A Master Application has been filed and accepted with the Department of Community & Economic Development (CED)
Planning Division of the City of Renton. The following briefly describes the application and the n ecessary Public
Approval.
DATE OF NOTICE OF APPLICATION: July 28, 2022
PROJECT NAME/NUMBER: PR21-000095 South Renton Transit Center / LUA22-
000272, TUP
PROJECT LOCATION: 750 Rainier Ave S (APN 192305-9035, -9063, -9068, -
9074)
APPLICANT/PROJECT CONTACT
PERSON:
Gary Yao, Sound Transit / 401 S Jackson St, Seattle, WA 98104 /
gary.yao@soundtransit.org
LOCATION WHERE APPLICATION MAY
BE REVIEWED:
Applicant documents are available online through the City of Renton
Document Center website. See also https://cutt.ly/uZhoYr3
PROJECT DESCRIPTION: The applicant, Sound Transit, is requesting a Tier II Temporary Use Permit to conduct
soil remediation work and place artwork at the South Renton Transit Center site located at 750 Rainier Ave S (APN
192305-9035, -9063, -9068, -9074). The soil remediation work would include excavating and removing known
contaminated material on-site and backfilling would be completed using non -contaminated soil through best
management practices and controls. The soil remediation work will require a Building Grading Permit. According to COR
Maps, the site contains high seismic hazards and is in the Downtown Wellhead Protection Area (Zone 2). Sound Transit,
the lead agency for the new South Renton Transit Center and BRT station, issued a Determination of Nonsignificance
(DNS) under WAC 197-11-340 (2) and Sound Transit’s SEPA rules on September 30, 2020. The applicant submitted a
remediation plan, geotechnical recommendation report, storm drainage report, and contract specifications with the
application.
DATE OF APPLICATION: July 27, 2022
NOTICE OF COMPLETE APPLICATION: July 28, 2022
PERMITS/REVIEW REQUESTED: Tier II Temporary Use Permit
OTHER PERMITS WHICH MAY BE
REQUIRED:
Construction Permit, Critical Area Permit or Letter of Exemption
REQUESTED STUDIES: Storm Drainage Report, Geotechnical Recommendation Report
Comments on the above application must be submitted in writing by 5:00 PM on August 11, 2022. Please submit
comments online at https://cutt.ly/SQvBak4. Alternatively, you may physically mail your comments to: City of Renton,
CED, Attn: Planning Division, 1055 South Grady Way, Renton, WA 98057. Please include the Land Use file number (LUA)
NOTICE
SW 7th St
Anyone that would like to be informed of future actions or would like to become a party of record on this proposal must
fill out our online form at https://cutt.ly/SQvBak4 or complete this form and return to: City of Renton, CED Planning
Division, 1055 So. Grady Way, Renton, WA 98057.
Name/File No.: PR21-000095 South Renton Transit Center / LUA22-000272, TUP
Name: __________________________________ Email: _______________________ Phone No. ___________________
Mailing Address: __________________________________City/State/Zip: _____________________________________
Notice will be sent via email, unless a hard copy is specifically requested. Check box to receive via US Mail
or project address in your comments. Anyone who submits written comments will automatically become a party of
record and will be notified of any decision on this project.
Contact Project Planner: Clark H. Close, Principal Planner; Tel: (425) 430-7289 ; Email: cclose@rentonwa.gov
Hardie Ave SW SW 7th St Lake Ave S