HomeMy WebLinkAboutRFI-292Cornerstone General Contractors 11805 North Creek Pkwy S Suite 115 Bothell, Washington 98011 P: (425) 481-7460 F: (425) 481-7497 Project: 2113 Renton ES #16 Duvall Ave NE Renton, Washington 98059     RFI #292: ROW Trenching for the added communication conduit in CCD#004.1 & Street lighting conduit.   Status Open   To Taylor VanderKley (Hargis Engineers, Inc.)  Ingrida Sanders (Hutteball + Oremus Architecture)  From Jeremiah Tovrea (Sare Electric)   Date Initiated Oct 4, 2022 Due Date Oct 11, 2022 Location Project Stage Course of Construction Cost Impact TBD Schedule Impact TBD Spec Section 26 0543 - Underground Vaults and Raceways Cost Code Drawing Number E1.00 Updated in CCD#004.1 Reference Linked Drawings   Received From Jeremiah Tovrea (Sare Electric)Sub Job Copies To Kyle Cundy (Cornerstone General Contractors), Jason Lickert (Sare Electric), Katie Pond (Hutteball + Oremus Architecture), Ed Thomson (Renton School District)      Activity   Question Question from Jeremiah Tovrea Sare Electric on Thursday, Sep 29, 2022 at 04:39 PM PDT  Per flag note 8 on E1.00 CCD#004.1 the added communications conduit is supposed to be run in the landscape buffer on the Duvall side of the sidewalk.  Street Lighting Note 7 on E1.00 calls to have our pole bases 3' from the edge of the side and 7' from the edge of Duvall Ave.  We prefer to use a common trench for these scopes.  Is it acceptable to run the street lighting and 2" spare communication conduit under the east edge of the sidewalk?  Light pole base and existing utilities block routing on the edge of the landscape buffer.  This will leave a small channel in the direct center of the landscape buffer where trees will be planted.  Attachments streetltg.PNG    Awaiting an Official Response   All Replies Response from Ingrida Sanders Hutteball + Oremus Architecture on Wednesday, Oct 5, 2022 at 07:05 AM PDT  See the response from Electrical Engineer.   Response from Taylor VanderKley Hargis Engineers, Inc. on Tuesday, Oct 4, 2022 at 04:58 PM PDT  FLAG NOTE 8 INDICATES THE REQUIREMENT TO ROUTE WITHIN EXISTING LANDSCAPE BUFFERS ON THE NORTH AND SOUTH ENDS OF THE ROW BEYOND THE SCHOOL'S PARCEL. THE REQUIREMENT IS TO ELIMINATE IMPACTS TO EXISTING HARDSCAPE TO REMAIN. IT IS ACCEPTABLE TO COMBINE THE LIGHTING AND SPARE COMMUNCATION CONDUITS AS INDICATED PENDING APPROVAL FROM THE CITY OF RENTON.  Attachments 2113-Renton_ES_16-292- ROW_Trenching_for_the_added_communication_conduit_in_CCD_004.1_amp_Street_lighting_co_2022-10-04_HEI Review.pdf     Cornerstone General Contractors Page 1 of 1 Printed On: Oct 6, 2022 11:32 AM PDT