CITY OF RENTON Ι PERMIT SERVICES
SPECIAL PERMIT REVIEW SUBMITTAL
REQUIREMENTS
SPECIFIC CODE SECTION (S) RELATED TO THIS DOCUMENT
RMC 4-9-220 Special Permit Review Process
RMC 4-8 Permits—General and Appeals
PURPOSE
Recognizing that there are certain uses of property that may be detrimental to the public health, safety, morals, and
general welfare, and not permitted by right in the zone where proposed, depending upon the facts of each particular
case, a limited power to issue permits for such uses is vested in the Hearing Examiner following recommendation by the
Planning Division. (Ordinance 3592, 12-14-1981)
FREE PRE-APPLICATION MEETING
Prior to submitting an application, the applicant should informally discuss the proposed development with the Planning
Division. The Planning Division will provide assistance and detailed information on the City’s requirements and standards.
For further information on this meeting, see the instruction sheet entitled "Pre-Application.”
APPLICATION SCREENING
A Pre-Submittal screening may be required prior to formal Land Use Review. The screening will be performed
electronically via an FTP link that your Project Manager will provide to you. After you upload your submittal documents
the Project Manager will review the submittal materials to ensure that requested revisions or missing items have been
updated and/or corrected. If all required submittal items are provided and complete, unless waived by the Project
Manager, staff will take in the application for official review.
ELECTRONIC FILE STANDARDS
All documents MUST be submitted electronically. Specific file naming conventions for submitted plans are required to
facilitate the electronic plan review process. Failure to adhere to the sample file naming format listed in the Electronic
File Standards may result in a request for resubmittal and/or delay the plan review process, deeming the application
incomplete.
COMPLETE APPLICATION REQUIRED
In order to accept your application, each of the numbered items must be submitted at the same time. Determination
that an application is complete indicates only that the application is ready for review on its merits, not that the City will
make a favorable decision on the application.
APPLICATION SUBMITTAL HOURS
Applications should be submitted to City staff electronically, not in person. Please email or call your assigned Project
Manager to submit your application. If you have any Planning related questions you may reach out to Planning Customer
Service at 425-430-7294 or planningcustomerservice@rentonwa.gov.
TIME FRAME
The average time frame for processing of a Special Permit Review varies from varies from 6 to 12 wee ks, depending on
whether the decision may be made administratively (6 to 8 weeks), by the Hearing Examiner (8 to 12 weeks), or by the
rentonwa.gov/permitservices | planningcustomerservice@rentonwa.gov | 425-430-7294 11/22/2023 Page 2 of 16
SPECIAL PERMIT REVIEW SUBMITTAL REQUIREMENTS
City Council (12 weeks). This time frame assumes no appeals are filed.
ADDITIONAL PERMITS
Additional permits from other agencies may be required. It is the applicant’s responsibility to obtain these other
approvals. Information regarding these other requirements may be found at https://apps.oria.wa.gov/opas/
SOME KEY THINGS TO REMEMBER
1. City Staff or other agencies may request additional information during the review and decision-making process.
2. It is important that the applicant submit the requested material quickly to avoid delays in the process.
3. Any time spent gathering data and/or additional city review period will increase the time required to process the
application.
SUBMITTAL REQUIREMENTS
The submittal checklist is not an exhaustive list of submittal requirements and may be modified in cases where additional
information is required to complete the review of an application. The applicant should contact the assigned Project
Manager if there are any questions regarding submittal requirements.
All Application Materials Required Unless Waived by City Staff.
1. Pre-Application Meeting Summary: If the application was reviewed at a “pre-application meeting.”
2. Waiver Form: A Waiver Form will be provided to you by City Staff during the Pre-Submittal Review. The Waiver
Form should be submitted with the land use application.
3. Land Use Permit Master Application Form: The standardized application form used for the majority of land
use permit applications including, but not limited to, the following:
a. Owner, applicant, and contact person names, addresses and telephone numbers;
b. Notarized signatures of all current property owners;
c. Name of the proposed project;
d. Project/property address;
e. King County Assessor’s tax account number;
f. Existing and proposed land uses;
g. Existing and, if applicable, proposed Comprehensive Plan map designation;
h. Existing and, if applicable, proposed zoning designation;
i. Site area;
j. Estimated project cost
k. Whether or no the project site contains any environmentally sensitive areas; and
l. Property legal description.
Note: The application must have notarized signatures of ALL current property owners listed on the Title Report.
If the property owner is a corporation, the authorized representative must attach proof of signing authority on
behalf of the corporation. The legal description of the property must be attached to the application form.
4. Fees: The application must be accompanied by the required application fee (see Fee Schedule). Please call 425-
430-7294 to verify the exact amount required. Checks should be made out to the City of Renton and cannot be
accepted for over the total fee amount. Credit cards may also be used to pay required application fees. Fees are paid
at Cashier on the 1st Floor City Hall.
rentonwa.gov/permitservices | planningcustomerservice@rentonwa.gov | 425-430-7294 11/22/2023 Page 3 of 16
SPECIAL PERMIT REVIEW SUBMITTAL REQUIREMENTS
5. Environmental Checklist: The standard State of Washing form required under WAC 197-11-742 and 197-11-960.
6. Title Report: A document prepared by a title insurance company documenting the ownership and title of all
interested parties in the plat, subdivision, or dedication and lis ting all encumbrances. In the case of a final plat, the
certificate shall be dated within forty five (45) days prior to the approval of the final plat.
7. Project Narrative: A clear and concise description and summary of the proposed project, including the following:
a. Project name, size and location of site;
b. Zoning designation of the site and adjacent properties;
c. Current use of the site and any existing improvements;
d. Special site features (i.e., wetlands, water bodies, steep slopes);
e. Statement addressing soil type and drainage conditions;
f. Proposed use of the property and scope of the proposed development (i.e., height, square footage, lot
coverage, parking, access, etc.);
g. Proposed off-site improvements (i.e., installation of sidewalks, fire hydrants, sewer main, etc.);
h. Total estimated construction cost and estimated fair market value of the proposed project;
i. Estimated quantities and type of materials involved if any fil l or excavation is proposed;
j. Number, type and size of trees to be removed;
k. Explanation of any land to be dedicated to the City; and
l. For shoreline applications only:
• Name of adjacent water area or wetlands,
• Nature of existing shoreline—describe:
Type of shoreline (i.e. lake, stream, lagoon, march, bog, floodplain, floodway);
Type of beach (i.e. accretion, erosion, high bank-low bank);
Type of material (i.e. sand, gravel, mud, clay, rock, riprap); and
The extent and type of any bulkheading.
• The number and location of structures and/or residential units (existing and potential) which might
have views obstructed as a result of proposed project; and
m. The proposed number, size, and density of the new lots, for subdivision applications only.
8. Construction Mitigation Description: A written narrative addressing each of the following:
a. Proposed construction dates (begin and end dates);
b. Hours and days of operation;
c. Proposed hauling/transportation routes;
d. Measures to be implemented to minimize dust, traffic and transportation impacts, erosion, mud, noise, and
other noxious characteristics;
e. Any special hours proposed for construction or hauling (i.e. weekends, late nights); and
f. Preliminary traffic control plan.
Note: If your project requires the use of cranes, please contact the City’s Airport Manager at 425- 430-7471 to
determine whether Federal Aviation Administration (FAA) notification will be required.
9. Neighborhood Detail Map: Please provide a map, drawn at a scale of one inch equals one hundred feet (1" =
rentonwa.gov/permitservices | planningcustomerservice@rentonwa.gov | 425-430-7294 11/22/2023 Page 4 of 16
SPECIAL PERMIT REVIEW SUBMITTAL REQUIREMENTS
100') or one inch equals two hundred feet (1" = 200') (or other scale approved by the Planning Division Director or
designee). The map shall show the location of the subject site relative to the property boundaries of the surrounding
parcels within approximately one thousand feet (1,000') or approximately two thousand five hundred feet (2,500')
for properties over five (5) acres and identifying the subject site with a darker perimeter line than that of surrounding
properties. The map shall also show the property’s lot lines, existing land uses, building outlines, City boundaries of
the City of Renton (if applicable), north arrow (oriented to the top of the plan sheet), graphic scale used for the map,
and City of Renton (not King County) street names for all streets shown. (Amd. Ord. 4963, 5
-13-2002)
10. Site Plan: A single fully dimensioned plan sheet drawn at a scale of one inch equals twenty feet (1”=20’) (or
another scale approved by the Planning Division Director or designee) clearly indicating the following:
a. Name of proposed project;
b. Date, scale, and north arrow oriented to the top of the plan sheet;
c. Drawing of the subject property with all property lines dimensioned and names of adjacent streets;
d. Widths of all adjacent streets and alleys;
e. The location of all existing public improvements including, but not limited to, curbs, gutters, sidewalks,
median islands, street trees, fire hydrants, utility poles, etc., along the full property frontage;
f. Location and dimensions of existing and proposed structures, parking and loading areas, driveways, existing
trees on and abutting the site, existing or proposed fencing or retaining walls, freestanding signs, easements,
refuse and recycling areas, freestanding liquid fixtures, utility junction boxes, public utility transformers,
storage areas, buffer areas, open spaces, and landscaped areas;
g. The location and dimensions of natural features such as streams, lakes, marshes and wetlands. Include
boundaries of utility, open space, and/or critical area(s) tracts, square footage, and purpose statement of
each tract. Clearly delineate the critical area and buffer boundaries within the tract and indicate a dimension
for buffer width;
h. Ordinary high water mark, existing and proposed, and name of water body if applicable;
i. For wireless communication facilities, indicate type and locations of existing and new plant materials used
to screen facility components and the proposed color(s) for the facility;
j. A legend listing the following must be included on one of the site plan sheets:
• Total square footage of the site,
• Square footage (by floor and overall total) of each individual building and/or use,
• Total square footage of all buildings (footprint of each building),
• Percentage of lot coverage,
• Square footage of all landscaping (total, parking lot, and wildlife habitat),
• Allowable and proposed building height,
• Building setbacks required by Code,
• Proposed building setbacks,
• Parking analysis, including:
Number of stalls required, by use; number of stalls provided, by use,
Size of stalls and angles,
Location and number of handicap stalls, compact, employee, and/or guest parking stalls,
Location and size of curb cuts,
rentonwa.gov/permitservices | planningcustomerservice@rentonwa.gov | 425-430-7294 11/22/2023 Page 5 of 16
SPECIAL PERMIT REVIEW SUBMITTAL REQUIREMENTS
Traffic flow within the parking, loading, and maneuvering areas and ingress and egress,
Location of wheel stops,
Loading space,
Stacking space,
Location and dimensions of bicycle racks, carpool parking spaces, and other facilities designed
to accommodate access to the site,
Square footage interior parking lot landscaping;
k. Footprint of all proposed buildings showing the location of building entrances, window openings, and
landscape features (required for Urban Center Design Overlay District review packet only);
l. Footprint of all abutting and adjacent buildings showing the location of building entrances, window
openings, and landscape features (required for Urban Center Design Overlay District review packet only);
m. For nonconforming use or structure rebuild approval permits: draw on the scaled plan the exact sizes and
locations of existing structures and uses, whether damaged or not; write on the scaled plan the dates these
structures/uses were established; on a separate sheet, identify the subject property, abutting lots and
buildings and list adjacent and abutting land uses.
11. Floor Plans: A basic line drawing plan of the general building layout showing walls, exits, windows, and designated
uses indicating the proposed locations of kitchens, baths and floor drains, bedrooms and living areas, with sufficient
detail for City staff to determine if an oil/water separator or grease interceptor is required and to determine sizing
of side sewer.
12. Landscaping Plan, Conceptual: A fully dimensioned plan, prepared by a landscape architect registered in the State
of Washington, a certified nurseryman, or other similarly qualified professional, drawn at the same scale as the
project site plan (or other scale approved by the Community and Economic Development Administrator), clearly
indicating the following:
a. a. Date, graphic scale, and north arrow;
b. b. Location of proposed buildings, parking areas, access and existing buildings to remain;
c. c. Names and locations of abutting streets and public improvements, including easements;
d. d. Existing and proposed contours at five foot (5') intervals or less;
e. e. Location, size, and purpose of planting areas, including those required in RMC 4-4-070, Landscaping, and
those required in RMC 4-3-090, Shoreline Master Program Regulations;
f. f. Location and height for proposed berming;
g. g. Location and elevations for any proposed landscape-related structures such as arbors, gazebos, fencing,
etc.;
h. h. Location, size, spacing and names of existing and proposed shrubs, trees, ground covers, and decorative
rockery or like landscape improvements in relationship to proposed and existing utilities; and
i. i. The location, size and species of all protected trees on site. Protected trees shall have the approximate drip
line shown (see RMC 4-4-130, Tree Retention and Land Clearing Regulations). (Ord. 5100, 11-1-2004; Ord.
5304, 9-17-2007; Ord. 5633, 10-24-2011; Ord. 5676, 12-3-2012)
13. Tree Retention/Land Clearing (Tree Inventory) Plan: A completed tree retention worksheet accompanied by a
full dimensional plan, drawn by a certified arborist or a licensed landscape architect, based on finished grade, drawn
at the same scale as the project site plan with the northern property line at the top of the sheet, clearly showing the
following:
a. All property boundaries and adjacent streets;
rentonwa.gov/permitservices | planningcustomerservice@rentonwa.gov | 425-430-7294 11/22/2023 Page 6 of 16
SPECIAL PERMIT REVIEW SUBMITTAL REQUIREMENTS
b. Location of all areas proposed to be cleared;
c. Species and sizes of vegetation to be removed, altered or retained and the boundaries and predominant
species of stands of trees consisting of five (5) or more trees. This requirement applies only to trees six inch
(6") caliper and larger, fifty four inches (54") above grade, and the location, size and species of all protected
trees on the site;
d. For trees proposed to be retained, a complete description of each tree’s health, condition, and viability;
e. For trees proposed to be retained, a description of the method(s) used to determine the limits of disturbance
(i.e., critical root zone, root plate diameter, or a case-by-case basis description for individual trees);
f. For trees proposed to be preserved within a tree protection tract, any special instructions for maintenance
(e.g., trimming, ground clearing, root pruning, monitoring, aftercare, etc.);
g. For trees not viable for retention, the reason(s) for removal based on poor health, high risk of failure due to
structure, defects, unavoidable isolation (i.e., high blow down potential), or unsuitability of species, etc., and
for which no reasonable alternative action is possible (pruning, cabling, etc.);
h. A description of the impact of necessary tree removal to the remaining trees, including those in a grove or
on abutting properties;
i. For development applications, a discussion of timing and installation of tree protection measures that must
include fencing and be in accordance with the tree protection standards as outlined in RMC 4-4-130H9,
Protection Measures During Construction;
j. The suggested location and species of supplemental trees to be used when required. The report shall
include planting and maintenance specifications;
k. Future building sites and drip lines of any trees which will overhang/overlap a construction line;
l. Location and dimensions of rights-of-way, utility lines, fire hydrants, street lighting, and easements;
m. Where the drip line of a tree overlaps an area where construction activities will occur, this shall be
indicated on the plan;
n. For allowed activities, including allowed exemptions, modifications, and variances, show all trees proposed
to be removed in priority tree retention areas: slopes twenty five percent (25%) to thirty nine percent (39%),
high or very high landslide hazard areas, and high erosion hazard areas;
o. Show trees to be removed in protected critical areas: wetlands, Shorelines of the State, streams and lakes,
floodways, floodplain slopes forty percent (40%) or greater, very high landslide hazard areas, and critical
habitat if the activity is exempt or allowed by the critical areas regulations in RMC 4-3-050C3, Exemptions –
Critical Areas and Buffers;
p. Show all trees to be retained in critical area buffers; and
In all other areas of the site, trees to be removed may be indicated generally with clearing limit lines except
for protected trees. The location, size, and species of all protected trees on a site shall be shown. The plan
shall also differentiate any approved replacement trees from the protected trees. Replacement trees may be
authorized in accordance with RMC 4-4-130H1e, Replacement Requirements, and the number of
replacement trees shall be determined pursuant to any planned replanting areas in accordance with RMC 4
-4-130H1c, Calculating Tree Retention.
14. Tree Retention Worksheet: Please provide a completed City of Renton tree retention worksheet: https://
edocs.rentonwa.gov/Documents/DocView.aspx?id=8464283&dbid=1&repo=CityofRenton
rentonwa.gov/permitservices | planningcustomerservice@rentonwa.gov | 425-430-7294 11/22/2023 Page 7 of 16
SPECIAL PERMIT REVIEW SUBMITTAL REQUIREMENTS
15. Architectural Elevations: Please provide elevations for each building and each building face (N,S,E,W), of a 24” x
36” fully-dimensioned architectural elevation plan drawn at a scale of 1/4” = 1’ or 1/8” = 1’ (or other size or scale
approved by the Planning Division). The plans must clearly indicate the information required by the “Permits” section
of the currently adopted Uniform Building Code and RCW 19.27 (State Building Code Act, Statewide amendments),
including, but not limited to the following:
a. Existing and proposed ground elevations;
b. Existing average grade level underneath proposed structure;
c. Height of existing and proposed structures showing finished rooftop elevations based upon site elevations
for proposed structures and any existing/abutting structures;
d. Building materials and colors including roof, walls, any wireless communication facilities, and enclosures;
e. Fence or retaining wall materials, colors, and architectural design;
f. Architectural design of on-site lighting fixtures; and
g. Cross-section of roof showing location and height of rooftop equipment (including air conditioners,
compressors, etc.) and proposed screening.
h. Required for the Urban Center Design Overlay District review packet.
• Identify building elevations by street name and orientation, i.e., Burnett Ave. (west) elevation.
• Show the location of rooflines, doors and window openings.
• Indicate typical detailing around doors, windows and balconies indicating finishes, color and reflectivity
of glazing.
• Identify offsets in walls intended to meet the minimum requirements for building modulation
indicating the amount of offset.
• Show on each elevation any roof top elements such as mechanical and elevator penthouses that
protrude above the parapet or penetrate the roof and would be visible from other buildings of the same
height.
• Photographs of proposed materials from manufacturers’ catalogues. A materials board showing actual
materials and colors referenced on the architectural elevations is recommended.
i. Required for shoreline permits:
• Include measurements of the existing and proposed elevations of the stream, river, or lake bottom in
relationship to the proposed structure, if the proposed structure is located fully or partially in, or over,
the water.
• Projects exceeding thirty five feet (35') in height must demonstrate compliance with the height
requirement in RMC 4-3-090D7a
16. Wetlands Delineation Map
17. Wetland Assessment: A wetland assessment includes the following:
a. A description of the project and maps at a scale no smaller than one inch equals two hundred feet (1" =
200') showing the entire parcel of land owned by the applicant and the wetland boundary surveyed by a
qualified surveyor, and pursuant to RMC 4-3-050F2, Plans and Studies Required;
b. A description of the vegetative cover of the wetland and adjacent area including identification of the
dominant plant and animal species;
rentonwa.gov/permitservices | planningcustomerservice@rentonwa.gov | 425-430-7294 11/22/2023 Page 8 of 16
SPECIAL PERMIT REVIEW SUBMITTAL REQUIREMENTS
c. A site plan for the proposed activity at a scale no smaller than one inch equals two hundred feet (1" = 200')
showing the location, width, depth and length of all existing and proposed structures, roads, stormwater
management facilities, sewage treatment and installations within the wetland and its buffer;
d. The exact locations and specifications for all activities associated with site development including the type,
extent and method of operations;
e. Elevations of the site and adjacent lands within the wetland and its buffer at contour intervals of no greater
than five feet (5') or at a contour interval appropriate to the site topography and acceptable to the City;
f. Top view and typical cross-section views of the wetland and its buffer to scale;
g. The purposes of the project;
h. Such other information as may be needed by the City, including but not limited to a study of hazards if
present on site, the effect of any protective measures that might be taken to reduce such hazards; and any
other information deemed necessary to verify compliance with the provisions of this Section. (Ord. 4587, 3-
18-1996; Amd. Ord. 4835, 3-27-2000; Ord. 5137, 4-25-2005; Ord. 5757, 6-1-2015)
Note: Please provide a map and a report if ANY wetlands are located on the subject property or within 100 feet
of the subject property. The wetland report/delineation must be prepared by a qualified professional and include
the information specified in RMC 4-8-120D.23. In addition, if any alteration to the wetland or buffer is proposed,
a wetland mitigation plan is also required. See RMC 4-8-120D.23. for plan content requirements.
18. Wetland Mitigation Plan-Preliminary: A preliminary wetland mitigation plan shall include the following:
a. A site plan demonstrating sufficient area for replacement ratios;
b. Proposed planting scheme for created, restored, and enhanced wetlands;
c. Written report, formatted to eight and one-half inches (8.5") by eleven inches (11"), shall include:
• Identifying direct and indirect impacts of the project to the wetland area and wetland functions,
environmental goals and objectives, and performance standards, and evaluating alternative methods
of developing the property using the following criteria in this order:
Avoiding any disturbances to the wetland or buffer;
Minimizing any wetland or buffer impacts;
Compensating for any wetland or buffer impacts;
Restoring any wetlands or buffer impacted or lost temporarily;
Creating new wetlands and buffers for those lost; and
Enhancing an existing degraded wetland to compensate for lost functions and values, i n addition to
restoring a wetland or creating a wetland.
• Evaluating each of the mitigation plan criteria found in RMC 4-3-050L.
• For projects proposing a reduction in wetland buffer width with enhancement, providing a detailed
analysis of the project’s compliance with each of the following criteria:
The reduced buffer will function at a higher level than the standard buffer;
An enhanced buffer shall never be less than seventy five percent (75%) of the standard width at its
narrowest point; and
The buffer area has less than fifteen percent (15%) slopes and no direct or indirect, short-term or
long-term, adverse impacts to regulated wetlands, as determined by the City, will result from a
regulated activity; and
rentonwa.gov/permitservices | planningcustomerservice@rentonwa.gov | 425-430-7294 11/22/2023 Page 9 of 16
SPECIAL PERMIT REVIEW SUBMITTAL REQUIREMENTS
The proposal shall rely upon a site-specific evaluation and documentation of buffer adequacy based
upon Wetlands in Washington State, Volume 1: A Synthesis of the Science (Ecology Publication No.
05-06-006, March 2005) and Wetlands in Washington State, Volume 2: Managing and Protecting
Wetlands (Ecology Publication No. 04-06-008, April 2005), or similar approaches; and
The proposed buffer standard is based on consideration of the best available science as described
in WAC 365-195-905.
• And, for projects proposing averaging in wetland buffer width with enhancement, providing a detailed
analysis of the project’s compliance with each of the following criteria:
There are existing physical improvements in or near the wetland and buffer; and
That width averaging will not adversely impact the wetland function and values; and
That the total area contained within the wetland buffer after averaging is no less than that
contained within the required standard buffer prior to averaging; and
A site-specific evaluation and documentation of buffer adequacy based upon Wetlands in
Washington State, Volume 1: A Synthesis of the Science (Ecology Publication No. 05-06-006, March 2005)
and Wetlands in Washington State, Volume 2: Managing and Protecting Wetlands (Ecology Publication No.
04-06-008, April 2005), or similar approaches have been conducted. The proposed buffer standard is based
on consideration of the best available science as described in WAC 365-195-905; and
In no instance shall the buffer width be reduced by more than seventy five percent (75%) of the
standard buffer. Greater buffer width reductions require review as a variance pursuant to RMC 4-9-
250B; and
An analysis of the effectiveness of the proposed Buffer Enhancement. (Ord. 4835, 3-27-2000; Ord.
5137, 4-25-2005; Ord. 5757, 6-1-2015)
19. Habitat Data Report that includes:
a. Site Plan: The site plan shall indicate:
• The vegetative cover types reflecting the general boundaries of the different plant communities on the
site;
• The exact locations and specifications for all activities associated with site development including the
type, extent and method of operations;
• Top view and typical cross-section views of critical habitat/wildlife habitat to scale;
• The results of searches of the State Department of Fish and Wildlife’s Natural Heritage and Non-Game
Data System databases;
• The results of searches of the Washington State Department of Fish and Wildlife Priority Habitat and
Species database.
b. Narrative Report: A narrative report shall be prepared to accompany the site plan which describes:
• The layers, diversity and variety of habitat found on the site
• The location of any migration or movement corridors;
• The species typically associated with the cover types, including an identification of any critical wildlife
species that might be expected to be found;
• Identification of any areas that have been previously disturbed or degraded by human activity or
natural processes;
• A summary of existing habitat functions and values, utilizing a habitat evaluation procedure or
methodology approved by the City;
rentonwa.gov/permitservices | planningcustomerservice@rentonwa.gov | 425-430-7294 11/22/2023 Page 10 of 16
SPECIAL PERMIT REVIEW SUBMITTAL REQUIREMENTS
• A summary of proposed habitat alterations and impacts and proposed habitat management program.
Potential impacts may include but are not limited to clearing of vegetation, fragmentation of wildlife
habitat, expected decrease in species diversity or quantity, changes in water quality, increases in human
intrusion, and impacts on wetlands or water resources. (Ord. 4835, 3-27-2000)
20. Flood Hazard Data: Flood hazard data includes:
a. Plans in duplicate drawn to scale showing the nature, location, dimensions, and elevations of the area in
question; existing or proposed structures, fill, storage or materials, drainage facilities, and the location of
the foregoing;
b. Elevation in relation to mean sea level of the lowest floor (including basement) of all structures;
c. Elevation in relation to mean sea level to which any structure has been floodproofed;
d. Certification by a registered professional engineer or architect that the floodproofing methods criteria in
RMC 4-3-050I3c; and for any nonresidential structure meet the floodproofing; and
e. Description of the extent to which watercourse will be altered or relocated as a result of proposed
development.
21. Standard Stream or Lake Study: A report shall be prepared by a qualified biologist and include the following
information:
a. Site Map: Site map(s) indicating, at a scale no smaller than one inch equals twenty feet (1" = 20') (unless
otherwise approved by the Community and Economic Development Administrator):
• The entire parcel of land owned by the applicant, including one hundred feet (100') of the abutting
parcels through which the water body(ies) flow(s);
• The ordinary high water mark (OHWM) determined in the field by a qualified consultant pursuant to
RMC 4-3-050G7, Streams and Lakes, (the OHWM must also be flagged in the field);
• Stream or lake classification, as recorded in the City of Renton’s COR Maps, the City’s online interactive
mapping application available through the City’s website, for the City of Renton Water Class or RMC 4 -
3-090 (if unclassified, see “Supplemental Stream or Lake Study” below);
• Topography of the site and abutting lands in relation to the stream(s) and its/their buffer(s) at contour
intervals of two feet (2') where slopes are less than ten percent (10%), and of five feet (5') where slopes
are ten percent (10%) or greater;
• One hundred (100) year floodplain and floodway boundaries, including one hundred feet (100') of the
abutting parcels through which the water body(ies) flow(s);
• Site drainage patterns, using arrows to indicate the direction of major drainage flow;
• Top view and typical cross-section views of the stream or lake bed, banks, and buffers to scale;
• The vegetative cover of the entire site, including the stream or lake, banks, riparian area, and/or abutting
wetland areas, extending one hundred feet (100') upstream and downstream from the property line.
Include position, species, and size of all trees of at least six inch (6") caliper and larger, fifty four inches
(54") above grade, and the location, size and species of all protected trees on the site that are within one
hundred feet (100') of the OHWM, and the location of measures to protect trees on and abutting the
site;
rentonwa.gov/permitservices | planningcustomerservice@rentonwa.gov | 425-430-7294 11/22/2023 Page 11 of 16
SPECIAL PERMIT REVIEW SUBMITTAL REQUIREMENTS
• The location, width, depth, and length of all existing and proposed structures, roads, stormwater
management facilities, wastewater treatment and installations in relation to the stream/lake and its/
their buffer(s); and
• Location of site access, ingress and egress.
b. Grading Plan: A grading plan prepared in accordance with RMC 4-8-120D7, and showing contour intervals
of two feet (2') where slopes are less than ten percent (10%), and of five feet (5') where slopes are ten
percent (10%) or greater.
c. Stream or Lake Assessment Narrative: A narrative report, formatted to eight and one-half inches (8.5") by
eleven inches (11"), shall be prepared to accompany the site plan and describes:
• The stream or lake classification as recorded in the City of Renton’s COR Maps, the City’s online
interactive mapping application available through the City’s website, for the City of Renton Water Class
or RMC 4-3-090;
• The vegetative cover of the site, including the stream or lake, banks, riparian area, wetland areas, and
flood hazard areas extending one hundred feet (100') upstream and downstream from the property line,
including the impacts of the proposal on the identified vegetation;
• The ecological functions currently provided by the stream/lake and existing riparian area and the impacts
of the proposal on the identified ecological functions;
• Observed or reported fish and wildlife that make use of the area including, but not limited to, salmonids,
mammals, and bird nesting, breeding, and feeding/foraging areas, including the impacts of the proposal
on the identified fish and wildlife;
• Measures to protect trees, as defined in RMC 4-11-200, and vegetation; and
• For shorelines regulated under RMC 4-3-090, Shoreline Master Program Regulations, the study shall
demonstrate if the proposal meets the criteria of no net loss of ecological functions as described in RMC
4-3-090D2. If the proposal requires mitigation for substantial impacts to the existing vegetation buffer
in order to demonstrate no net loss of ecological functions, a supplemental stream or lake study is
required.
Note: Please provide a report containing the information specified in RMC Section 4-8-120D.19. In addition,
if the project involves an unclassified stream, a supplemental stream or lake study is also required. If any
alteration to a water-body or buffer is proposed a supplemental stream or lake study and mitigation plan
are also required.
22. Utilities Plan, Generalized: A plan drawn on twenty two inch by thirty four inch (22" x 34") plan sheets using a
graphic scale of one inch equals twenty feet (1" = 20') (or other scale or size approved by the Planning Division’s
Development Engineering Manager or designee) clearly showing all existing (to remain) and proposed public or
private improvements to be dedicated or sold to the public including, but not limited to: curbs, gutters, sidewalks,
median islands, street trees, fire hydrants, utility poles, refuse areas, signage, fre estanding lighting fixtures, utility
junction boxes, public utility transformers, etc., along the full property frontage. The finished floor elevations for
each floor of proposed and existing (to remain) structures shall be shown. (Amd. Ord. 4835, 3-27-2000)
23. Geotechnical Report: A study prepared in accordance with generally accepted geotechnical practices and
stamped by a professional engineer licensed in the State of Washington which includes soils and slope stability
rentonwa.gov/permitservices | planningcustomerservice@rentonwa.gov | 425-430-7294 11/22/2023 Page 12 of 16
SPECIAL PERMIT REVIEW SUBMITTAL REQUIREMENTS
analysis, boring and test pit logs, and recommendations on slope setbacks, foundation design, retaining wall design,
material selection, and all other pertinent elements. If the evaluation involves geologic evaluations or
interpretations, the report shall be reviewed and approved by a geologist. Further recommendations, additions or
exceptions to the original report based on the plans, site conditions, or other supporting data shall be signed and
sealed by the geotechnical engineer. If the geotechnical engineer who reviews the plans and specifications is not the
same engineer who prepared the geotechnical report, the new engineer shall, in a letter to the City accompanying
the plans and specifications, express his or her agreement or disagreement with the recommendatio ns in the
geotechnical report and state that the plans and specifications conform to his or her recommendations. If the site
contains a geologic hazard regulated by the critical areas regulations, the preparation and content requirements of
RMC 4-8-120D, Table 18 shall also apply. If the site is within a channel migration zone, within shoreline jurisdiction,
the geotechnical report shall also include a geomorphic assessment by a Washington State licensed geologist with
engineering geology or hydrogeology specialty license plus experience in conducting fluvial geomorphic assessments.
24. Traffic Study: A report prepared by a State of Washington licensed engineer containing the elements and
information identified in the City of Renton “Policy Guidelines for Traffic Impact Analysis of New Development” in
sufficient detail to define potential problems related to the proposed development and identify the improvements
necessary to accommodate the development in a safe and efficient manner.
25. Grading Plan: A twenty two inch by thirty four inch (22" x 34") plan drawn by a State of Washington licensed civil
engineer at a scale of one inch to forty feet (1" to 40') (horizontal feet) and one inch to ten feet (1" to 10') (vertical
feet) (or other size plan sheet or scale approved by the Planning Division Development Engineering Manager or
designer) clearly indicating the following:
a. Graphic scale and north arrow;
b. Dimensions of all property lines, easements, and abutting streets;
c. Location and dimension of all on-site structures and the location of any structures within fifteen feet (15')
of the subject property or which may be affected by the proposed work;
d. Accurate existing and proposed contour lines drawn at five foot (5'), or less, intervals showing existing ground
and details of terrain and area drainage to include surrounding off-site contours within one hundred feet
(100') of the site;
e. Location of natural drainage systems, including perennial and intermittent streams, the presence of
bordering vegetation, and floodplains;
f. Setback areas and any areas not to be disturbed, including the location, size and species of all protected trees
on site. Protected trees shall have the approximate drip line shown. The method of tree protection during
grading and construction shall be shown. If grade changes in the vicinity of the protected trees are necessary,
the method of reconciling the drip line with the finished elevation shall be included (see RMC 4- 4-130, Tree
Retention and Land Clearing Regulations);
g. Finished contours drawn at five foot (5') intervals as a result of grading;
h. Proposed drainage channels and related construction with associated underground storm lines sized and
connections shown; and
i. General notes addressing the following (may be listed on the cover sheet):
• Area in square feet of the entire property.
rentonwa.gov/permitservices | planningcustomerservice@rentonwa.gov | 425-430-7294 11/22/2023 Page 13 of 16
SPECIAL PERMIT REVIEW SUBMITTAL REQUIREMENTS
• Area of work in square feet.
• Both the number of tons and cubic yards of soil to be added, removed, or relocated.
• Type and location of fill origin, and destination of any soil to be removed from site.
• Finished floor elevation(s) of all structures, existing and proposed.
26. Affidavit of Installation of Public Information Sign (s): A notarized statement signed by the applicant of
applicant’s representative attesting that the required public information sign(s) has been installed in accordance with
City Code requirements.
27. Biological Assessment/Critical Area Study: Projects with the potential to impact fish (Chinook salmon, bull trout,
steelhead trout), unexpected, new, rare or other endangered species habitat (bald eagles) shall provide a biological
assessment/critical area study. The purpose of this assessment is to determine whether a proposed action is likely
to: (1) adversely affect listed or de-listed species or designated critical habitat; (2) jeopardize the continued existence
of species that are proposed for listing, or unexpected, new or rare species; or (3) adversely modify proposed critical
habitat. A biological assessment/critical area study is a written study that evaluates the proposal, all probable impacts
and risks related to the critical area, and recommends appropriate mitigation measures to adequately protect the
functions and values of the critical area, and preserve anadromous fish and their habitat.
The assessment/study shall be prepared by a person with experience and training in the scientific discipline
appropriate for the relevant critical area in accordance with WAC 365-195-095(4). A qualified professional must have
obtained a B.S. or B.A. or equivalent degree in biology, engineering, environmental studies, fisheries,
geomorphology, biological assessment, or related field, and have at least five (5) years of related work experience.
a. A qualified professional for wetlands must be a professional wetland scientist with at least two (2) years of
full-time work experience as a wetlands professional, including delineating wetlands using the federal
manuals and supplements, preparing wetlands reports, conducting function assessments, and developing
and implementing mitigation plans.
b. A qualified professional for Habitat conservation must have a degree in biology or a related degree and
professional experience related to the subject species.
c. A qualified professional for a geological hazard must be a professional engineer or geologist, licensed in the
state of Washington.
d. A qualified professional for Wellhead Protection Areas means a hydrogeologist, geologist, engineer, or
other scientist with experience in preparing hydrogeologic assessments.
The assessment/study shall use scientifically valid methods and studies in the an alysis of critical area data and field
reconnaissance and reference the source of the material used. Best available science is that scientific information
applicable to the critical area prepared by local state or federal natural agencies or a qualified scientific professional
that is consistent with the criteria established in WAC 395-195-900 through 365-195-925.
The assessment/study shall contain, at a minimum, the following information, as applicable:
a. The name and contact information of the applicant;
b. The dates, names, and qualifications of the persons preparing the assessment/study and documentation of
any fieldwork performed on the site;
c. A description of the proposal and identification of the permits requested;
d. A site plan showing:
• Identified critical areas, buffers and the development proposal with dimensions;
• Topography at two-foot (2') intervals;
rentonwa.gov/permitservices | planningcustomerservice@rentonwa.gov | 425-430-7294 11/22/2023 Page 14 of 16
SPECIAL PERMIT REVIEW SUBMITTAL REQUIREMENTS
• Limits of any areas to be cleared/impacted; and
• A description of the proposed stormwater management plan for the development and consideration of
impacts to drainage alterations;
e. Accurate identification, location, and characterization of critical areas, water bodies, and buffers adjacent
to the proposed project area or potentially impacted by the proposed project;
f. A statement specifying the accuracy of the assessment/study, assumptions used in the assessment/study,
and explaining how best available science has been incorporated;
g. Determination of the degree of hazard and risk from the proposal both on the site and on surrounding
properties;
h. An assessment of the probable cumulative impacts to the critical areas, their buffers and other properties
resulting from the proposal;
i. An evaluation of the project’s compliance with sections 7 and 9 of the Endangered Species Act;
j. A description of reasonable efforts made to apply mitigation sequencing to avoid, minimize, and mitigate
impacts to critical areas;
k. Plans for adequate mitigation to offset any impacts and an explanation of how best management practices
will be used to minimize impacts to critical area; and
l. Recommendations for maintenance, short-term and long-term monitoring, contingency plans and security
requirements.
28. Easements, Existing: A recorded document by the property owner granting one or more privileges to use the
owner’s land to and/or for the use by the public, a corporation or another person or entity. Easements may be
referenced by property deed and are identified in the property title report.
29. Covenants, Existing: The recorded limitation on property which may be set forth in the property deed and/or
identified in a title report.
30. Hazardous Materials Management Statement: A statement which includes:
a. A description of refueling of construction vehicles that will occur on the site and an inventory of hazardous
materials expected to be temporarily stored, dispensed, used, or handled on the site.
b. A description of how the requirements in RMC 4-4-030C7, Construction Activity Standards – Zones 1 and 2,
will be met by the applicant.
31. Letter of Understanding Geologic Risk: Please provide a letter from the applicant, or the owner of the site, stating
that he or she understands and accepts the risk of developing in an unstable area and that he or she will advise, in
writing, any prospective purchasers of the site, or any prospective purchasers of structures or portions of structures
on the site, of the unstable potential of the area.
32. Parking, Lot Coverage, Landscaping A nalysis: A listing of the following information (may also be included on the
first sheet of the site plan):
a. Total square footage of the site;
b. Total square footage of existing area(s) of impervious surfacing;
c. Total square footage of existing natural/undeveloped area;
d. Square footage (by floor and overall total) of each individual building and/or use;
e. Total square footage of the footprints of all buildings;
f. Percentage of lot covered by buildings or structures;
g. Total pavement square footage, both existing pavement to remain plus new pavement proposed to be
installed;
rentonwa.gov/permitservices | planningcustomerservice@rentonwa.gov | 425-430-7294 11/22/2023 Page 15 of 16
SPECIAL PERMIT REVIEW SUBMITTAL REQUIREMENTS
h. Square footage of any on-site wetlands;
i. Parking analysis to include the total number of parking spaces required and provided, number of compact
and “ADA accessible” spaces provided, and parking space dimensions;
j. Square footage of landscaping for each area, for interior parking lot landscaping, and total;
k. Allowable and proposed building height;
l. Building setbacks required by Code; and
m. Proposed building setbacks. (Ord. 4587, 3-18-1996)
33. Electronic Copy: All documents MUST be submitted electronically and meet the City’s current Electronic File
Standards. An FTP link to upload your submittal will be provided to you by your Project Manager.
34. Colored Rendering: A computer-generated exterior color view of the proposed building(s), site, and
landscaping in three (3) dimensional form.
REVIEW PROCESS
In addition to the criteria outlined in the Conditional Use Justification, the City will also consider the following criteria
when evaluating your proposal.
• Lot Coverage: Lot coverage in residential zones shall not exceed fifty percent (50%) of the lot coverage of the zone
in which the proposed use is to be located. Lot coverage in all other zones shall conform to the requirements of
the zone in which the proposed use is to be located.
• Yards: Yards shall conform to the requirements of the zone in which the proposed use is to be located. Additions
to the structure shall not be allowed in any required yard.
• Height: Building and structure heights shall conform to the requirements of the zone in which the proposed use is
to be located. Spires, bell towers, public utility antennas, or similar structures may exceed height requirement
upon approval of a variance. Building heights should be related to surrounding uses in order to allow optimal
sunlight and ventilation, and minimal obstruction of views from adjacent structures.
• Compatibility: The proposed use shall be compatible with the residential scale and character of the neighborhood.
• Parking: Parking under the building structure should be encouraged. Lot coverage may be increased to as much as
seventy five percent (75%) of the lot coverage requirement of the zone in which the proposed use is located if all
parking is provided underground or within the structure.
• Traffic: Traffic and circulation patterns of vehicles and pedestrians relating to the proposed use and surrounding
area shall be reviewed for potential effects on, and to ensure safe movement in, the surrounding area.
• Noise, Glare: Potential noise, light, and glare impacts shall be evaluated based on the location of the proposed use
on the lot and the location of on-site parking areas, outdoor recreational areas, and refuse storage areas.
• Landscaping: Landscaping shall be provided in all areas not occupied by buildings or paving. The hearing Examiner
may require additional landscaping to buffer adjacent properties from potentially adverse effects of the proposed
use.
• Accessory Uses: Accessory uses to conditional uses such as day schools, auditoriums used for social and sport
activities, health centers, convents, preschool facilities, convalescent homes, and others of a similar nature shall be
considered to be separate uses and shall be subject to the provisions of the use district in which they are located.
• Conversions: No existing building or structure shall be converted to a conditional use unless such building or
structure complies, or is brought into compliance, with the provisions of Title 4.
• Public Improvements: The proposed use and location shall be adequately served by, and not impose an undue
burden on, any public improvements, facilities, utilities, and/or services. Approval of a conditional use permit may
be conditioned upon the provision and/or guarantee by the applicant of necessary public improvements, facilities,
utilities, and/or services.
rentonwa.gov/permitservices | planningcustomerservice@rentonwa.gov | 425-430-7294 11/22/2023 Page 16 of 16
SPECIAL PERMIT REVIEW SUBMITTAL REQUIREMENTS
PUBLIC HEARINGS
If a public hearing is required for the Conditional Use Permit, a notice of the hearing will be published at least ten (10)
days prior to the hearing. Notices will also be posted at the project site, and parties of record will receive notices vial
mail. Planning Division staff will issue a report to the Hearing Examiner seven (7) days prior to the hearing. The
Hearing Examiner will normally review the Conditional Use Permit application and issue a final decision within 14 days
of the public hearing. However, for more complex projects, if more than 14 days will be needed, the Examiner will so
indicate t the time of the public hearing. The Hearing Examiner’s decision to approve, conditionally approve, or deny
the site plan will be mailed to the applicant and all parties of record.
APPEAL AND RECONSIDERATION PROCESS FOR DECISIONS
Any person, including the applicant, aggrieved by the granting or denial of an application, may make a written application
for reconsideration to the Reviewing Official within 14 calendar days of the date of the decision. After review of the
request, the Reviewing Official may take whatever action is deemed proper. The Reviewing Official’s written decision on
the reconsideration request will be mailed to all parties of record within 10 days from the date the request was filed. If
any party is still not satisfied after a reconsideration decision has been issued, an appeal may be submitted within 14
days to:
• The Hearing Examiner for Administrative decisions
• The City Council for Hearing Examiner decisions
An appeal may be filed without first requesting reconsideration by the Reviewing Official, however, it must be filed within
14 days of the date when the original decision was issued. See Renton Municipal Code, Section 4-8-110 for further
information on the appeal process and time frames.
RESOURCES
City of Renton Forms
Electronic File Standards
Note: This handout shall not be used as a substitute for codes and regulations. The Applicant is responsible for
compliance with all codes and regulations, whether or not described in this document.