Loading...
HomeMy WebLinkAboutQuestions & Answers No. 4Page 1 of 6     RAINIER AVE S CORRIDOR IMPROVEMENTS - PHASE 4 (S 3RD ST TO NW 3RD PL) October 12, 2022 The responses to bidder inquiries, unless incorporated into a formal addendum to the contract, are not  part of the contract and are provided for the bidders’ convenience only. The responses may be  considered along with all other information furnished to prospective bidders for the purpose of bidding  on the project. The use of information provided in the responses o bidder inquires is not to be construed  in any way as a waiver of the provisions nor excuse the contra tor from full compliance with the contract  requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary  response previously given and any such subsequent response of addenda should be taken into  consideration when submitting a bid for the project.  Questions and Answers No. 4   1. Question: On the sanitary sewer plan page 120 shows water & sewer utility clearances, and which  materials to use.  On the below example with the 6” water close to the 8” SS line. Do we use 8”  C900 per note 2 below, or 8” ductile iron per the detail on plan page 120?  Do we use this pipe for  the whole 281 ft run, or just a certain footage before and after the 6” water line?  Or do we still  just use SDR35 PVC for the 281 ft run?    Answer:  Please use C900 PVC for sewer mains less than or equal to 12‐inch that cannot meet  minimum clearance from water mains.  For sewer mains greater than 12‐inch please use DI.  Do not change materials between manholes.  If C900 or DI is needed due to a water main crossing,  it needs to be used the entire length of that run. Sheet 120 “Water & Sewer Utility Clearances”  detail has been updated to reflect this and will be issued with Addendum 4. Utility profiles have  been reviewed for pipe profile clearances and any revised drainage/sewer/water profile sheets  clarifying clearances will be issued with Addendum 4. Please note that one run of 18” SD  Polypropylene will need to be revised to 18” SD DIP per the revised clearance detail, see updated  sheet 82 in Addendum 4.     Page 2 of 6    2. Question: There are discrepancies with the bid form and the quantities shown in plans. Please  reconfirm the quantities for the following bid items below.     Answer:  See table below. Revisions to Schedule D – JUT quantities bid items in previously issued  Addendum 3 were bid items D19, D21, D23, D27, D34, D38, and D41. (These were the bid numbers  in Addendum 3.)    Bid  item  Description  Check count from plans  D‐19 Install Handhole (32"x44")  ‐ PSE  4 ea Confirmed – HH01A, HH02A, HH03A, HH04A  Quantity Updated in issued Addendum 3, Schedule D  D‐21 Install Handhole  (23.25"x32.75") ‐ PSE  3 ea Confirmed – HH09, HH0X, HH0X1   Quantity Updated in Addendum 4, Schedule D   D‐23 Install Three Phase  Transformer (70"x136") –  PSE  4 ea Confirmed ‐ V10, V11A, V12A, V15A  Quantity Updated in issued Addendum 3, Schedule D D‐25 Install Three Phase  Junction Box ‐ PSE  Refer to Appendix F for PSE Plans and Structure Sizing Details  for Sizing. 56”x84”  9 ea Confirmed ‐ J02, J05, J06, J07, J10, J12, J13, J02A, J03A  No Change  D‐27 Install PSE Vault – PSE Refer to Appendix F for PSE Plans and Structure Sizing Details  for Sizing. Pull Vault 70”x136”  4 ea Confirmed ‐ PV02, PV03, PV06A, PV02A  Quantity Updated in issued Addendum 3, Schedule D   D‐34 Install 24"x36" Vault ‐  Comcast  17 ea Confirmed ‐ CV03, CV06, CV07, CV08, CV09, CV10, CV15,  CV16, CV25, CV26, CV28, CV17, CV18, CV19, CV20, CV21, CV22  Quantity Updated in issued Addendum 3, Schedule D   D‐35 Install 24"x24" Pedestal ‐  Comcast  1 ea Confirmed ‐ CV27  No change  D‐37 Install 3048 Handhole ‐  Century Link  2 ea Confirmed ‐ CL01, CL13  No change  D‐38 Install 25‐TA Vault ‐  Century Link  5 ea Confirmed ‐ CL02, CL03, CL10, CL14, CL15  Quantity Updated in issued Addendum 3, Schedule D  D‐40 Install 467‐TA Vault ‐  Century Link  5 ea Confirmed ‐ CL04, CL12, CL16, CL18, CL21  No Change  D‐41 Install 38Y‐612 Base‐ Military Vault ‐ Century  Link  1 ea Confirmed – CL08  Quantity Updated in issued Addendum 3, Schedule D  D‐42 Install 96‐612‐7‐TA Vault ‐  Century Link  1 ea Confirmed ‐ CL08.  No Change  No  Bid  Items  – But  on  Plans  “PSE 3‐P transformer “     (1) sheet 145 ‐ PV02          (1) sheet 146 ‐ PV10          (1) sheet 147 ‐ V15A         Or?  “PSE Pull Vault 70x136”  KPG‐PSOMAS COMMENT:  See Bid Item Above, D‐27 “Install Pull Vault – PSE”    Page 3 of 6    (1) sheet 146 ‐ PV03  (1) sheet 147 ‐ PV06A  (1) sheet 149 ‐ PV02A      3. Question: I'm working on a CIPP quote for this project, but the quantities on the bid form do not  line up with the plans.  On the bid form, item C13 is for 1910 LF of 12" CIPP.  I do not see any 8"  CIPP listed on the bid form.  In the plans, I found 12 segments of CIPP listed ‐ 1 is 12", 424 LF.  The  other 11 segments are 8" for a total of 1935 LF.  Can you please clarify which is correct?     Answer:     8” CIPP  2040 LF    12” CIPP  450 LF  Bid form will be updated to include 8” CIPP and revised quantities for 8” CIPP and 12” CIPP will be  issued with Addendum 4.     4. Question: The below is the spec for the watermain flanged bolts.  Stainless Steel bolts are not A‐ 307 / A‐307 bolts are carbon steel, not stainless steel. Do you want 316 stainless steel (ASTM  F593) flange bolts, or carbon steel (A‐307 grade A) flange bolts?        Answer:  For flanged fittings, the City water utility will accept both carbon steel bolts and nuts (A‐ 307) and stainless steel bolts and nuts (316SS).    5. Question: Bid item A72 is Bioretention Planter with a qty of 800 square feet.  While we would not  create/build (or bid) the bioretention planter, we would supply the bioretention soil media (bid  item A77) since we would be installing plant material in the bioretention areas.      I’ve measured the areas where bioretention soil media is to be installed and I’m coming up with  over 3,000 square feet.  Unless I’m missing something, the 800 square feet for bioretention  planter is too low.  Installing 190 CY of bioretention soil media (A77) at an 18” depth would cover  over 3,400 square feet.     Answer:  Bid item A72 Bioretention Planter measurement shall be per LS. Updated bid proposal  and specs for unit revision to LS will be included in Addendum 4. For measurement and payment,  see special provision sections 7‐10.4 Measurement and 7‐10.5 Payment and Bioretention cell  details sheet 104.      6. Question: In review of addendum 2, plans sheets 251, 253, and 254 were replaced with revised  sheets showing the 4’x6’ tree grates and their locations.  However, there seems to be a conflict as  the one tree grate identified on plan sheet 251 is actually part of a Filtera Unit as defined on plan  sheet 239.  The bid item for the tree grates is A157 for a qty of 3.  When you include the tree grate  that has been incorrectly identified on revised plan sheet 251, you have identified 4 locations for  tree grates.  I have found 3 tree grates in total on plan sheet 241 (1) and 242 (2).   Page 4 of 6      Answer:  3 tree grates total for the project is correct. Sheet 251 will be updated to remove the  tree grate note from the filterra unit. Updated sheet 251 will be included in Addendum 4.       7. Question: I had a question about the Schedule D Scope of work in particular to the 4” PSE Fiber  Conduit sheets 154‐159.  I don’t see that item on the bid schedule anywhere.  I have come up with  right around 2220 L/F of the 4” PSE Fiber.      Answer:  This quantity was originally included in item D17 Install 4” Diameter Conduit – PSE  Power. For clarity the 4” PSE Fiber will be separated out into it’s own new item. Updated Proposal  Schedule D showing this revision will be included in Addendum 4.     8. Question: Bid Items 124 – Curb Ramp Type Perp B, and 127 – Curb Ramp Type Combo – I think the  quantities for these two bid items are switched.  I see 1 ea type Perp B and 4 ea Type Combos.  Please advise.    Answer:  This is correct. Bid item A124 Cement Conc. Curb Ramp, Type Perpendicular B, 1 EA   Bid item A127 Cement Conc. Curb Ramp, Type Combination, 4 EA. Revised bid item quantities to  be included in Addendum 4.    9. Question: Bid Item 129 – Decorative Concrete Finish – (Special Provisions page 250 – top 2  paragraphs) – The special provisions provide a generalized description of the “concrete acid stain”  and “sealer” for the decorative concrete finish item.  To accurately bid this item we need either  the product name or a more complete and specific product specification.  Please provide  additional information.    Answer:  Due to federal funding on the project we are unable to specify a specific product or  brand. Spec section will be updated to provide additional performance spec in Addendum 4.     The updated concrete stain performance spec will read as follows:  Concrete stain shall be a penetrating, semi‐transparent, water‐based stain specifically formulated  to color concrete, or other cement‐based materials, by delivering ultra‐fine pigment to the  concrete surface, for exterior use.  Color of stained concrete surface shall reveal a bluish‐green  color tone.    Concrete stains shall have the following characteristics:  • Low VOC water‐based formulation  • Stain application: pump sprayer, mop, stain/paint roller  • Apply top coat sealer with superior adhesion to stained concrete surfaces, 25% solids, durable  satin acrylic finish that is non‐yellowing and UV resistant.    Physical and Chemical Properties shall include the following:  • Flash Point > 93.3ºC (200ºF) ‐ TAG Closed Cup   • Physical State Liquid   • Solubility < 70%  • Volatiles < 70%   • VOC 0%   Page 5 of 6    • LVP‐VOC 0%   • Specific Gravity / Density ~ 1.11   • pH (± 0.3) 7.5 – 8.5   • Boiling Point >100°C / 212°F   • Molecular Weight (g/mol) Varies    10. Question: Reviewing the plans for the Gateway Wall A & B (Bid Item ‐ A160) on plan Sheet 258,  there is a callout for a "Decorative Metal Sheath" at the end corners of each wall.    Each of the callouts on the elevation views and layout views reference the Decorative Metal  Sheath detail on the same sheet.    Even though the note states custom fit for the sheath, the detail for the sheath does not indicate  the dimensions for the aluminum plate required to fit the sheath at the corner.  At the very least,  there is not enough information to determine how far past the corner in each direction the metal  sheath is to cover on the concrete.  Can this information be provided prior to the bid?    Also, on Sheet 258 there is a note at the elevation view for both walls indicating "decorative  cutouts" on the metal sheath, and to see the detail for information.  The detail for the sheath does  not give any indication as to what the metal cutouts are to be on each, nor the size or quantity.  Is  there any way to preview the art work to get more accurate pricing prior to bid?    Answer:  The decorative metal sheath wraps around the rounded (1’‐6” wide) wall ends which is  approximately 2’‐5” +/‐.  Contractor should still verify on site for a more accurate measurement.  The height of the decorative metal sheath for each wall has a typical dimension 3” from the top  and bottom of the wall but will need to be field verified as well.    There are decorative metal sheaths for each wall end (4 total sheaths for 2 walls – A & B).    Please see images below from previous Rainier Ave project along the corridor for intended  “decorative cutouts” material and layout.  Notice that the top of wall is level and the heights of  the sheaths vary due to the grade change across the span of the walls.  As with any custom  installation like this, we expect the Contractor to submit shop drawings once they field verify the  wall conditions in order to custom fit the decorative metal sheaths.                Page 6 of 6    11. Question: On the sanitary sewer mains that are now C900 PVC, will the 6” side services still be  SDR35(transition to SDR35 at the 8x6 tee)?    Answer:  We are not currently planning for any C900 sewer pipe on the main line. Water service  lines have been raised where needed to provide 1.5’ clearance as part of the plan revisions in  Addendum 4, so the side sewer materials will not need to be determined by the mainline  material.    End of Questions and Answers No. 4