520
RENTON WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059032 LUA22-000272
KING COUNTY-TRANSIT
M\S 901-TR-0440
901 5TH AVE SUITE 400
SEATTLE WA 98164 NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059073 LUA22-000272
BONNELL FAMILY LLC
C/A U.S.W. PETROL CORP #115
906 RANCHERO CONEJO BLVD
NEWBURY PARK CA 91320 NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059054 LUA22-000272
SAIFIL PROPERTIES LLC
2900 SE 3RD ST
RENTON WA 98056
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059027 LUA22-000272
RAINIER TRIANGLE LLC
25516 142ND AVE SE
KENT WA 98042
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
7232000020 LUA22-000272
RVA OFFICE LLC
15 S GRADY WAY #520
RENTON WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059031 LUA22-000272
RENTON PROP HOLDING LLC
200 SW GRADY WY
RENTON WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059103 LUA22-000272
RVA LAND LLC
15 S GRADY WAY #520
RENTON WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059063 LUA22-000272
(CPSRTA) SOUND TRANSIT
401 S JACKSON STREET
SEATTLE WA 98104
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059048 LUA22-000272
WALMART INC
ATTN PROPERTY TAX DEPT
PO BOX 8050 MS 0555
BENTONVILLE AR 72716 NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059074 LUA22-000272
(CPSRTA) SOUND TRANSIT
401 S JACKSON STREET
SEATTLE WA 98104
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059017 LUA22-000272
RA MAC INC
4607 FOREST AVE SE
MERCER ISLAND WA 98040
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059104 LUA22-000272
BONNELL FAMILY LLC
10047 MAIN STREET #509
BELLEVUE WA 98004
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059063 LUA22-000272
(CPSRTA) SOUND TRANSIT
401 S JACKSON STREET
SEATTLE WA 98104
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
3340401630 LUA22-000272
RENTON HOTEL INVESTORS LLC
1 S GRADY WY
RENTON WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059035 LUA22-000272
(CPSRTA) SOUND TRANSIT
401 S JACKSON STREET
SEATTLE WA 98104
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059068 LUA22-000272
(CPSRTA) SOUND TRANSIT
401 S JACKSON STREET
SEATTLE WA 98104
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059029 LUA22-000272
BONNELL FAMILY L L C
10047 MAIN STREET #509
BELLEVUE WA 98004
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
1923059101 LUA22-000272
RVA LAND LLC
15 S GRADY WAY #520
RENTON WA 98057
NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
LUA22-000272
Puget Sound Energy
Wendy Weiker, Community Svs. Mgr.
355 110th Ave NE, Mailstop EST 11W
BELLEVUE WA 98004 NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St
DEPARTMENT OF COMMUNITY & ECONOMIC DEVELOPMENT
Planning Division
1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425 -430-7200, ext. 2
www.rentonwa.gov
OF APPLICATION
A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the applic ation and the necessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
LUA22-000272
King County Department of Permitting & Environmental Review
Attn: SEPA Section
35030 SE Douglas St, Ste 210
Snoqualimie WA 98065 NOTICE
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be no tified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
SW 7th St