HomeMy WebLinkAboutC_On Hold Letter_Tran Short Plat_220823_v1
August 24, 2022
Will Sowder
Puget Sound Permits
405 6th Avenue
Tacoma, WA 98402
SUBJECT: "On Hold" Notice
Tran Short Plat, LUA22-00276, SHPL-A, MOD
Dear Mr. Sowder,
The Planning Division of the City of Renton accepted the above master application for review on July 27, 2022.
During review of the submitted project documents, staff has determined that additional information is needed in
order to proceed with review of the application. Specifically, the applicant shall address the following:
- Provide updated Technical Information Report that complies with the 2022 Renton Surface Water Design
Manual
- Update site plan to show joint use driveway tract between lots 1 and 2 as required in original Tran Short
Plat decision and as shown on the civil construction permit documents.
- Update conceptual landscape plan to comply with landscape requirements in RMC 4-4-070, including
adding on-site trees to meet tree density minimum, providing street trees in front of all three lots, and 10
feet of on-site landscaping along all lot frontages.
At this time, your project has been placed “on hold” pending receipt of the updated project documents identified
above and in the attached memo. The maximum time for resubmittal shall be within ninety (90) days of this notice,
unless an extension is approved by the Current Planning Project Manager. Please contact me at (425) 430-7219 if
you have any questions.
Sincerely,
Alex Morganroth
Senior Planner
cc: Sang Tran/Owner
Chris Tibaldi/Engineer
Jonathan Chavez/Staff