FIELD REPORT
Date Project Name Project No. Report No.
07/25/2022 Renton Elementary School 16 20180398E003 042
Location Municipality AESI Project Manager AESI Field Rep
1075 Duvall Ave NE Renton Bruce Guenzler, L.E.G. Scott R. Hannah, L.G.
Permit No. Client/Owner Attn Requested By
B21004604 Renton School District No. 403 Ed Thomson Contractor
Engineer/Architect General Contractor Grading Contractor Weather
CPL / Hutteball + Oremus Cornerstone/Kyle Continental Dirt Contractors/ Jerry Jr. Sunny, 80’s
THE FOLLOWING WAS NOTED:
AESI was onsite today at 2:15 pm to observe earthwork operations. While on-site, we met with Jerry Jr. with Continental Dirt
Contractors (CDC) and Jared with Cornerstone. CDC was installing shallow storm line along the west side of the bus loop. CDC had
finish-graded and recompacted the surface of the northern portion of the bus loop and hardscape areas. They were also cutting
down the bus loop road between SD 7 and SD 5 approximately 8 inches in order to place a layer of winterizing rock, per Jerry Jr.
On-site Storm Installation SD 7 to SD 5:
While onsite today, we observed CDC installing shallow storm at SD 5. The storm excavation extended approximately 40 feet
southwards of SD 5 towards SD 4 at the time of our site visit. Cut stakes showed the pipe invert elevation to be on the order of 4 feet deep at SD 4. Earlier today, CDC installed and backfilled the shallow storm from SD 7 southwards to near SD 5. The backfill consisted
mostly of onsite soil mixed in varying amounts with the 2-1/2 inch minus crushed rock used for the building pad and some of the
road area. The compacted surface of the trench just north of SD 5 was observed with a ½ inch diameter, steel soil probe and noted
to be in a firm and unyielding condition. The surface along the storm trench north of SD 5 to SD 7 was being cut by a dozer to lower
the road area. AESI will complete surface tests over the storm line at a later date. CDC planned to continue shallow storm
tomorrow west of SD 4. The storm pipe is shown in Figure 1 below.
Figure 1: Shallow storm being installed today shown in blue.
SD 7
SD 4 SD 5
16
Date Project Name Project No. Report No.
07/25/2022 Renton ES 16 20180398E003 042
Page 2 of 2
FIELD REPORT
SD 6 looking S SD 6 looking N
Finish-graded northern Bus loop looking N