HomeMy WebLinkAboutCity's Request-HEX Extension Request-Grant Ave-Inspection LogINSPECTION WORKSHEET - T AVENUE TOWNHOMES
U16004475Case Number:
Inspection Date:
Inspector:Patrick DeCaro- Primary Inspector
Inspection Status:Scheduled
Inspection Type:ENG - Inspection Log
Case Module:Permit Management
Job Address:1600 Grant Aves
Renton, WA 98055-3608
Parcel Number:2023059052
Checklist Item Passed Comments
Contractor Contact Information No
Inspector Comments No
Created By Created OnNote
10/24/2022. Erosion Control ; There was a Hydraulic/Diesel fuel spill today at Grant Ave Townhomes.
One of the dump trucks going down the North driveway ran over rebar that punctured the tank on the
truck and began leaking. The driver put out absorbent pads and the contractor pushed material to
keep the liquid from leaving the site. The amount spilled was approximately 5 gallons of
diesel/hydraulic fluid. They have scraped off approximately 5 yards of material that they are placing on
plastic, covering with more plastic, and will be removing with a vac truck tomorrow. The
Superintendent has been told numerous times about having the cement concrete workers clean-up
the rebar and debris from the roadways on site, but it has not been done. Also called Nathan at the
shops to let him know and talked to DOE about the spill. Told DOE of the plan to remove the material
and dispose of it and they were fine with that. Contractor continues working on buildings. They will
block the roadway on the North side to prevent vehicles driving over the water line because it does not
have the appropiate cover to protect it.
Patrick DeCaro 10/24/2022
10/21/2022. Erosion Control ; No Issues. Contractor is working on buildings. Also moving stockpiled
dirt around job site. Contractor has tried to block road to unload a machine and have a truck back onto
the site, both with no trafffic control. I have told them this will not happen without certified flaggers and
proper signage. Talked to Super about making sure our water main line has 3' of cover. They wanted
to wait until the foundation next to the line was poured before adding material over the line. I told him
that cannot happen as the trucks and equipment going over the water line could be damaged and
that they need to survey in the cover to make sure it is adequate.
Patrick DeCaro 10/21/2022
10/20/2022. Erosion Control ; No Issues. Contractor is working on buildings. Also moving stockpiled
dirt around job site. Contractor is also covering exposed material on site. Asked them when they were
going to hydroseed the site and they said next Thursday. Told them they are out of compliance for the
wet weather season and to get it done as soon as possible. Also told them they need to survey in the
area in front of Building #1 where the material is only 18" above the water line, so we can make sure
we get the correct cover.
Patrick DeCaro 10/20/2022
10/18/2022. Erosion Control ; No Issues. Contractor is working on buildings. Also moving stockpiled
dirt around job site. Contractor is also starting to working on forming the concrete water meter box on
Building #2, so the protection has been removed from around the meter setter. I told them to make
sure the meter setter is protected at all times.
Patrick DeCaro 10/18/2022
10/13/2022. Erosion Control ; No Issues. Contractor is working on buildings. Also moving stockpiled
dirt around job site. They have pulled off one of the water valve can tops and are working to replace it.
Contractor is also starting to working on forming the concrete water meter box on Building #2, so the
protection has been removed from around the meter setter. I told them to make sure the meter setter
is protected at all times.
Patrick DeCaro 10/13/2022
10/12/2022. Erosion Control ; No Issues. Contractor is working on pouring foundation for building #1.
Also working on buildings. Traffic control looked good.
Patrick DeCaro 10/12/2022
10/11/2022. Erosion Control ; No Issues. Contractor is working on buildings. Still have not completed
erosion control issues.
Patrick DeCaro 10/11/2022
10/10/2022. Erosion Control ; No Issues. Contractor is working on buildings.Patrick DeCaro 10/10/2022
10/06/2022. Erosion Control ; No Issues. Contractor is working on buildings. COR water crew came
on site and removed the 5 water meter setters from the area of Building #1. After removing they called
me to say the water main in that area only has 18" of cover. I called the Superintendent and told they
we need at least 3' of cover over the main.
Patrick DeCaro 10/6/2022
10/05/2022. Erosion Control ; No Issues. Contractor is working on buildings. Told them to stabilize
the site for wet weather season.
Patrick DeCaro 10/5/2022
10/04/2022. Erosion Control ; No Issues. Contractor is working on buildings.Patrick DeCaro 10/4/2022
10/03/2022. Erosion Control ; No Issues. Contractor is working on buildings.Patrick DeCaro 10/3/2022
9/29/2022. Erosion Control ; No Issues. Contractor is working on buildings.Patrick DeCaro 9/29/2022
9/28/2022. Erosion Control ; No Issues. Contractor is working on buildings. Walked job site and
checked all water setters. They are still locked and protected.
Patrick DeCaro 9/28/2022
9/27/2022. Erosion Control ; No Issues. Contractor is working on buildings.Patrick DeCaro 9/27/2022
9/26/2022. Erosion Control ; No Issues. Contractor is working on buildings.Patrick DeCaro 9/26/2022
9/23/2022. Erosion Control ; No Issues. Contractor is working on buildings.Patrick DeCaro 9/23/2022
9/22/2022. Erosion Control ; No Issues. Contractor is working on buildings.Patrick DeCaro 9/22/2022
9/21/2022. Erosion Control ; No Issues. Went to job site this morning to check if water service setters
were locked off and protected. All were locked so I removed the Red Tag. Called contractor to let them
know they could go back to work. They are working on framing for the building foundation.
Patrick DeCaro 9/21/2022
9/20/2022. Erosion Control ; No Issues. Contractor is working on building foundations today. COR
locator called and said someone on site had hooked up a hose to one of the water meter setters and
were stealing water. I arrived on site and they had taken the hose off of the setter, but it was still there
with area all wet. The meter setters for building #8 were not secure and the contractor was building
the foundations around then. I notified the contractor that I was Reg Tagging the job and all work was
to stop. Talked to COR water crew and they are going to place padlocks on all existing water meter
setters so they cannot be accessed. Told contractor when all the setters were locked and the other
meters were secure, I would remove the Red Tag.
Patrick DeCaro 9/20/2022
9/19/2022. Erosion Control ; No Issues. Contractor is pouring cement concrete for the building. Traffic
control looks good. Contractor called and said that 3 of the water services for building #1 (That are
already installed) are going to be in the way of the foundation and need to be removed.
Patrick DeCaro 9/19/2022
9/15/2022. Erosion Control ; No Issues. Contractor is working on buildings. Contractor has cleaned
up the spilling rocks from the construction entrance.
Patrick DeCaro 9/15/2022
9/14/2022. Erosion Control ; No Issues. Contractor is working on buildings. Called contractor and
asked them to clean up the spilling rocks from the construction entrance.
Patrick DeCaro 9/14/2022
9/13/2022. Erosion Control ; No Issues. Contractor is working on buildings. Contractor called and
asked what kind of rock walls should be installed on the top of the project. the plans do not define
what kind. I called Jill Ding (COR) for direction. She said cement concrete blocks or regular rockery
stones work for her, so that is what I told the contractor. Walked the entire site and found everything to
okay.
Patrick DeCaro 9/13/2022
9/12/2022. Erosion Control ; No Issues. Contractor is working on buildings.Patrick DeCaro 9/12/2022
9/6/2022. Erosion Control ; No Issues. Contractor is working on buildings.Patrick DeCaro 9/6/2022
No crewmembers are seen onsite.Joe Nerlfi 9/2/2022
No activity is seen onsite at Grant Avenue.Joe Nerlfi 9/1/2022
The carpenters construct the wood wall forms along the eastside of the plat.Joe Nerlfi 9/1/2022
8/30/2022. Erosion Control ; No Issues. Contractor is working on buildings and grading material.Patrick DeCaro 8/30/2022
8/29/2022. Erosion Control ; No Issues. COR water crew has repaired the water valve between
buildings #4 and #5. The Red Tag has now been removed from the site. Contractor has been
working on grading material and framing buildings.
Patrick DeCaro 8/29/2022
8/26/2022. Erosion Control ; No Issues. Job is still Red Tagged. Contractor is working on buildings.Patrick DeCaro 8/26/2022
8/25/2022. Erosion Control ; No Issues. Job is still Red Tagged. Gave the contractor the option to go
back to work on certain items if they block the access road to the water line blow-off. They have placed
ecology blocks to stop access to the road and are working on fixing the construction entrances.
Patrick DeCaro 8/25/2022
8/24/2022. Erosion Control ; No Issues. Job site is still Red Tagged. They have fixed Items 1-4 and
6-8. COR water crew member checked the water line blow-off and found it to be leaking. He has
called for locates and will schedule the repair when the locates are down. Informed the owner that the
Red Tag will not be removed until the water system is repaired and safe.
1.Building #8- water meter valve has the cement concrete collar around it destroyed.
2.Building #6- (2) of the water service concrete boxes have had the protection knocked down and
are not protected anymore.
3.Top of the Circle- Casting was removed from the structure leaving an open hole fall hazard.
4.Building #5- water service concrete box has had the protection knocked down and are not
protected anymore.
5.Between Buildings #4 and #5- Water blow off has been run over and is bent.
6.Building #4- water service concrete box has had the protection knocked down and are not
protected anymore.
7.Building #3- water service concrete boxes have had the protection knocked down and are not
protected anymore.
8.Building #2- water service concrete box has had the protection knocked down and are not
protected anymore.
Informed Superintendent that when all items were fixed and our water crew has checked that the
blow-off was safe, I would remove the Red Tag.
Patrick DeCaro 8/24/2022
8/23/2022. Erosion Control ; No Issues. Walked the job site today and placed a Red Tag for the
following:
1.Building #8- water meter valve has the cement concrete collar around it destroyed.
2.Building #6- (2) of the water service concrete boxes have had the protection knocked down and
are not protected anymore.
3.Top of the Circle- Casting was removed from the structure leaving an open hole fall hazard.
4.Building #5- water service concrete box has had the protection knocked down and are not
protected anymore.
5.Between Buildings #4 and #5- Water blow off has been run over and is bent.
6.Building #4- water service concrete box has had the protection knocked down and are not
protected anymore.
7.Building #3- water service concrete boxes have had the protection knocked down and are not
protected anymore.
8.Building #2- water service concrete box has had the protection knocked down and are not
protected anymore.
Informed Superintendent that when all items were fixed and our water crew has checked that the
blow-off was safe, I would remove the Red Tag.
Patrick DeCaro 8/23/2022
8/22/2022. Erosion Control ; No Issues. Contractor is working on buildings today. Superintendent
called about not being able to use the construction entrance with the 4" x 8" quarry spalls. (The trucks
can't make it up the hill). I told them they could use 2" x 4" spalls or pave the area.
Patrick DeCaro 8/22/2022
8/18/2022. Erosion Control ; No Issues. Contractor is working on buildings today.Patrick DeCaro 8/18/2022
8/17/2022. Erosion Control ; No Issues. Contractor is working on buildings today.Patrick DeCaro 8/17/2022
8/16/2022. Erosion Control ; No Issues. Contractor is working on buildings today.Patrick DeCaro 8/16/2022
8/15/2022. Erosion Control ; No Issues. Contractor is paving 3 area on Grant Ave that were saw cut
last week. Traffic control looks good.
Patrick DeCaro 8/15/2022
8/11/2022. Erosion Control ; No Issues. Contractor is working on buildings today. They also have a
saw cutter working on Grant Ave Cutting for the asphalt replacement, which is scheduled for Monday.
Traffic control looks good.
Patrick DeCaro 8/11/2022
8/10/2022. Erosion Control ; No Issues. Contractor is working on buildings today.Patrick DeCaro 8/10/2022
8/9/2022. Erosion Control ; No Issues. Did not see contractor working on site today. Red Tag was
pulled at 8:00am this morning.
Patrick DeCaro 8/9/2022
8/3/2022. Erosion Control ; No Issues. Contractor continues working on Red Tag items. They have
completed all but 3 of them. Walked the site with contractor, superintendent, and Building Inspector to
check work.
Patrick DeCaro 8/3/2022
8/2/2022. Erosion Control ; No Issues. Contractor is working on Red Tag items.Patrick DeCaro 8/2/2022
8/1/2022. Erosion Control ; No Issues. Contractor is starting to work on the Red Tag items. 1 Laborer
arrived on site at 11:30am and started installing silt fence around the existing water services
throughout the site for protection.
Patrick DeCaro 8/1/2022
7/29/2022. Erosion Control ; No Issues. Contractor is not working on site today. Red Tag is still in
effect. Owner replied to the e-mail and will start working on Red Tag items Monday.
Patrick DeCaro 7/29/2022
7/28/2022. Erosion Control ; No Issues. Contractor is not working on site today. Red Tag is still in
effect. The e-mail sent to owner about getting a schedule before they come back on site to work has
not arrived yet.
Patrick DeCaro 7/28/2022
7/27/2022. Erosion Control ; No Issues. Contractor is not working on site today. Red Tag is still in
effect. Sent e-mail to owner about getting a schedule before they come back on site to work.
Patrick DeCaro 7/27/2022
7/26/2022. Erosion Control ; No Issues. Contractor is not working on site today. Red Tag is still in
effect.
Patrick DeCaro 7/26/2022
7/25/2022. Erosion Control ; No Issues. Contractor is not working on site today. Red Tag is still in
effect. COR water crew on site working on removing 7 water services and checking the other 29.
Patrick DeCaro 7/25/2022
7/21/2022. Erosion Control ; No Issues. Contractor is not working on site today. red Tag is still in
effect. Walked the site with COR water crew to check upcoming work.
Patrick DeCaro 7/21/2022
7/20/2022. Erosion Control ; No Issues. Contractor is not working on site today. Red Tag still in effect.
Notified owner that the COR water crew will be on site next Tuesday to remove water services.
Patrick DeCaro 7/20/2022
7/15/2022. Erosion Control ; No Issues. Contractor is not working on site today. Red Tag is still in
effect.
Patrick DeCaro 7/15/2022
7/14/2022. Erosion Control ; No Issues. Contractor is not working on site today. Red Tag is still in
effect.
Patrick DeCaro 7/14/2022
7/12/2022. Erosion Control ; Stockpiles on site are not covered and the silt fence throughout site
needs repaired. Contractor is not working on site today. Took pictures of all the things not per COR
standards on site, crafted a letter to the owner explaining what is going to happen before they can
return to work, and sent it to the owner, superintendent, and contractor.
7/13/2022. Erosion Control ; Stockpiles on site are not covered and the silt fence throughout site
needs repaired. Contractor is not working on site today. Took more pictures and walked the site with
a COR water crew worker while he checked the hydrants. Again told the superintendent no one is to
be working on the site. The picture of the "Jumper" on Tuesday shows someone has been illegally
taking water from the system. Today it was gone. A lock was put on the service to insure no more
water can be taken.
Patrick DeCaro 7/13/2022
7/11/2022. Erosion Control ; No Issues. Contractor is not working on site today. Met building
inspector on site and we made a list of the deficiencies that need to be done before the Red Tags are
removed.
Patrick DeCaro 7/11/2022
7/6/2022. Erosion control ; No issues. Contractor is pouring cement concrete for building
foundations. They are backing concrete trucks across Grant ave with no traffic control. I have Red
Tagged the job for safety reasons. My Supervisor and a building inspector allowed them to complete
the pouring of the last 2 trucks then the Red Tag will be enforced.
Patrick DeCaro 7/7/2022
7/6/2022. Erosion control ; No issues. Contractor is excavating for building foundations.Patrick DeCaro 7/6/2022
7/1/2022. Erosion control ; No issues. Contractor is excavating for building foundations.Patrick DeCaro 7/1/2022
6/30/2022. Erosion control ; No issues. Contractor is excavating for building foundations.Patrick DeCaro 6/30/2022
6/29/2022. Erosion control ; No issues. Contractor is excavating for building foundations.Patrick DeCaro 6/29/2022
6/28/2022. Erosion control ; No issues. Contractor is excavating for building foundations.Patrick DeCaro 6/28/2022
6/27/2022. Erosion control ; No issues. Contractor is excavating for building foundations.Patrick DeCaro 6/27/2022
6/23/2022. Erosion control ; No issues. Contractor is excavating for building foundations.Patrick DeCaro 6/23/2022
6/22/2022. Erosion control ; No issues. Contractor is excavating for building foundations.Patrick DeCaro 6/22/2022
6/21/2022. Erosion control ; No issues. Contractor is excavating for building foundations.Patrick DeCaro 6/21/2022
6/16/2022. Erosion control ; No issues. Contractor is excavating for building foundations.Patrick DeCaro 6/16/2022
6/15/2022. Erosion control ; No issues. Contractor is excavating for building foundations.Patrick DeCaro 6/15/2022
6/14/2022. Erosion control ; No issues. Contractor is excavating for building foundations.Patrick DeCaro 6/14/2022
6/13/2022. Erosion control ; No issues. Contractor is installing 33 LF of storm pipe coming from the
existing CB in Grant Ave to CB #14 on site.
Patrick DeCaro 6/13/2022
6/9/2022. Erosion control ; No issues. Contractor started to excavate for the storm pipe install on
Grant Ave. Heavy rain was causing the trench to fall in so they backfilled, covered with a steel sheet,
and will try again another day.
Patrick DeCaro 6/9/2022
6/8/2022. Erosion control ; No issues. Contractor is pumping water from the vault to prepare for
tomorrow when they will be working on storm.
Patrick DeCaro 6/8/2022
6/6/2022. Erosion Control ; No Issues. Building contractor continues working on buildings. No other
work is being done on site.
Patrick DeCaro 6/6/2022
6/3/2022. Erosion Control ; No Issues. Building contractor continues working on buildings. No other
work is being done on site.
Patrick DeCaro 6/3/2022
6/2/2022. Erosion Control ; No Issues. Building contractor continues working on buildings. No other
work is being done on site.
Patrick DeCaro 6/2/2022
6/1/2022. Erosion control ; No issues. Contractor is not working on site today.Patrick DeCaro 6/1/2022
5/31/2022. Erosion control ; No issues. Contractor is not working on site today.Patrick DeCaro 5/31/2022
5/26/2022. Erosion control ; No issues. Contractor has survey on site for the storm line issues in
Grant Ave S. roadway.
Patrick DeCaro 5/26/2022
5/25/2022. Erosion control ; No issues. Contractor is not working on site today.Patrick DeCaro 5/25/2022
5/24/2022. Erosion control ; No issues. Contractor is not working on site today. They have stopped by
to take elevation shots for the storm drainage issues.
Patrick DeCaro 5/24/2022
5/23/2022. Erosion control ; No issues. Contractor is not working on site today.Patrick DeCaro 5/23/2022
5/20/2022. Erosion control ; No issues. Contractor is not working on site today.Patrick DeCaro 5/20/2022
5/19/2022. Erosion control ; No issues. Contractor is not working on site today.Patrick DeCaro 5/19/2022
5/18/2022. Erosion control ; No issues. Contractor is not working on site today.Patrick DeCaro 5/18/2022
5/16/2022. Erosion Control ; No Issues. Building contractor continues working on buildings. No other
work is being done on site.
Patrick DeCaro 5/16/2022
5/12/2022. Erosion control ; Contractor has fixed the erosion control issues I pointed out. Otherwise
contractor is not working on site the rest of today.
Patrick DeCaro 5/12/2022
5/11/2022. Erosion control ; Went to job site and erosion issues have not been fixed yet. Called the
Superintendent and he met me on site so I could show him the issues. He said he will talk to the
contractor about having them fixed. I told him they need to be fixed by tomorrow.
Patrick DeCaro 5/11/2022
5/9/2022. Erosion control ; Called contractor about exposed dirt and silt fence repair on site.
Contractor is not working on site today and erosion issues have not been fixed yet. Called contractor
again about fixing erosion issues, left a message and got no response.
Patrick DeCaro 5/9/2022
5/6/2022. Erosion control ; Called contractor about exposed dirt and silt fence repair on site.
Contractor is not working on site today and erosion issues have not been fixed yet. Called contractor
again about fixing erosion issues.
Patrick DeCaro 5/6/2022
5/5/2022. Erosion control ; Called contractor about exposed dirt and silt fence repair on site.
Contractor is not working on site today and erosion issues have not been fixed yet.
Patrick DeCaro 5/5/2022
5/4/2022. Erosion control ; Called contractor about exposed dirt and silt fence repair on site.
Contractor is not working on site today and erosion issues have not been fixed yet.
Patrick DeCaro 5/4/2022
5/3/2022. Erosion control ; Called contractor about exposed dirt and silt fence repair on site.
Contractor is not working on site today and erosion issues have not been fixed yet.
Patrick DeCaro 5/3/2022
5/2/2022. Erosion control ; Called contractor about exposed dirt and silt fence repair on site.
Contractor is not working on site today.
Patrick DeCaro 5/2/2022
4/26/2022. Erosion control ; No issues. Building contractor continues framing and constructing
buildings on site.
Patrick DeCaro 4/26/2022
4/25/2022. Erosion control ; No issues. Contractor is not working on site today.Patrick DeCaro 4/25/2022
4/22/2022. Erosion control ; No issues. Contractor is not working on site today.Patrick DeCaro 4/22/2022
4/21/2022. Erosion control ; No issues. Building contractor continues framing and constructing
buildings on site. Site contractor started excavating for the storm line to be installed in the existing
catch basin on Grant Ave at the North side of the site. They have broken an existing corrugated metal
storm pipe. Called Nathan (COR Surface Water) to see how he would like it repaired. They have cut
out the bad section and replaced it with new pipe and a collar. Backfilling and covering the roadway
with a steel sheet and cold mix asphalt. Traffic control looks good. The contractor has checked to see
if the new storm pipe to be installed will work with the existing conditions on Grant Ave, which they
have found it will not. Told them to consult with their engineer and come up with a fix.
Patrick DeCaro 4/21/2022
4/14/2022. Erosion control ; No issues. Building contractor continues framing and constructing
buildings on site. Site contractor continues trying to clean the storm system on site and are grading
on site material.
Patrick DeCaro 4/14/2022
4/13/2022. Erosion control ; No issues. Building contractor continues framing and constructing
buildings on site. Site contractor continues trying to clean the storm system on site and have
completed installing another storm pipe run.
Patrick DeCaro 4/13/2022
4/12/2022. Erosion control ; No issues. Building contractor continues framing and constructing
buildings on site. Site contractor continues trying to clean the storm system on site.
Patrick DeCaro 4/12/2022
4/11/2022. Erosion control ; No issues. Building contractor continues framing and constructing
buildings on site. Site contractor continues trying to clean the storm system on site.
Patrick DeCaro 4/11/2022
4/8/2022. Erosion control ; need stock piles covered. Building contractor continues framing and
constructing buildings on site. Site contractor is trying to clean the storm system on site.
Patrick DeCaro 4/8/2022
4/7/2022. Erosion control ; need stock piles covered. Building contractor continues framing and
constructing buildings on site. Site contractor is trying to clean the storm system on site. Called
superintendent about covering stock piles and not using on site water.
Patrick DeCaro 4/7/2022
4/6/2022. Erosion control ; No issues. Contractor continues framing and constructing buildings on
site.
Patrick DeCaro 4/6/2022
4/5/2022. Erosion control ; No issues. Contractor continues framing and constructing buildings on
site.
Patrick DeCaro 4/5/2022
Contractor continues framing and constructing buildings throughout job site.Patrick DeCaro 3/31/2022
Contractor continues framing and constructing buildings throughout job site.Patrick DeCaro 3/30/2022
Contractor continues framing and constructing buildings throughout job site.Patrick DeCaro 3/29/2022
Contractor continues framing and constructing buildings throughout job site.Patrick DeCaro 3/28/2022
Contractor continues framing and constructing buildings throughout job site.Patrick DeCaro 3/25/2022
Contractor continues framing and constructing buildings throughout job site.Patrick DeCaro 3/24/2022
Contractor continues framing and constructing buildings throughout job site.Patrick DeCaro 3/23/2022
Contractor continues framing and constructing buildings throughout job site.Patrick DeCaro 3/22/2022
Contractor continues framing and constructing buildings throughout job site.Patrick DeCaro 3/21/2022
Contractor continues framing and constructing buildings throughout job site.Patrick DeCaro 3/17/2022
Contractor continues framing and constructing buildings throughout job site.Patrick DeCaro 3/16/2022
Contractor continues framing and constructing buildings throughout job site.Patrick DeCaro 3/15/2022
Contractor continues framing and constructing buildings throughout job site. Sent an e-mail to the
owner to see when they will finish the rest of the utility work.
Patrick DeCaro 3/14/2022
Contractor continues framing and constructing buildings throughout job site.Patrick DeCaro 3/11/2022
Contractor continues framing and constructing buildings throughout job site.Patrick DeCaro 3/10/2022
Contractor continues framing and constructing buildings throughout job site. Will be sending an
e-mail to the owner to see when they will finish the rest of the utility work.
Patrick DeCaro 3/9/2022
Contractor continues framing and constructing buildings throughout job site.Patrick DeCaro 3/8/2022
Contractor continues framing buildings throughout job site.Patrick DeCaro 3/7/2022
Contractor continues framing buildings throughout job site.Patrick DeCaro 3/3/2022
Contractor continues framing buildings throughout job site.Patrick DeCaro 3/2/2022
Contractor continues framing buildings throughout job site.Patrick DeCaro 3/1/2022
Contractor continues framing buildings throughout job site.Patrick DeCaro 2/17/2022
Contractor continues framing buildings throughout job site.Patrick DeCaro 2/16/2022
Contractor continues framing buildings throughout job site.Patrick DeCaro 2/15/2022
Contractor continues framing buildings throughout job site.Patrick DeCaro 2/14/2022
Contractor continues framing buildings throughout job site.Patrick DeCaro 2/11/2022
Contractor continues framing buildings throughout job site.Patrick DeCaro 2/10/2022
Contractor continues framing buildings throughout job site.Patrick DeCaro 2/9/2022
Contractor continues framing buildings throughout job site.Patrick DeCaro 2/8/2022
Contractor continues framing buildings throughout job site.Patrick DeCaro 2/7/2022
Contractor continues framing buildings throughout job site.Patrick DeCaro 2/3/2022
Contractor continues framing buildings throughout job site.Patrick DeCaro 2/2/2022
Contractor continues framing buildings throughout job site.Patrick DeCaro 2/1/2022
Contractor continues framing buildings throughout job site.Patrick DeCaro 1/31/2022
1/24/22 - Brianne and Holly Visit Site. Walked the property. Contractor on site building homes at top of
hill. Broken water lid in road at top of circle. Erosion control at entrance need to be cleaned and
improved.
Holly Powers 1/24/2022
Contractor is not working on site today. Informed them that the COR water crew will turn on the new
water system tomorrow. Also told them they need to have hoses and find an area to discharge all the
water.
Patrick DeCaro 1/6/2022
Asked contractor to refresh the cold mix asphalt patch on Grant Ave South, which they did today.
Otherwise no work on site.
Patrick DeCaro 1/5/2022
Did not see contractor working on site today. Rental truck showed up on site to pick up steel sheets.
Told him they can't park in the roadway without traffic control and sent him away.
Patrick DeCaro 1/4/2022
Contractor is removing steel sheets from the roadway, compacting material around the water valves,
installing valve cans, and placing cold mix asphalt on the roadway.
Patrick DeCaro 1/3/2022
Did not see contractor working on site today.Patrick DeCaro 12/22/2021
COR water crew on site to do the (2) water line cut-ins. Completed. Traffic control looks good.
Contractor has poured the cement concrete thrust blocks for the water line. They have also covered
the excavated holes with steel sheets and cold mix asphalt.
Patrick DeCaro 12/21/2021
Contractor has (2) vac trucks on site excavating the South connection point for the new water system.
COR water crew on site to check the excavation and parts for the tie-in. Told site Superintendent they
need to have traffic control on site tomorrow by 7:00am so the water crew can start the tie-in work.
Traffic control today looked good. Excavated holes are covered with steel sheets and cold mix
asphalt.
Patrick DeCaro 12/20/2021
Contractor continues using vac trucks to excavate for the water line tie-in. Traffic control looks good.
Received purity sample results today and they all passed.
Patrick DeCaro 12/17/2021
Contractor has a vac truck on site excavating for the water line on Grant Ave S. for the tie-in. Traffic
control looked good.
Patrick DeCaro 12/16/2021
Contractor has flushed the water line and I took purity samples today that were sent to the lab for
testing. Contractor is also continuing work on placing concrete around the water valves on site. Traffic
control crew was not safe today so I told the Superintendent they were not allow back on site, and if
this crew returned no one would be allowed to work.
Patrick DeCaro 12/15/2021
COR water crew on site to check chlorine residuals. Everything looks good. Contractor is now
flushing the water line system. Traffic control looks good. They are also fixing the silt fence, covering
material stockpiles, and pouring cement concrete around water valve cans.
Patrick DeCaro 12/14/2021
COR water crew on site to chlorinate the new water system. Traffic control looked good. Talked to
Superintendent on site about stockpiles being re-covered, silt fence repair, and water leaving the job
site. Tested water leaving site and it was at 25 NTU. They are addressing the problem.
Patrick DeCaro 12/13/2021
Contractor has tried to pressure test the new water line with the bends they installed. Test has
passed and the City crew will chlorinate the line Monday. Traffic control looks good.
Patrick DeCaro 12/9/2021
Contractor has tried to pressure test the new water line with the bends they installed. Test has failed
again and they said they will try again tomorrow. Traffic control looks good.
Patrick DeCaro 12/8/2021
Contractor has tried to pressure test the new water line with the bends they installed. Test has failed
again and they said they will try again tomorrow. Traffic control looks good.
Patrick DeCaro 12/7/2021
Contractor has tried to pressure test the new water line with the bends they installed. The test lost 10
PSI in 1 1/2 hours. Test has failed. They will try again tomorrow. Traffic control looks good.
Patrick DeCaro 12/6/2021
Contractor is backfilling, compacting, and placing asphalt cold mix over the areas on Grant Ave S. that
were excavated for the new water line. Covering the gas lines with sand. Traffic control looks good.
Patrick DeCaro 12/3/2021
Did not see anyone working on site today.Patrick DeCaro 12/2/2021
Contractor has a vac truck on site excavating for water pipe thrust blocks and have poured them on
both the South and North pipe bends. They are using restraint rods to hold the vertical bends in place.
Traffic control looks good. Steel sheets and cold mix placed over the open trench.
Patrick DeCaro 12/1/2021
Contractor has installed 7 LF of 10" DI water line going into Grant Ave S. today. Traffic control looks
good. Covering the open trenches on roadway with steel sheets and cold mix asphalt.
Patrick DeCaro 11/30/2021
Contractor has installed 17 LF of 10" DI water line going into Grant Ave S. today. PSE Inspector on site
for gas line crossing. Traffic control looks good. Covering the open trenches on roadway with steel
sheets and cold mix asphalt.
Patrick DeCaro 11/29/2021
Contractor continues preparation for the water line for a new pressure test. They have been working
all day for the line to hold pressure. Left site at 2:45pm after contractor said the line will still not hold
pressure. They are planning to try again Friday. Contractor has repaired the plastic but not all the silt
fence for erosion control. Asked again for the erosion issues to be addressed.
Patrick DeCaro 11/10/2021
Contractor continues on site preparation for the water line for a new pressure test. They have been
working all day for the line to hold pressure. Left site at 2:30pm after asking contractor if they were
going to try and get the line to pressure tomorrow. Also asked the contractor to repair the plastic and
silt fence for erosion control.
Patrick DeCaro 11/9/2021
Contractor is on site preparing the water line for a new pressure test.Patrick DeCaro 11/8/2021
Did not see anyone working on site today.Patrick DeCaro 11/5/2021
COR water crew on site to take residual chlorine test on the new water system. When they arrived
they found the top blow-off had no water or pressure. They then moved to the fist inline hydrant and
found the same thing. They said this indicated a leak or someone opened something on the line
between yesterday and today. The test was a failure and I asked the contractor to pressure test the
line again to find the issue.
Patrick DeCaro 11/4/2021
COR water crew on site chlorinating the new water system.Patrick DeCaro 11/3/2021
COR water crew on site to chlorinate the new water line. I made a scheduling mistake for today so the
chlorination will be done tomorrow.
Patrick DeCaro 11/2/2021
Did not see anyone working on site today. Called contractor and let them know that the City water
crew will chlorinate the new water line Tuesday November, 2nd.
Patrick DeCaro 11/1/2021
Did not see anyone working on site today. Sent an e-mail to the owner explaining what needs to
happen before they can chlorinate the new water line.
Patrick DeCaro 10/28/2021
Contractor is re-pouring the cement concrete that goes around 2 of the water valves that were broken.
Other contractor is grading for the garage floor inside the building foundation. Asked for the contractor
to have their material engineer send in writing that the backfill material under the garage footing is
acceptable.
Patrick DeCaro 10/27/2021
Met with contractor on site and measured the bury depth of the meter setters to make sure in is within
COR specifications. All boxes are good.
Patrick DeCaro 10/26/2021
Did not see anyone working on site today when I arrived. Site Superintendent met me on site and we
went and checked every meter setter installed. Half of them were still not within City standard. Also
informed him to fix erosion control issues.
3:30pm- Contractor called and said he had adjusted all meter setters to the correct standard
specifications. Will check tomorrow.
Patrick DeCaro 10/25/2021
Arrived on site at 7:45am and contractor is starting to dig out the meter setter boxes so they can
adjust the meter to the correct height inside the box. COR water manager on site to check progress.
Informs the contractor they will need compression fitting on the back of the setter so the plumber can
connect to it. Site superintendent left at approx. 9:30am to pick some up. Contractor started building
the valve clusters that the COR water crew will use to cut into the city water main. I checked the meter
setter heights at 12:30pm and found that 33 of the 36 were not up to specification. Asked contractor
about it and they said they were not going to adjust them until the plumber shows up to install the tail
piece to the setter. Contractor has left the site at 1:00pm. Cement concrete boxes have still not been
built for some of the meter setters to be put into. (Pictures taken). Saw no plumbers or concrete
workers on site.
Additional contractor on site to work on installing the roadway prism. As of 1:00pm when I left he had
done no work.
Patrick DeCaro 10/19/2021
Contractor continues grading material on site for the roadway prism. Also placing cement concrete
around the water valves to keep them level and at the correct elevation. They still have to remove the
muddy material in the top cul-de-sac and replace with crushed rock for the roadway grading. Walked
the site with the COR water manager and checked all the meter boxes. Most of them are set below
the 15" maximum depth we told them so they need to be fixed. They have also installed Pex pipe
behind the setters and not the standard copper tail piece. Told them that needs to be fixed. They
wanted to try and set up the water valve cut in with the city crews but we told them that can not happen
until everything on site is done.
Patrick DeCaro 10/18/2021
Contractor continues grading material on site for the roadway prism. Other contractor is burying water
service lines and placing them in meter boxes.
Patrick DeCaro 10/13/2021
Contractor is grading material on site for the roadway prism. Other contractor is burying water service
lines and placing them in meter boxes.
Patrick DeCaro 10/12/2021
Contractor continues grading material on site to meet the roadway prism. Other contractor is working
on water services. Walked the site with COR water department and found services will not be set in
the correct area so they will need to be fixed before installation.
Patrick DeCaro 10/11/2021
Contractor is grading material on site to meet the roadway prism.Patrick DeCaro 10/8/2021
Contractor has successfully pressure tested the water line today. Now when they complete the list of
items for water line connection, we can schedule the chlorination.
Patrick DeCaro 10/7/2021
Contractor is trying to pressure test the water line but did not have all the hydrants open so they will try
again tomorrow. Other contractor is trying to clean the muddy material from the job site.
Patrick DeCaro 10/6/2021
Water contractor showed up on site then left because they said they could not work because of rain.
Other contractor has completed the wall installation by the edge of the vault. Owner has a pump truck
arriving on site to pour a building footing. The owner had no traffic control in place so I told them no
trucks can come on site without approved traffic control in place. Special inspector on site to check
footing rebar and concrete. Sweeper on site for street cleaning.
Patrick DeCaro 10/5/2021
Contractor has successfully pushed the poly pig through the water line for a second time. They are
now trying to prep the line for pressure testing. Other contractor is excavating behind a hydrant for the
installation of a wall. I told them that the area will need to be re-compacted because it is to close to
the hydrant thrust block.
Patrick DeCaro 10/4/2021
Contractor has tried to pressure test the water line for their own knowledge and pushed apart one of
the water line joints. The trench was filled with muddy water so I told them they need to push a poly
pig through the line again to make sure it is clean. They have poured 2 thrust blocks behind the
hydrants at the bottom of the job site. Told them again to work on erosion control to cover exposed
stock piles and place permanent winter erosion control throughout the job site.
Patrick DeCaro 9/30/2021
Contractor did not work on site today. They told me concrete was coming between 2 and 3pm today to
pour thrust blocks. I arrive at 2:45pm and no one was here. The concrete truck arrived at 2:45pm and
pulled onto the site. I called the contractor, owner, and superintendent to see what was going on.
They said the pour for today was canceled but no one informed me. I had to direct the concrete truck
safely onto the roadway because no contractor was on site. Justin and I walked the site today and
found a lot of deficiencies for the work being done. Sent the owner, super, and contractor an e-mail
stating everything that needed to be done before they can proceed with the water line installation.
Patrick DeCaro 9/29/2021
Contractor has tried to set up the pressure test of the water line. They have found that the gaskets in 2
of the hydrants were full of rocks and were damaged so the line would not hold pressure. They had to
remove the hydrant thrust blocks to get to the gaskets. They have replaced the gaskets and will
re-pour the thrust blocks tomorrow. They also have saw cutters on site cutting across Grant Ave S. for
the water line installation.
Patrick DeCaro 9/28/2021
Contractor is flushing the water system and preparing the new line for pressure testing. I also asked
them again to cover the stock piles with plastic for erosion control.
Patrick DeCaro 9/22/2021
Contractor has pushed the poly pig through the new water line from the North side of the job site
down the South side of the line. Told the contractor to flush the hydrants and water services before
pressure testing. Again reminded the contractor about the placement of the water services since
there are several building foundations not poured yet.
Patrick DeCaro 9/21/2021
Contractor has pushed the poly pig through the new water line from the top of the job site down the
South side of the line. They have also poured the thrust block for the blow off at the top of the water
line. I informed them that the material behind the thrust block needed to be replaced and certified by a
material tester before they can pressure test the line.
Patrick DeCaro 9/20/2021
9-17-21
Log: Contractor on site continuing to flush new ductile iron water main. Contractor install silt fencing.
Tom Main 9/17/2021
Contractor continues working on the new water line. Other contractor is not working on site today.
Asked Superintendent again to cover stockpiles.
Patrick DeCaro 9/16/2021
Contractor continues working on the new water line. Other contractor is not working on site today.Patrick DeCaro 9/15/2021
Contractor continues working on the new water line. They tries pushing the poly pig to clean the line
but there was to much material in the pipe. Other contractor is not working on site today. Asked site
Superintendent to cover exposed stockpiles for erosion control.
Patrick DeCaro 9/14/2021
Contractor continues working on the new water line. Other contractor is not working on site today.Patrick DeCaro 9/13/2021
Contractor continues working on the new water line. Other contractor is not working on site today.Patrick DeCaro 9/10/2021
Contractor continues working on the new water line. Other contractor is not working on site today.Patrick DeCaro 9/9/2021
Contractor continues working on the new water line. Other contractor is not working on site today.Patrick DeCaro 9/8/2021
Contractor continues working on the new water line. Other contractor is not on site today.Patrick DeCaro 9/7/2021
Contractor is backfilling sewer stubs. Other contractor is working on water system.Patrick DeCaro 9/2/2021
Contractor is backfilling side sewers. Other contractor not working on site today.Patrick DeCaro 9/1/2021
Contractor is backfilling side sewers. Other contractor is installing meter setters on the water
services.
Patrick DeCaro 8/31/2021
Contractor is backfilling the sewer excavated areas. Other contractor is installing the water meter
setters onto the water lines.
Patrick DeCaro 8/30/2021
Contractor continues excavating for the side sewer installations. Other contractor continues working
on the new water line.
Patrick DeCaro 8/26/2021
Contractor continues excavating for the side sewer installations. Other contractor is working on the
new water line. They had a saw cutter on site to cut across the roadway. I asked for an approved traffic
control plan and certified flaggers. They had neither so I told them they have to get the plan before
they can proceed with the roadway work.
Patrick DeCaro 8/25/2021
Contractor is backfilling side sewers and continues working on the water line and services.Patrick DeCaro 8/24/2021
Contractor continues working on replacing the corps for the new water system.Patrick DeCaro 8/23/2021
Jobsite drive-through is performed at Grant Avenue Townhome, the crew continues working to
replace the corps for the water services.
Joe Nerlfi 8/21/2021
Contractor is excavating, removing, and replacing the corps for the water services on the new main
line.
Patrick DeCaro 8/21/2021
Contractor is backfilling sewer stubs. Also started excavating for the water service lines that need to
be replaced.
Patrick DeCaro 8/19/2021
Contractor continues excavating for the side sewer installations on building foundations. Received
confirmation of the new contractors business licenses. They are working on site material to clean up
work site.
Patrick DeCaro 8/18/2021
Contractor is excavating for the side sewer installations on building foundations. Some new
contractor is on site to work on the water. Asked for a COR Business License but have not received
proof of it yet.
Patrick DeCaro 8/17/2021
Contractor is working on placing plastic over stockpiled material for erosion control.Patrick DeCaro 8/16/2021
Contractor is working material on site.Patrick DeCaro 8/13/2021
Contractor is excavating for the side sewer installations on building foundations.Patrick DeCaro 8/12/2021
Contractor is excavating for the side sewer installations on building foundations.Patrick DeCaro 8/11/2021
Contractor is excavating for the side sewer installations on building foundations. Called
Superintendent again about erosion control for the unworked dirt on site.
Patrick DeCaro 8/10/2021
Contractor is backfilling the side sewers that were installed today and excavating for other ones.Patrick DeCaro 8/5/2021
Contractor is backfilling the side sewers that were installed today.Patrick DeCaro 8/4/2021
Contractor is excavating for the side sewer installations on Building 4 foundations. Called
Superintendent and told him they need to address the erosion control for the areas of the site that
have not been worked for more that 7 days.
Patrick DeCaro 8/3/2021
Contractor continues excavating for the side sewer installations on Building 5 foundations.Patrick DeCaro 7/30/2021
Contractor is excavating for the side sewer installations on Building 5 foundations. They tried to call in
for a side sewer inspection but called for a storm by mistake. Scott Mitchell (COR Building Inspector)
on site discussing internal building plumbing to make the side sewer connection.
Patrick DeCaro 7/28/2021
Contractor has excavated to expose the sewer tee and ABS pipe for the plumber so they can install
the side sewer. They have undermined the building foundation at the garage entrance. I called Scott
(COR Building Inspector) and Brianne (COR Plan Reviewer for this project) to notify them of this. They
are going to continue to excavate for the other sewer tees on the rest of the building foundations.
Patrick DeCaro 7/27/2021
Contractor is removing the saw cut garage floors from the building foundations so they can excavate
and expose the sewer tees and black ABS pipe.
Patrick DeCaro 7/26/2021
Contractor is not working on site today.Patrick DeCaro 7/22/2021
Contractor is not doing any work on site today.Patrick DeCaro 7/21/2021
Contractor continues saw cutting the cement concrete garage panels that are in the way of the side
sewer hook ups.
Patrick DeCaro 7/20/2021
Contractor continues saw cutting the cement concrete garage panels that are in the way of the side
sewer hook ups.
Patrick DeCaro 7/19/2021
Contractor is grading material on site for a rock wall that is to be installed.Patrick DeCaro 7/16/2021
Contractor is saw cutting the cement concrete garage panels that are in the way of the side sewer
hook ups.
Patrick DeCaro 7/15/2021
Met on site with super and contractor to discuss sewer hook ups. Contractor is moving material on
site.
Patrick DeCaro 7/14/2021
Met on site with super to discuss sewer hook ups and water meter services.Patrick DeCaro 7/13/2021
Site superintendent has concrete being poured for the water meter walls next to the building
foundations. Checked the concrete truck ticket and it was over 90 minutes so I told the contractor they
couldn't use any more of the mix.
Patrick DeCaro 7/12/2021
Met on site with contractor, engineer, superintendent, and Justin (COR) to discuss side sewer
issues. Walked around the job site and they showed us the problem as they saw it, which was they
thought they did not have enough room to connect the side sewer before the foundation. We saw that
the room is there but the garage floors have already been poured and where the plumber installed
the ABS pipe is not in line with the mainline sewer tees. Justin gave them a few suggestions about
how to fix it and told them to come up with a plan and let us know how they are going to address the
problem.
Patrick DeCaro 7/8/2021
Contractor continues excavating for building foundations.Patrick DeCaro 7/7/2021
Contractor is excavating for building foundations.Patrick DeCaro 7/6/2021
Contractor is moving and grading stockpiled material on site.Patrick DeCaro 7/2/2021
Contractor continues exposing and marking sewer stubs on the new sewer main. They are also
grading down material so the concrete workers have access to the buildings.
Patrick DeCaro 7/1/2021
Contractor is exposing and marking sewer stubs on the new sewer main. Also marked the water
meter walls that needed to be removed because they were sub standard.
Patrick DeCaro 6/30/2021
Concrete contractor on site and was going to hand mix bagged concrete to complete the 2 water
meter walls not done and the 1 that was only half done. Told them they needed to be done all at once
with concrete from a truck. Also checked the 4 completed walls and told them they need to be redone
because of cracking, bottoms blown out, and not square to the building foundations.
Patrick DeCaro 6/29/2021
Contractor is not working on site today.Patrick DeCaro 6/28/2021
Contractor continues having material delivered to the site and are grading around the vault. They have
also installed a manhole for sewer on site.
Patrick DeCaro 6/24/2021
Contractor continues having material delivered to the site and are grading around the vault.Patrick DeCaro 6/23/2021
Contractor continues having material delivered to the site and are grading around the vault.Patrick DeCaro 6/22/2021
Contractor is having material delivered to the site and are grading around the vault.Patrick DeCaro 6/21/2021
Contractor is backfilling around the styrofoam on the vault.Patrick DeCaro 6/17/2021
Contractor has had more styrofoam delivered to the site which they are placing on top of the vault.Patrick DeCaro 6/16/2021
Contractor has had more styrofoam delivered to the site which they are placing on top of the vault.Patrick DeCaro 6/15/2021
Went to site today and contractor said they were not working because the material is to wet from the
weekend rain.
Patrick DeCaro 6/14/2021
Contractor is working on where the water services will be going on site.Patrick DeCaro 6/10/2021
Contractor is checking water service and sewer clean out locations compared to the update plans.Patrick DeCaro 6/9/2021
Contractor is grading material for the block wall on site.Patrick DeCaro 6/8/2021
Contractor is having material delivered to the site today, grading, and compacting.Patrick DeCaro 6/3/2021
Contractor is having material delivered to the site today, grading, and compacting.Patrick DeCaro 6/2/2021
Contractor is having material delivered to the site today.Patrick DeCaro 6/1/2021
Contractor is not working on site today.Patrick DeCaro 5/27/2021
Contractor is grading and compacting material on site. They have set some styro foam on top of the
vault per the plans but checking the elevations it is not enough. Talked to Brianne (COR) and she told
me to let them know we will not accept any work on the vault until out Building Inspector and a
Structural Engineer buy off on it.
Patrick DeCaro 5/25/2021
Contractor is grading and compacting material on site.Patrick DeCaro 5/24/2021
Contractor is grading and compacting material on site.Patrick DeCaro 5/21/2021
Contractor is grading and compacting material on site.Patrick DeCaro 5/20/2021
Contractor is grading and compacting material on site.Patrick DeCaro 5/19/2021
Contractor is grading and compacting material on site.Patrick DeCaro 5/18/2021
Contractor is grading and compacting material on site.Patrick DeCaro 5/17/2021
Time did not allow for a site visit today.Patrick DeCaro 5/13/2021
Contractor continues working to install storm pipe out of the vault.Patrick DeCaro 5/12/2021
5/10/21- Contractor is working on pacing crushed rock on top of the storm vault.
5/11/21- Contractor continues on the storm vault.
Patrick DeCaro 5/11/2021
Contractor has a core driller on site cutting a hole in the storm vault so they can install storm pipe.Patrick DeCaro 5/7/2021
Did not see anyone working on site today.Patrick DeCaro 5/6/2021
Contractor is working on excavating around the vault to install a storm pipe.Patrick DeCaro 5/5/2021
Contractor is grading material around the vault.Patrick DeCaro 5/3/2021
Contractor is installing a storm structure and storm pipe at the North construction entrance of the job
site.
Patrick DeCaro 4/29/2021
Contractor continues installing storm pipe on both sides of the property leading to the roadway.Patrick DeCaro 4/28/2021
Contractor is installing storm pipe on both sides of the property leading to the roadway.Patrick DeCaro 4/27/2021
Contractor is installing storm pipe on both sides of the property leading to the roadway.Patrick DeCaro 4/26/2021
Contractor is installing storm pipe on both sides of the property leading to the roadway.Patrick DeCaro 4/23/2021
Contractor is installing storm pipe on both sides of the property leading to the roadway. Asked them
to freshen up the cold mix asphalt patches from their pot holing on Grant Ave.
Patrick DeCaro 4/22/2021
Contractor is installing a storm pipe from the vault to a catch basin. Also backfilling and compacting
around the storm vault.
Patrick DeCaro 4/21/2021
Contractor has a core driller cutting a hole in the storm vault. They have also started to install a Type 2
storm catch basin.
Patrick DeCaro 4/20/2021
4-13-21
Log: contactor on site continuing to pump down storm water vault.
Tom Main 4/13/2021
4-12-21
Log: contractor on site this shift. i spoke with lan reviewer Brianne and she indicated they could go
back to work. The contractor is pumping out the storm water vault out into the power easement to the
north. Contractor is installing a second construction entrance on the nw corner of project. I requested
the contractor get all silt fence repaired where necessary. Grass has started growing over a large
portion of the project limiting the need for straw.
Tom Main 4/12/2021
Did not see anyone working on site today.Patrick DeCaro 4/6/2021
Did not see anyone working on site today.Patrick DeCaro 4/1/2021
Did not see anyone working on site today.Patrick DeCaro 3/31/2021
Did not see anyone working on site today.Patrick DeCaro 3/30/2021
Did not see anyone working on site today.Patrick DeCaro 3/29/2021
Did not see anyone working on site today.Patrick DeCaro 3/24/2021
Did not see anyone working on site today.Patrick DeCaro 3/23/2021
Did not see anyone working on site today.Patrick DeCaro 3/22/2021
Did not see anyone working on site today.Patrick DeCaro 3/18/2021
Did not see anyone working on site today.Patrick DeCaro 3/17/2021
Did not see anyone working on site today.Patrick DeCaro 3/16/2021
Did not see anyone working on site today. Met on site with contractor to discuss installation of water
meters. Contractor will discuss problem with engineer.
Patrick DeCaro 3/15/2021
Did not see anyone working on site today.Patrick DeCaro 3/12/2021
Contractor has started installing the water meter setters on site.Patrick DeCaro 3/11/2021
Did not see anyone working on site today.Patrick DeCaro 3/10/2021
Did not see anyone working on site today.Patrick DeCaro 3/9/2021
Did not see anyone working on site today.Patrick DeCaro 3/8/2021
Did not see anyone working on site today.Patrick DeCaro 3/4/2021
Met contractor and Geo-tech engineer on site to test 4 locations for compaction behind thrust blocks
for the water line. Excavated down and the areas were tested. All passed. Contractor then backfilled
and compacted the areas.
Patrick DeCaro 3/3/2021
Did not see anyone working on site today. Plastic has been repaired for erosion control.Patrick DeCaro 3/2/2021
Did not see anyone working on site today. Met on site with owner to discuss water line installation.
Asked them to do the erosion control repair that I have been asking for for a week.
Patrick DeCaro 3/1/2021
Did not see anyone working on site today. Contractor has still not repaired the erosion control issues
I called about. Tried calling again and got no answer.
Patrick DeCaro 2/26/2021
Did not see anyone working on site today. Contractor has still not repaired the erosion control issues
I called about. Tried calling again and got no answer.
Patrick DeCaro 2/25/2021
Time did not allow for a site visit today.Patrick DeCaro 2/24/2021
Did not see anyone working on site today. Called contractor to fix plastic that is covering stockpiles for
erosion control.
Patrick DeCaro 2/22/2021
Did not see anyone working on site today.Patrick DeCaro 2/12/2021
Did not see anyone working on site today.Patrick DeCaro 2/11/2021
Did not see anyone working on site today.Patrick DeCaro 2/10/2021
Did not see anyone working on site today.Patrick DeCaro 2/9/2021
Did not see anyone working on site today.Patrick DeCaro 2/8/2021
Did not see anyone working on site today.Patrick DeCaro 2/4/2021
Did not see anyone working on site today.Patrick DeCaro 2/3/2021
Did not see anyone working on site today.Patrick DeCaro 2/2/2021
Did not see anyone working on site today.Patrick DeCaro 2/1/2021
Contractor is on site with a materials tester to check the compaction of the soil behind the water line
thrust blocks. I told the contractor it needed to be checked right behind the blocks and he said the soil
engineer told him to just dig down about 1 foot and check there. They did 1 test when I was there by
Catch Basin #9, which I don't know how close it is to the thrust block. (Picture taken). The tester said it
was 17% moisture and numbers of 114. He said that would make the test to low on compaction and
to high on moisture.
Patrick DeCaro 1/29/2021
Did not see anyone working on site today. Erosion control issue I asked about was fixed when I drove
past the site today.
Patrick DeCaro 1/28/2021
Did not see anyone working on site today. Called contractor about erosion control issue that I brought
up last week and they came and fixed it today. Met on site with owner representative to discuss water
line installation and on site material testing. Talked to owner rep and material testing company about
needing test results for placed material behind thrust blocks for the water line. Told them we need
passing results before any testing can be done on the water line.
Patrick DeCaro 1/27/2021
Did not see contractor working on site today. Erosion control repair of the silt fence I asked for last
week has not been done yet.
Patrick DeCaro 1/21/2021
Did not see anyone working on site today.Patrick DeCaro 1/20/2021
Did not see contractor working on site today. Erosion control repair of the silt fence I asked for last
week has not been done yet.
Patrick DeCaro 1/19/2021
Did not see contractor working on site today.Patrick DeCaro 1/15/2021
Contractor has fixed most of the erosion control issues on site. I called and told them there are a few
more issues to repair and they said they will do it tomorrow.
Patrick DeCaro 1/14/2021
Did not see contractor working on site today. Called contractor and asked them to fix the erosion
control issues on the site from last nights wind storm.
Patrick DeCaro 1/13/2021
Did not see contractor working on site today. Erosion control looked good.Patrick DeCaro 1/12/2021
Did not see contractor working on site today. Pot holes have been filled with cold mix asphalt as
requested.
Patrick DeCaro 1/11/2021
Did not see contractor working on site today. Pot holes have not been repaired yet. Called contractor
and they said they would fix them tomorrow morning.
Patrick DeCaro 1/7/2021
Did not see contractor working on site today.Patrick DeCaro 1/6/2021
Did not see contractor working on site today. Called contractor and asked them to repair the pot hole
cold mix patches that are sinking on Grant Ave.
Patrick DeCaro 1/5/2021
Did not see contractor working on site today.Patrick DeCaro 1/4/2021
Did not see contractor working on site today.Patrick DeCaro 12/31/2020
Did not see contractor working on site today. Erosion control looks good.Patrick DeCaro 12/30/2020
Did not see contractor working on site today.Patrick DeCaro 12/29/2020
Did not see contractor working on site today.Patrick DeCaro 12/28/2020
Did not see contractor working on site today.Patrick DeCaro 12/18/2020
Did not see contractor working on site today.Patrick DeCaro 12/17/2020
Did not see contractor working on site today.Patrick DeCaro 12/16/2020
Did not see contractor working on site today.Patrick DeCaro 12/15/2020
Did not see contractor working on site today. Pot holes in roadway are sinking so I told the contractor
to add cold mix asphalt to repair them.
Patrick DeCaro 12/14/2020
Did not see contractor working on site today.Patrick DeCaro 12/9/2020
Contractor is using a vac truck to pot hole for underground utilities on Grant Ave. Traffic control looked
good.
Patrick DeCaro 12/8/2020
Did not see contractor working on site today.Patrick DeCaro 12/7/2020
Did not see contractor working on site today.Patrick DeCaro 12/4/2020
Did not see contractor working on site today.Patrick DeCaro 12/3/2020
Did not see contractor working on site today.Patrick DeCaro 12/2/2020
Met on site with COR Water Manager and contractor to discuss water line tie-in to the job site.
Contractor is working on storm structure.
Patrick DeCaro 12/1/2020
Did not see contractor working on site today.Patrick DeCaro 11/25/2020
Did not see contractor working on site today.Patrick DeCaro 11/24/2020
Did not see contractor working on site today. Truck driver on site removing fencing.Patrick DeCaro 11/23/2020
Did not see contractor working on site today.Patrick DeCaro 11/20/2020
Did not see contractor working on site today. Truck driver on site removing excavator.Patrick DeCaro 11/19/2020
Did not see contractor working on site today.Patrick DeCaro 11/18/2020
Contractor is placing straw and plastic for erosion control throughout the job site. Also having truck
delivering material to place on the South side of the vault to stabilize the construction entrance.
(Picture). Flatbed truck and trailer showed up to remove a machine but told them they could not load
because they had no flaggers.
Patrick DeCaro 11/17/2020
7:45am- Contractor not on site. Called contractor to tell them we still do not have compaction test
results so they can't pour the water line thrust blocks. 8:30am- 2 laborers arrive on site to work on
erosion control. 9:15am- Solo truck brings quarry spalls that the contractor is using to rebuild and
stabilize the construction entrance. 10:15am- Gary and 1 laborer arrive on site. There is dirty water
leaving the site that I told them to address ASAP. Laborers are trying to get the thrust block holes
ready for cement concrete. 10:50am- Called Mr. Singh and left a message about getting the
compaction reports. Truck with straw arrives on site. Also told the Owners Rep on site about the
compaction reports. 11:15am- 1 laborer arrives on site. 12:00pm- Talked to Gary and explained they
can pour the water main thrust blocks today at their own risk. We will not let them put an pressure on
the new water line (Push the pig, pressure test), until we have the engineers stamped acceptable
compaction test results. 12:30pm- Contractor is placing material on the South side of the vault next to
the construction entrance. They are backfilling to stabilize the open area between the vault and
construction entrance. 1:15pm- Contractor continues installing material on the South side of the vault.
They are also placing straw around the job site for erosion control. 2:00pm- Concrete arrives on site
and the contractor pours thrust blocks for the water line. (Pictures). 3:00pm- Contractor continues
installing straw for erosion throughout the job site. 3:30pm- Contractor has left the site for the day.
Patrick DeCaro 11/16/2020
7:30am- 1 operator and 1 laborer arrive on site. 8:15am- Gary and another laborer arrive on site. They
have started to excavate for the water line installation on the North side. 8:45am- Another laborer
arrives on site and starts to work on the blow-off and air vacuum for the water line. Truck and trailer
arrive on site to remove scaffolding but no flaggers are on site. Owner rep asks if they can just back it
onto the site and I tell him no. 10:15am- Contractor continues installing water line on the North side of
the project. Owner rep has the truck and trailer on the shoulder of the road with 3 laborers hand
loading the scaffolding onto it. 10:30am- 1 Certified flagger has shown up on site, still waiting for the
2nd. Told Gary we need the material test compaction results before they pour the thrust blocks and
pressure test the water main. He also said the material tester will be on site today. Also the sweeper
will be here by the end of the day. Sent Mr. Singh (Owner) an e-mail saying we are still waiting for the
compaction test results. 11:00am- 2nd flagger shows up but does no have a Certified flagger card
with them, tell him he can't flag here today. Contractor continues installing water main, blow-off
assembly, and air vacuum. 12:30pm- Truck and trailer have been loaded and left the site. Contractor
continues working on the water main installation. Still no material tester on site. 1:45pm- Contractor
has completed the water main install to the right of way on the North side of the project. Backfilled
except for the thrust block locations. Now working on installing a hydrant on the North side main.
2:15pm- Mr. Singh on site and I remind him that we still have no compaction reports for the job site.
Gary says they want to pour the concrete thrust blocks Monday. I remind him we have no compaction
reports and the blocks need to go against 95% compacted material. Tell him they can't backfill
around the blocks until Tuesday and any erosion control they disturb will need to be replaced.
3:15pm- Hydrant on the North side of project is installed. Still no material tester on site. 4:00pm-
Contractor has left the site for the day. Still never saw a materials tester or sweeper.
Patrick DeCaro 11/12/2020
7:30am- 1 operator and 1 laborer arrive on site. Operator has started to move the Styrofoam blocks
into a pile on the vault using the excavator. 8:00am- Another laborer and a dump truck arrive on site.
Truck is dropping on backfill material. 8:15am- Core driller and Gary arrive on site. 9:00am- Another 2
laborers arrive on site. Contractor is moving material away from the North side of the vault so the core
drilling can work. He is going to widen the storm pipe access hole in the vault. 9:15am- Owner has 2
laborers on site to stack the styrofoam blocks on top of the vault. Contractor continues working with
the core driller and has half his crew starting to install the water line blow off and vacuum assembly.
10:15am- Core drilling continues on the vault. 12:15pm- Core driller continues working on the vault.
Crew working on the water line has had to stop because of lack of parts. They are now setting CB #8.
Contractor is also backfilling the South side of the vault and compacting with a vibratory roller. Ask
Gary and he said the material tester would be on site today. He also said a sweeper truck would be
on site later. Laborers continue stacking styrofoam on the vault. 1:15pm- Core driller has completed
cut through the vault. (Pictures). He told me he cut through 6+/- pieces of rebar when making the hole.
Contractor is installing storm pipe from CB#8 to the new hole in the vault. Sent an e-mail to Scott
Mitchell (COR Building Inspector) with pictures about them cutting through the rebar in the vault.
2:30pm- Contractor has completed installing the 12" storm pipe from CB #8 to the vault. 3:15pm-
Contractor is backfilling and compacting on the North side of the vault which includes the new storm
line that was just installed. Still no material tester or sweeper truck on site. 4:30pm- Still no material
tester or sweeper truck on site. Roadway has track out from the job site. Left the site for the day.
Patrick DeCaro 11/11/2020
8:00am- Contractor arrives on site with Gary, 1 operator, and 1 laborer. They are moving on site
material so they can work on the storm and using a roller for compaction. No flaggers are on site.
9:00am- Contractor continues same work. 11:00am- Contractor continues same work. 2 flaggers
arrive on site. I check and 1 has an expired card and the other one does not have his card with him. A
truck shows up with foam for the vault but I tell him he can't unload because both flaggers credentials
are no good. The truck leaves the area and parks off site. 11:30am- Owners Rep is trying to get more
flaggers. Truck driver told me he has given the Rep 30 minutes then he will leave. 12:15pm- 2
Certified flaggers arrive on site and will use a single lane closure so the contractor can unload the
truck. Contractor has dug down on the North side of the vault for the storm install and found that the
vault opening will not work with the storm pipe. They are also pumping ground water from the
excavated hole. Called Building inspector Scott Mitchell to let him know. 1:00pm- Contractor is
unloading the Styrofoam for the vault from the truck using an excavator. (Video). 2:00pm- Completed
unloading the truck and the flaggers have left the site. Styrofoam is in a pile on the front edge of the
job site. (Pictures). 2:15pm- Gary just called and said they will have a core driller tomorrow morning to
cut into the vault for the storm pipe opening. He said there is nothing else they can do today so they
have left the site. 2:45pm- Scott Mitchell arrives on site to see the area they are core drilling tomorrow.
He tells me to look and make sure they do not cut into the rebar of the vault. 3:15pm- Sweeper arrives
on site and is cleaning the roadway. 3:45pm- Sweeper is gone and have left the job site for the day.
Patrick DeCaro 11/10/2020
7:45am-Contractor arrives on site. There is 1 operator and 1 laborer. I call Mr. Singh (Site Owner) and
inform him we still do not have any compaction tests for the vault backfill. 8:00am- Flaggers arrive on
site. Only 1 of them has a Certified Flagging card so I tell the other they can't work until they produce a
valid card. COR Locator on site painting out underground utilities. 8:15am- Trucks start arriving and
are dropping the material on site because of the flagging issue. Another laborer and Gary arrives on
site. 9:00am- Contractor is moving on site material down to the East side of the vault. 9:30am- 2nd
Flagger arrives on site and he is certified. Gary just said we were correct and the plastic that was
buried Saturday needs to be removed. They will did that out and backfill today. I have to leave site for
other inspections at this time but will return. 1:30pm- Return to site and contractor is placing quarry
spalls on the South side of the vault. Their roller has been broken down all day so they can't place
and compact any material today. Asked Gary if the materials tester was on site and took some shots.
He said the tester took some shots on the North side that is approx. 8-10 feet deep, and some
surface shots at a few other places around the vault. He said he also took material to come up with a
proctor for the test. Looks like a sweeper has made a pass throughout the job site. 2:30pm-
Contractor continues installing quarry spalls on the South side of the vault with 1 operator and 1
laborer. 3:00pm- Sweeper on site cleaning the roadway. 3:30pm- Mechanic on site to work on roller,
no one else is working. 4:00pm- Roller is repaired and contractor is compacting material on the West
side of the vault. 4:20pm- Contractor has left the job site for the day.
Patrick DeCaro 11/9/2020
8:30am- Contractor and Certified flaggers arrive on site. Flaggers ask for "Flaggers Ahead" sign
which is not on site and said they will not flag until one is set up. Contractor sends someone to go get
one. There is Gary, 1 operator, and 2 laborers on site. 9:15am- Contractor is moving material around
the North side of the vault. 10:00am- Laborer returns with flagging sign. Trucks start coming in and
delivering material that is being placed on the West side of the vault. Compacting with a vibratory
roller. Asked if materials tester would be coming out and they said yes. No material tester on site.
Contractor told me the materials tester never showed up yesterday and he did "Virtual Testing" by
watching on camera the procedures used for compaction. 12:00pm- Contractor continues to place
material on the West side of the vault, using a vibratory roller for compaction. Still no material tester
on site. Asked them to remove the plastic erosion control sheets on the West side of the vault that is
starting to get buried. Gary said the materials engineer told him it was ok to bury because it would act
as a vapor barrier. (Picture taken). 1:00pm- Contractor has now moved to the North side of the vault to
place material. Compacting with a vibratory roller. Still no material tester on site. 2:30pm- Contractor
continues placing and compacting material on both the North and West sides of the vault. Last truck
of the day just left. Asked again about the materials tester and they said he is on the way. 3:15pm-
Contractor has called the tester and he is not coming today. Sweeper has not shown up on site yet so
I am waiting to see when they will arrive. Contractor has left the site for the day. 3:30pm- Mr. Singh on
site and I tell him I am waiting until 4:00pm to see if the sweeper will show up. He tells me I need to
work with him because the roadway is not that bad. He tells me if they do not show up today they will
be here Monday. 4:00pm- Sweeper did not show up on site. (Picture).
Patrick DeCaro 11/7/2020
7:45am- 1 laborer on site unloading footing drain pipe. Water proof contractor on site unloading and
starting to install the remainder of the material to the vault. 1st truck and trailer shows up and stops in
front of site. I told him to leave because no traffic control has been set up yet. 8:30am- Trucks
continue to show up on site, still no flaggers. Gary shows up and sends 2 of his workers to flag. I ask
them for Certified Flaggers cards, they say they don't have them, so I tell them they can't flag the traffic.
Issue a Stop Work Order on the site for traffic control and safety, also saying we need a meeting on
site to discuss solutions. Talk to Justin and Bri, it is decided that we have a defined game plan for
staging and trucking before materials can continue being brought to the site. Let them start back
working on site only. No materials tester on site yet. They have Gary, 1 operator, and 4 laborers
working on site. Water proof contractor continues installing on the vault. 10:45am- Sweeper arrives
and starts working the roadway in front of project. 12:00pm- Water proof contractor has completed
install and left the site. Contractor continues using on site material to backfill around the East side of
the vault, compacting with a vibratory roller. Materials tester is still not on site for compaction testing.
1:30pm- Contractor continues using on site material to backfill around the East side of the vault,
compacting with a vibratory roller. Materials tester is still not on site for compaction testing. 2:30pm-
Contractor continues using on site material to backfill around the East side of the vault, compacting
with a vibratory roller. Materials tester is still not on site for compaction testing. 3:00pm- Contractor
continues using on site material to backfill around the East side of the vault, compacting with a
vibratory roller. Materials tester is still not on site for compaction testing. Left the site for the day.
Patrick DeCaro 11/6/2020
7:45am- 1 Laborer arrived on site. 8:00am- 3 trucks arrive on site with pit run for backfilling the vault.
No traffic control is in place and no flaggers on site for trucks. 8:30am- Gary and another laborer
arrive on site and the 2 laborers start to remove the form nails from around the outside of the vault,
where the water proofing will go. Water proof contractor has started to install the water proof material
around the vault. Gary is moving material from the NorthEast outside corner of the vault to make room
for the quarry spall backfill, footing drains, and water proofing material. 9:00am- Scott Mitchell (COR
Building inspector) on site and is checking the water proof material installation. 11:00am- Water
proofing contractor has left the site because he has run out of material. He said he may be back later
today or tomorrow. Gary continues to excavate the NorthEast corner of the vault to expose the vault for
the water proof material and footing drain. 11:45am- Bob (PSE Locator) on site talking to contractor
about still no locates being called in for this job. 12:30pm- Gary and laborer leave the job site for the
day.
Patrick DeCaro 11/5/2020
Contractor arrived on site at approx. 7:45am. They have Gary (Foreman), 1 operator, and 2 laborers
on site. They have started to backfill on the South side of the vault with quarry spalls, and the North
side with quarry spalls and native material which they are compacting with a vibratory roller. Laborer
is starting to remove the form nails that are sticking out of the outside vault walls. 9:00am-checked
South side of vault and noticed they were backfilling over form wood and garbage so instructed them
to remove trash from area before backfilling. Also told them the same thing for the East side of the
vault. Scott Mitchell (COR Building inspector) arrived on site and I showed him the areas they were
backfilling with the trash there. He also instructed them to remove it before more backfilling. Scott
asked Gary about the mirror drains and when they would be installed. Gary said later today or
tomorrow. Asked Gary about material tester coming to check compaction around the vault. He told me
he didn't need to listen to Scott or I about compaction, only his Soil engineer. 10:00am-There are now
only 1 operator and 1 laborer backfilling the South side of the vault with quarry spalls.
12:15pm-Notified Hakem (Owner Representative) that the nails are still on the South side of the vault
where they are backfilling and need to be removed, per Scott. Operator and Laborer have left the site
because the excavator they are using is not working well. They said Gary told them they were done for
the day.
Patrick DeCaro 11/4/2020
Arrived on site 7:45am. Truck and trailer blocking the road waiting by the entrance with no traffic
control in site. Called Gary and told him we need traffic control. He arrives and has 2 workers with
paddles to control truck traffic in and out. Asked about them applying for a traffic control plan and he
said it has not been done yet. Told him he needs one ASAP. 1 truck and trailer is delivering quarry
spalls which 1 operator is placing on the East side of the vault. There is a footing drain installed on
the North side of the vault, but nothing yet on the East. I call Scott Mitchell (COR Building Inspector) to
inform him of work around the vault .Contractor said the mirror drains will be installed to the outside
of the vault on Thursday. I asked Scott if the form nails on the outside of the vault need to be removed
before the drains are installed and he said yes. This has not been done on any side yet. Owner
representative on site and I tell him about the needed traffic control plan. Heavy rain has caused dirty
water to begin leaving the site. I tell contractor they need to fix problem. The operator digs a channel
across the entrance and the workers place a straw waddle in the curb line to address erosion
issues. Bob from PSE shows up on site at this time and tells contractor they should not be digging
because their locates are out of date. They have not been renewed since March 1. Gary has left the
site and leaves the operator and 2 workers to flag for the trucks that will continue to bring quarry
spalls, which are now going to be stockpiled on site. Vault contractors are working on removing forms
and scaffolding from inside the vault. 1:45pm: Truck and trailer on site and only 1 flagger to work
roadway. I called Gary to ask him about it and he said he did not know why there were not 2. Asked
about the traffic control plan again and he said he was in contact with Ethan (COR Traffic) to get it
done. No other work is being done on site.
Patrick DeCaro 11/3/2020
Contractor has 1 operator removing dirt and quarry spalls from the North end of the vault. They also
have 1 truck and trailer delivering quarry spalls that they are placing on the East side of the vault near
the road. Asked the operator and Gary to remove the wood forms and pump the water out of the East
side of the vault area. Operator left the job site at 2:30pm today. Vault contractors are removing form
work from inside the vault. Contacted Scott (COR Building Inspector) to let him know what was
happening with the vault.
Patrick DeCaro 11/2/2020
10/31/2020
0900: The crew works to excavate and haul off soils. The MCI Sweeper is making passes in the
roadway here on Grant. The crew has a CASE excavator, a Hitachi excavator, and a dump truck and is
performing dirt work on the northeast portion of the townhome plat.
1032: The inspector heads to another project.
1116: The sweeper continues working to clean up in the roadway.
1225: The crew is offsite and the dump truck and excavator are parked and shutdown; a chain is
installed between the concrete blocks in the construction entrance.
Joe Nerlfi 10/31/2020
Contractor continues installing water line and water service corps. Also backfilling around the vault so
they have an area to continue installing water. Discussed what needs to be done before end of day
Saturday for the winter shut down. Hydro seed is scheduled for tomorrow. After discussing site
conditions with Justin and Brianne (COR) it was decided to have the contractor backfill around the
entire vault and complete the water afterwards. They will be given an additional 2 weeks to complete
work. Talked to the contractor and made sure they completely understood our new plan. Also told
them Brianne wanted an e-mail by 3pm tomorrow detailing everything we talked about and to make
sure they fully understand.
Patrick DeCaro 10/29/2020
Contractor is installing water line and water service corps. Asked contractor about installing poly bags
on the water line and was told the geo-tech said the material did not dictate using bags. I told them it
was a city standard and was even in the pre-con notes but none were installed. Talked to Abdoul (City
of Renton) about it and he said if they bag whatever line they are installing from now on he is ok with
it.
Patrick DeCaro 10/28/2020
Contractor is excavating to expose the water line so they can install corps and meter setters to the
new line. Also grading on site material so it can be hydro seeded.
Patrick DeCaro 10/27/2020
Contractor is on site pouring cement concrete for the vault. They have concrete trucks coming and
going with no traffic control on site. I informed them they need flaggers on site for the trucks. None
showed up while I was on site. Another contractor is excavating and working on installing corps for
the water line.
Patrick DeCaro 10/26/2020
Did not see contractor working on site today.Patrick DeCaro 10/23/2020
Did not see contractor working on site today. Vault contractors were working on site.Patrick DeCaro 10/22/2020
Contractor is working on excavating to install services to the water system.Patrick DeCaro 10/21/2020
Contractor is working on moving the new sewer line so they can work on the water system.Patrick DeCaro 10/20/2020
Did not see contractor working on site today. Vault contractors were working on site.Patrick DeCaro 10/19/2020
Did not see contractor working on site today. Vault contractors were working on site.Patrick DeCaro 10/15/2020
Did not see contractor working on site today. Vault contractors were working on site.Patrick DeCaro 10/14/2020
Did not see contractor working on site today. Vault contractors were working on site.Patrick DeCaro 10/13/2020
Did not see contractor working on site today. Called COR Building inspector Scott Mitchell to inform
him that the concrete contractor is pouring building slabs, which he said no one had notified him.
Patrick DeCaro 10/12/2020
Contractor continues moving stockpiled materials to backfill building foundations. Met on site with the
owner, contractor, and Brianne (COR). Discussed what needs to be done before the mandated shut
down of the site on November 1st.
Patrick DeCaro 10/9/2020
Contractor continues moving stockpiled materials to backfill building foundations.Patrick DeCaro 10/8/2020
Contractor continues moving stockpiled materials to backfill building foundations.Patrick DeCaro 10/7/2020
Contractor continues moving stockpiled materials to backfill building foundations.Patrick DeCaro 10/5/2020
Contractor continues moving stockpiled materials to backfill building foundations.Patrick DeCaro 10/1/2020
Contractor continues moving stockpiled materials to backfill building foundations.Patrick DeCaro 9/30/2020
Contractor is moving stockpiled materials to backfill building foundations.Patrick DeCaro 9/29/2020
Did not see contractor working on site today.Patrick DeCaro 9/28/2020
Contractor is moving stockpiled materials to backfill building foundations.Patrick DeCaro 9/25/2020
Did not see contractor working on site today.Patrick DeCaro 9/24/2020
Contractor is working on pouring cement concrete for building foundations.Patrick DeCaro 9/22/2020
Contractor is helping a crew install scaffolding on site. Erosion control I asked for has been installed.Patrick DeCaro 9/21/2020
9/18/2020 The contractor was working on erosion control. They also delivered scaffolding to the site.Brad Stocco 9/18/2020
Did not see contractor working on site today. Still have not fixed the erosion control issues. Called
and talked to contractor telling them again to fix erosion control issues.
Patrick DeCaro 9/17/2020
Did not see contractor working on site today. Still have not fixed the erosion control issues. Called
and left a message but got no reply.
Patrick DeCaro 9/16/2020
Contractor is moving material on site. Told them they need to fix erosion control for exposed soils and
have flaggers for traffic control when trucks are backing into the site.
Patrick DeCaro 9/15/2020
Did not see contractor working on site today.Patrick DeCaro 9/14/2020
Did not see contractor working on site today.Patrick DeCaro 9/10/2020
Did not see contractor working on site today.Patrick DeCaro 9/9/2020
Did not see contractor working on site today. Building contractor is pouring concrete for Building 3
foundation and walls for Building 6.
Patrick DeCaro 9/3/2020
Contractor is moving material around job site.Patrick DeCaro 9/2/2020
Contractor is moving material around job site. Silt fence has been repaired and construction entrance
has been re-rocked.
Patrick DeCaro 9/1/2020
Contractor is moving material around job site. Erosion control has not been completed yet. Asked
again when it will be done and the contractor told me they were going to get the supplies today.
Patrick DeCaro 8/31/2020
Contractor is moving material around job site. Building contractor is working on foundations. Erosion
control has not been completed yet. Asked again when it will be done and the contractor told me
Monday.
Patrick DeCaro 8/28/2020
Contractor is moving material around job site. Building contractor is working on foundations. Erosion
control has not been completed yet. Asked again when it will be done and the contractor told me
tomorrow.
Patrick DeCaro 8/27/2020
8/19/20- Contractor is moving material around job site. Building contractor is working on foundations.
Erosion control has not been completed yet.
8/20/20- Contractor is moving material around job site. Building contractor is working on foundations.
Erosion control has not been completed yet.
8/24/20- Contractor is moving material around job site. Building contractor is working on foundations.
Erosion control has not been completed yet.
8/25/20- Contractor is moving material around job site. Building contractor is working on foundations.
Erosion control has not been completed yet.
8/26/20- Contractor is moving material around job site. Building contractor is working on foundations.
Erosion control has not been completed yet.
Patrick DeCaro 8/26/2020
Building contractor is working on building foundations. Contractor is moving material throughout the
job site. I asked the contractor to repair silt fence and plastic throughout job site.
Patrick DeCaro 8/18/2020
Did not see contractor working on site today. Building contractor is working on building foundations.Patrick DeCaro 8/17/2020
Did not see contractor working on site today. Building contractor is working on building foundations.Patrick DeCaro 8/11/2020
Did not see contractor working on site today. Building contractor is working on building foundations.Patrick DeCaro 8/10/2020
Did not see contractor working on site today.Patrick DeCaro 8/6/2020
Did not see contractor working on site today.Patrick DeCaro 8/5/2020
Contractor is assisting with the installation of the vault lid. Traffic control on site.Patrick DeCaro 8/4/2020
Contractor is assisting with the installation of the vault lid. Traffic control on site.Patrick DeCaro 8/3/2020
Contractor is working on backfilling around building foundations. Concrete contractor continues
working on the vault.
Patrick DeCaro 7/29/2020
Contractor is working on backfilling around building foundations. Told them that their erosion control
is in need of repairs before they proceed with other work. They said the vault is being poured Friday
and the lid is coming on Monday.
Patrick DeCaro 7/28/2020
Concrete contractor continues working on the vault. Contractor is moving material around the vault on
the job site.
Patrick DeCaro 7/27/2020
Concrete contractor continues working on the vault. Did not see contractor on site today.Patrick DeCaro 7/23/2020
Concrete contractor continues working on the vault. Did not see contractor on site today.Patrick DeCaro 7/22/2020
Concrete contractor continues working on the vault. Did not see contractor on site today.Patrick DeCaro 7/21/2020
Time did not allow for a site visit today.Patrick DeCaro 7/20/2020
Concrete contractor continues working on the vault. Contractor is moving material around the vault on
the job site.
Patrick DeCaro 7/16/2020
Concrete contractor continues working on the vault. Contractor is moving material around the vault on
the job site.
Patrick DeCaro 7/14/2020
Concrete contractor continues working on the vault. Contractor is moving material around the vault on
the job site.
Patrick DeCaro 7/13/2020
Concrete contractor continues working on the vault. Contractor is moving material around the vault on
the job site.
Patrick DeCaro 7/9/2020
Concrete contractor continues working on the vault. Contractor is moving material around the vault on
the job site.
Patrick DeCaro 7/8/2020
Contractor is not working on the site today. Concrete contractor continues working on the vault.Patrick DeCaro 7/7/2020
Concrete contractor continues working on the vault. Contractor is moving material around the vault on
the job site.
Patrick DeCaro 7/6/2020
Concrete contractor continues working on the vault. Contractor is moving material around the vault on
the job site.
Patrick DeCaro 7/2/2020
Contractor is not working on the site today. Concrete contractor continues working on the vault.Patrick DeCaro 7/1/2020
Contractor is not working on the site today. Concrete contractor continues working on the vault.Patrick DeCaro 6/30/2020
Contractor is not working on the site today. Concrete contractor is working on the vault.Patrick DeCaro 6/29/2020
Contractor is not working on the site today. Concrete contractor is working on the vault.Patrick DeCaro 6/24/2020
Contractor is excavating for buildings on the site today. Concrete contractor is working on the vault.Patrick DeCaro 6/18/2020
Contractor is excavating for buildings on the site today. Concrete contractor is working on the vault.Patrick DeCaro 6/17/2020
Contractor is excavating for buildings on the site today. Concrete contractor is working on the vault.Patrick DeCaro 6/16/2020
Contractor is not working on the site today. Concrete contractor is working on the vault.Patrick DeCaro 6/15/2020
Contractor is not working on the site today.Patrick DeCaro 6/11/2020
Contractor is pouring cement concrete for the building footings.Patrick DeCaro 6/10/2020
Time did not allow a site visit today.Patrick DeCaro 6/9/2020
Contractor is not working on the site today.Patrick DeCaro 6/8/2020
Contractor is removing material from the job site. Concrete contractor continues working on the vault.Patrick DeCaro 6/3/2020
Contractor continues excavating for sewer and building foundations. Concrete contractor continues
working on the vault.
Patrick DeCaro 6/2/2020
Contractor is excavating for sewer and building foundations. Concrete contractor is working on the
vault.
Patrick DeCaro 6/1/2020
Contractor continues digging for the foundation for one of the buildings.Patrick DeCaro 5/27/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site.
Also excavating for building foundations.
Patrick DeCaro 5/26/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site.Patrick DeCaro 5/21/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site.Patrick DeCaro 5/20/2020
Contractor continues digging for the foundation for one of the buildings.Patrick DeCaro 5/19/2020
Contractor is digging for the foundation for one of the buildings.Patrick DeCaro 5/18/2020
Contractor is starting to dig a foundation for one of the buildings.Patrick DeCaro 5/15/2020
Contractor is not working on the site today.Patrick DeCaro 5/14/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site.Patrick DeCaro 5/13/2020
Contractor is continuing to export material from the job site and take it to Cedar Ridge at 156th.Patrick DeCaro 5/12/2020
Contractor is continuing to export material from the job site and take it to Cedar Ridge at 156th.Patrick DeCaro 5/11/2020
5/6/2020
8:45am-contractor is continuing to export material to Cedars at 156th. advised contractor to put up
crew working signs in both directions and to wear a vest and hard hat while flagging. contractor
scheduled a sweeper for the next couple of days to keep road clean in front of site. contractor plans to
continue exporting material 5/7 and 5/8.
1pm-signs are up and road is being kept clean.
Kip Braaten 5/6/2020
5/5/2020
12pm-contractor exporting stock pile to 156th to use as fill dirt. no erosion control issues present,
contractor is keeping road clean.
Kip Braaten 5/5/2020
Contractor is not working on the site today.Patrick DeCaro 5/4/2020
Contractor has started removing stockpiled material from the site.Patrick DeCaro 4/30/2020
Time did not allow for a site visit today.Patrick DeCaro 4/29/2020
Did not see contractor working on site today.Patrick DeCaro 4/28/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site.Patrick DeCaro 4/27/2020
Contractor is not working on the site today.Patrick DeCaro 4/24/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site.Patrick DeCaro 4/23/2020
Did not see contractor working on site today.Patrick DeCaro 4/22/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site.Patrick DeCaro 4/21/2020
Did not see contractor working on site today.Patrick DeCaro 4/20/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site. Did
not see concrete contractor working on site today.
Patrick DeCaro 4/16/2020
Did not see contractor working on site today.Patrick DeCaro 4/15/2020
Contractor continues pumping water from the vault to the filter at the top of the job site. Original
concrete contractor is on site removing the forms that were left behind.
Patrick DeCaro 4/14/2020
Contractor continues pumping water from the vault to the filter at the top of the job site.Patrick DeCaro 4/13/2020
Contractor continues pumping water from the vault to the filter at the top of the job site. Special
Inspector on site watching concrete contractor placing repair material into the wall voids. At about
12:00pm Scott Mitchell (COR Building Inspector) put a Stop Work order on the site for vault issues.
They will be able to continue pumping the water from the vault and maintaining erosion control.
Patrick DeCaro 4/10/2020
Contractor continues pumping water from the vault to the filter at the top of the job site. Special
Inspector on site watching concrete contractor placing repair material into the wall voids.
Patrick DeCaro 4/9/2020
Contractor continues pumping water from the vault to the filter at the top of the job site. Special
Inspector on site watching concrete contractor placing repair material into the wall voids.
Patrick DeCaro 4/8/2020
Contractor continues pumping water from the vault to the filter at the top of the job site. Special
Inspector on site watching concrete contractor placing repair material into the wall voids.
Patrick DeCaro 4/7/2020
Contractor continues pumping water from the vault to the filter at the top of the job site. Special
Inspector on site watching concrete contractor hitting concrete vault walls checking for voids.
Patrick DeCaro 4/6/2020
Contractor continues pumping water from the vault to the filter at the top of the job site. Special
Inspector on site watching concrete contractor hitting concrete vault walls checking for voids.
Patrick DeCaro 4/2/2020
Contractor continues pumping water from the vault to the filter at the top of the job site. Special
Inspector on site watching concrete contractor hitting concrete vault walls checking for voids.
Patrick DeCaro 4/1/2020
Contractor continues pumping water from the vault to the filter at the top of the job site. Met on site
with owner, contractor, special inspector, and COR building inspector about vault repairs.
Patrick DeCaro 3/31/2020
Contractor continues pumping water from the vault to the filter at the top of the job site. Did not see
concrete contractor on site today.
Patrick DeCaro 3/30/2020
Contractor is abiding by the State mandated shut down and are not working on site today. No one is
pumping water on site today.
Patrick DeCaro 3/27/2020
Contractor continues pumping water from the vault to the filter at the top of the job site. Did not see
concrete contractor on site today. They were informed to final their erosion control by the end of the
day and then were shut down per the Governors notice to stop work. This job can continue work
during the shut down for water pumping and erosion control ONLY.
Patrick DeCaro 3/26/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site. Did
not see concrete contractor working on site today.
Patrick DeCaro 3/25/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site. Did
not see concrete contractor working on site today.
Patrick DeCaro 3/24/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site. Did
not see concrete contractor working on site today.
Patrick DeCaro 3/23/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site. Did
not see concrete contractor working on site today.
Patrick DeCaro 3/19/2020
3/17/2020. Did not see contractor working on site today. Did not see concrete contractor working on
site today.
3/18/2020. Contractor continues pumping water from the vault to the filter system at the top of the
project site. Did not see concrete contractor working on site today.
Patrick DeCaro 3/18/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site. Did
not see concrete contractor working on site today.
Patrick DeCaro 3/16/2020
3/13/2020. Contractor continues pumping water from the vault to the filter system at the top of the
project site. Did not see concrete contractor working on site today.
Patrick DeCaro 3/16/2020
Did not see contractor on site. Did not see concrete contractor working on site today. Water in about
half way up the inside and outside of the vault.
Patrick DeCaro 3/12/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site. Did
not see concrete contractor working on site today.
Patrick DeCaro 3/11/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site. Did
not see concrete contractor working on site today. Erosion control issues I asked contractor to work
on have been fixed.
Patrick DeCaro 3/10/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site. Did
not see concrete contractor working on site today. Asked contractor to repair plastic sheeting that has
blown off of the slopes.
Patrick DeCaro 3/9/2020
Contractor is pumping water offsite to percolate into the native material in the forested area; the vault
is nearly empty of water.
Joe Nerlfi 3/6/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site. Did
not see concrete contractor working on site today. Asked contractor to repair plastic sheeting that has
blown off of the slopes.
Patrick DeCaro 3/5/2020
Did not see contractor on site. Did not see concrete contractor working on site today. Water in about
half way up the inside and outside of the vault.
Patrick DeCaro 3/2/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site. Did
not see concrete contractor working on site today. Erosion control issues I asked them about the
other day have been fixed.
Patrick DeCaro 2/27/2020
Did not see contractor on site. Did not see concrete contractor working on site today. Water in about
half way up the outside of the vault, plastic has blown off of the site material, and silt fence needs to
be replaced. Called contractor to do the above work that was requested on Monday. They said they
would come out and take care of it today. Did not make it back this afternoon to check.
Patrick DeCaro 2/26/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site. Did
not see concrete contractor working on site today. Water in about half way up the outside of the vault,
plastic has blown off of the site material, and silt fence needs to be replaced. This work was still not
completed when I went by.
Patrick DeCaro 2/25/2020
Did not see anyone on site today. Water in about half way up the outside of the vault, plastic has
blown off of the site material, and silt fence needs to be replaced. I called contractor and told them the
things that needed to be done.
Patrick DeCaro 2/24/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site. Did
not see concrete contractor working on site today.
Patrick DeCaro 2/21/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site. Did
not see concrete contractor working on site today.
Patrick DeCaro 2/20/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site. Did
not see concrete contractor working on site today.
Patrick DeCaro 2/19/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site. Did
not see concrete contractor working on site today.
Patrick DeCaro 2/18/2020
Did not see anyone on site today. Water in about half way up the outside of the vault.Patrick DeCaro 2/17/2020
The contractor is not seen onsite.Joe Nerlfi 2/14/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site. Did
not see concrete contractor working on site today. Tester on site checking the NTU's of the water
leaving the site. Still waiting for any on the test results to be sent to us as requested.
Patrick DeCaro 2/13/2020
Did not see anyone on site today.Patrick DeCaro 2/12/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site. Did
not see concrete contractor working on site today. Contractor is also placing rock at the top side of the
vault and covering it with plastic to help stabilize the slope with the erosion issues.
Patrick DeCaro 2/10/2020
Did not see anyone on site today.Patrick DeCaro 2/7/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site. Did
not see concrete contractor working on site today.
Patrick DeCaro 2/6/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site. Did
not see concrete contractor working on site today.
Patrick DeCaro 2/5/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site. Did
not see concrete contractor working on site today.
Patrick DeCaro 2/4/2020
Contractor is not working on the site today.Patrick DeCaro 2/3/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site.
Concrete contractor continues to remove the forms from the vault area.
Patrick DeCaro 1/31/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site.
Concrete contractor continues to remove the forms from the vault area.
Patrick DeCaro 1/30/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site.
Concrete contractor continues to remove the forms from the vault area. Water leaving the site has
been tested for NTU's and is 20.
Patrick DeCaro 1/29/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site.
Concrete contractor continues to remove the forms from the vault area. Water leaving the site looks
questionable for NTU's so it will be tested tomorrow.
Patrick DeCaro 1/28/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site.
Concrete contractor is starting to remove the forms from the vault area. When they drove the crane
onto the lower part of the site they drug material onto the roadway. I asked the contractor to clean up
the road and place more straw around the disturbed areas, which they did.
Patrick DeCaro 1/27/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site.
Checked the water leaving the site today for NTU's and they were at 65. Told contractor to address
problem immediately. Contractor placed silt fence, straw waddles, and cleaned up curb and gutter
area of excess dirt. Kip (COR) checked the NTU's in the afternoon from the site and said all were
passing.
Patrick DeCaro 1/24/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site. Still
have not received NTU test results for water leaving the site.
Patrick DeCaro 1/23/2020
Did not see anyone working on the site today. Called contractor and requested the NTU report from
their CECSL. He said he would contact the site owner to send it.
Patrick DeCaro 1/22/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site. I
again asked contractor to have their CESCL take more tests of the water leaving the job site to make
sure it is under 25 NTU's.
Patrick DeCaro 1/21/2020
Time did not allow for a site visit today.Patrick DeCaro 1/17/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site. I
asked contractor to have their CESCL take more tests of the water leaving the job site to make sure it
is under 25 NTU's.
Patrick DeCaro 1/16/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site.Patrick DeCaro 1/15/2020
Contractor is not onsite; water still partially filling the vault.Joe Nerlfi 1/14/2020
Contractor continues pumping water from the vault to the filter system at the top of the project site.Patrick DeCaro 1/13/2020
Contractor is placing straw over the exposed areas of material on the job site. Also pumping water
from the vault to the top of the site and filtering it back down so what is leaving the site is clean.
Plastic has been fixed and all erosion issues are being worked on.
Patrick DeCaro 1/10/2020
Contractor has started to work on the erosion control issues that were stated to them yesterday. The
plastic and sandbags have been moved to cover the exposed soil, the silt fence next to the
construction entrance has been repaired, and they are placing straw on all exposed areas of soil.
Asked them to place straw bails across the catch basin opening by the NW corner of the vault to help
clean the water leaving the site. They are also starting to implement the de-watering plan that was
sent in by Gary (Prime Contractor).
Patrick DeCaro 1/9/2020
Contractor is not working on the site today. They have installed the fencing across the construction
entrance to close it off. Some of the exposed material has been covered with plastic and sand bags,
but there is still areas that have not been done. Silt fence along the construction entrance still needs
to be repaired, and there is water coming from the construction entrance and the NW corner of the
vault that is leaving the site and going into the catch basins on Grant Ave. The water will need to be
tested for NTU's.
Patrick DeCaro 1/8/2020
Contractor is not working on the site today. They have installed the fencing across the construction
entrance to close it off. Owner sent an e-mail saying they would be installing more plastic and sand
bags tomorrow for some of the erosion issues. Still have no plan for the water in the vault and the
water coming from the job site.
Patrick DeCaro 1/7/2020
Did not see anyone working on the site today. Called them about erosion issues on site (Plastic
blowing off stockpiles, debris everywhere, gate not closing access to job site).
Patrick DeCaro 1/6/2020
No crews are working onsite today. The vault is still filled with water.Joe Nerlfi 1/3/2020
No crews are working onsite today. The vault is still filled with water.Joe Nerlfi 1/2/2020
No crews are working onsite today. The vault is still filled with water.Joe Nerlfi 12/31/2019
The crew is onsite pumping the water out of the vault up to a temporary settling pond. The project
engineer tells the crew to stop pumping.
Joe Nerlfi 12/30/2019
No crews are working onsite today. the vault is still filled with water.Joe Nerlfi 12/27/2019
No crews are working onsite today; the vault remains mostly filled with water.Joe Nerlfi 12/24/2019
12-23-2019
1003: The inspector stops by the rain-soaked site and photographs the vault that is 75% filled with
turbid rainwater, floating boards, and assorted scrap wood. The crew is not onsite working today.
Joe Nerlfi 12/23/2019
Did not see anyone working on the site today. Called contractor and told them they to add straw and
address uncovered stockpiles on site for erosion.
Patrick DeCaro 12/20/2019
Did not see anyone working on the site today. Grass is going on the stock piles for erosion control.Patrick DeCaro 12/19/2019
Did not see anyone working on the site today.Patrick DeCaro 12/17/2019
Contractor is not working on site today. Vault inspection failed. No lids were placed.Patrick DeCaro 12/12/2019
Contractor is not working on site today. Concrete contractor continues stripping forms from the storm
vault.
Patrick DeCaro 12/11/2019
Contractor is not working on site today. Concrete contractor continues stripping forms from the storm
vault.
Patrick DeCaro 12/10/2019
Contractor is not working on site today. Concrete contractor is stripping forms from the storm vault.Patrick DeCaro 12/9/2019
Contractor is not working on site today. Did not see concrete contractor doing any form stripping
today.
Patrick DeCaro 12/6/2019
12-4-19. Contractor is not working on site today. Concrete contractor is stripping forms from the storm
vault.
12-5-19. Contractor is not working on site today. Did not see concrete contractor doing any form
stripping today.
Patrick DeCaro 12/5/2019
Contractor is not working on site today. Concrete contractor is stripping forms from the storm vault.Patrick DeCaro 12/3/2019
Contractor is not working on site today. Concrete contractor is stripping forms from the storm vault.Patrick DeCaro 12/2/2019
Did not see anyone working on anything at the site today.Patrick DeCaro 11/27/2019
Contractor is not working on site today. Concrete workers were stripping forms when I arrived at
10:30am. Notified the COR building inspector. Asked for a Foreman on site and got no reply from the
workers.
Patrick DeCaro 11/26/2019
Contractor is not working on site today. Concrete is being poured for the vault.Patrick DeCaro 11/25/2019
11/22/19. Contractor is not working on site today. Vault continues to be worked on.Patrick DeCaro 11/25/2019
Contractor is not working on the site today. Vault continues to be worked on.Patrick DeCaro 11/21/2019
Contractor is not working on the site today. Vault continues to be worked on.Patrick DeCaro 11/19/2019
Contractor is not working on the site today. Vault continues to be worked on.Patrick DeCaro 11/18/2019
Did not see anyone working on the site today.Patrick DeCaro 11/15/2019
Time did not allow for a site vist today.Patrick DeCaro 11/14/2019
Did not see anyone working on the site today.Patrick DeCaro 11/13/2019
Did not see anyone working on the site today.Patrick DeCaro 11/12/2019
Contractor is not working on the site today. Vault continues to be worked on.Patrick DeCaro 11/8/2019
Contractor is not working on the site today. Vault continues to be worked on.Patrick DeCaro 11/7/2019
Contractor is not working on the site today. Vault continues to be worked on.Patrick DeCaro 11/6/2019
Contractor is not working on the site today. Vault continues to be worked on.Patrick DeCaro 11/5/2019
Contractor is not working on the site today. Looks like all the exposed areas were covered with straw
for erosion control. Vault continues to be worked on.
Patrick DeCaro 11/4/2019
Contractor is on site placing straw and grass seed over the areas of the job site that will not be
worked this winter. Reminded them again about the shut down from November 1st to April 1st where
there is no earth work to be done during this time. They have been approved to continue work on the
vault but that is all. Took pictures of all the exposed and hydro seeded areas on the site today.
Patrick DeCaro 11/1/2019
Met with contractor and owner to discuss erosion control for their shut down on November 1. They are
continuing to work on the vault.
Patrick DeCaro 10/30/2019
10-29-19. Did not see contractor working on site today. Concrete crew continues working on setting
the rebar for the vault.
Patrick DeCaro 10/30/2019
Contractor is continuing to grading the roadway on the plat. Vault is still being worked on. They are
starting to form the inside walls. I asked the Superintendent if the rebar had been inspected yet and
he said No. They still have to tie vertical rebar for one more wall. Pavers showed up at approximately
2:30pm and said they were going to pave the on plat road. There was no traffic control in place. They
completed the asphalt paving at 7:00PM in the dark. There were no lights or light plants on site. I
asked the Super if the roadway sub-base had been tested for compaction before the asphalt and he
said No. I informed him that this would be a temporary roadway then because we have no
compaction reports for the sub-base. Witnessed the asphalt trucks sinking on the sub-base about
4-6 inches. Asphalt roadway was wavy and soft in places. They placed approximately 2-3 inches of
asphalt.
Patrick DeCaro 10/28/2019
Contractor is continuing to grading the roadway on the plat. They are also working on the utility
crossings on site. Vault is still being worked on.
Patrick DeCaro 10/25/2019
Contractor is placing recycled concrete over the quarry spalls to build the road going into the plat.
Vault is still being worked on. Site has been hydro-seeded.
Patrick DeCaro 10/24/2019
Contractor continues having trucks deliver 2 x 4 quarry spalls for the roadway they are trying to build
on site. Also grading for the roadway. Vault is having rebar installed for the walls. Site is being
hydro-seeded covering all exposed bare areas.
Patrick DeCaro 10/23/2019
Contractor continues having trucks deliver 2 x 4 quarry spalls for the roadway they are trying to build
on site. Also grading for the roadway. Vault is trying to be pumped out from all the water it collected.
No other erosion control measures have been installed.
Patrick DeCaro 10/22/2019
Contractor is having trucks deliver 2 x 4 quarry spalls for the roadway they are trying to build on site.
Also grading for the roadway. They have told me the entire site will be hydo-seeded on Wednesday.
Vault is trying to be pumped out from all the water it collected over the weekend. No other erosion
control measures have been installed.
Patrick DeCaro 10/21/2019
Contractor is excavating for the on site utility trench.Patrick DeCaro 10/18/2019
Contractor is working on the vault on the job site. Also grading the material stockpile on site. I asked
about the erosion control measures that have not been done. Still no erosion control measures for
the wet season have been installed. Still have not received information on the concrete workers City
of Renton Business License, which I asked for again today.
Patrick DeCaro 10/17/2019
Contractor is working on the vault on the job site. Still no erosion control measures for the wet
season have been installed. Still have not received information on the concrete workers City of
Renton Business License, which I asked for yesterday.
Patrick DeCaro 10/16/2019
Contractor is starting to excavate for the utility trench the job site. Also trying to grade the material
stock pile. Still no erosion control measures for the wet season have been installed. Asked for the
concrete workers City of Renton Business License, which they are checking to see if they have.
Patrick DeCaro 10/15/2019
Contractor continues fine grading the job site. Also trying to grade the material stock pile. Still no
erosion control measures for the wet season have been installed. Pictures were sent to Brianne
(COR) showing no erosion control measures installed. Vault is still not completed, and was worked
on over the weekend with no permission from the City.
Patrick DeCaro 10/14/2019
Contractor is fine grading the job site. Also trying to grade the material stock pile. Still no erosion
control measures for the wet season have been installed. Vault is still not completed.
Patrick DeCaro 10/11/2019
Contractor is working on grading stockpiled material on the job site.Patrick DeCaro 10/10/2019
Checked cotractors thrust blocks today. All looked good. They are backfilling and compacting over
thrust blocks.
Patrick DeCaro 10/9/2019
Contractor is excavating and installing thrust blocks for the water pipe and hydrants.Patrick DeCaro 10/8/2019
Contractor continues installing water hydrants and water pipe on the job site.Patrick DeCaro 10/7/2019
Contractor is pouring the cement concrete floor for the vault. They used 10 trucks to pour
approximately 100 yards of concrete. Material tester on site to take cylinders. 2 flaggers on site for
traffic control.
Patrick DeCaro 10/5/2019
Contractor is pumping out the water from the bottom of the vault base so they can pour the remainder
of it tomorrow.
Patrick DeCaro 10/4/2019
Contractor continues installing water hydrants and water pipe on the job site.Patrick DeCaro 10/3/2019
Contractor continues installing water hydrants and water pipe on the job site.Patrick DeCaro 10/2/2019
Contractor is installing water hydrants and water pipe on the job site. Also hauling away stockpiled
material.
Patrick DeCaro 10/1/2019
Contractor is installing water hydrants and water pipe on the job site.Patrick DeCaro 9/30/2019
9/28/2019 The contractor was hauling spoils off site. They had a sweeper truck on site all day.Brad Stocco 9/30/2019
Contractor is installing water hydrants on the job site.Patrick DeCaro 9/27/2019
Did not see contractor working on the site today.Patrick DeCaro 9/26/2019
Contractor is installing fire hydrants and setting forms for water line thrust blocks.Patrick DeCaro 9/25/2019
Met on site with Brianne (COR), contractor, and site owner. Discussed erosion control issues for the
wet season. Informed them to produce a schedule that shows their plans for the next month. Today
they are working on stabilizing the vault walls and continuing to install water pipe.
Patrick DeCaro 9/24/2019
Sub contractor is on site removing the forms from the vault floor that was poured last week.Patrick DeCaro 9/18/2019
Contractor is on site placing gravel for a roadway up to the top of the plat. Walked through with the
contractor and discussed erosion control issues they will need to address before the wet season
shut down. They are install and repair silt fence on site, cover or stabilize dirt pile, straw of hydro seed
entire site, and figure out where to put the ground water from the site.
Patrick DeCaro 9/17/2019
Did not see contractor working on the site today.Patrick DeCaro 9/16/2019
Contractor continues working on installing water line.Patrick DeCaro 9/13/2019
Contractor continues working on installing water line. Also pouring the floor of the storm vault. Mayes
Inspection on site to inspect rebar and concrete pour.
Patrick DeCaro 9/11/2019
Contractor continues working on installing water line and removing material pile from job site.Patrick DeCaro 9/10/2019
Contractor continues working on installing water line and working on getting vault ready to pour
concrete.
Patrick DeCaro 9/9/2019
Contractor is working on installing water line.Patrick DeCaro 9/4/2019
Time did not allow for a site visit today.Patrick DeCaro 9/3/2019
Did not see contractor working on the site today.Patrick DeCaro 8/30/2019
Time did not allow for a site visit today.Patrick DeCaro 8/28/2019
Did not see contractor working on the site today.Patrick DeCaro 8/27/2019
Contractor continues excavating for the vault on the front side of the job site.Patrick DeCaro 8/26/2019
Did not see contractor working on the site today.Patrick DeCaro 8/23/2019
Contractor continues excavating for the vault on the front side of the job site.Patrick DeCaro 8/20/2019
Did not see contractor working on the site today.Patrick DeCaro 8/19/2019
Did not see contractor working on the site today.Patrick DeCaro 8/15/2019
Did not see contractor working on the site today.Patrick DeCaro 8/14/2019
Did not see contractor working on the site today.Patrick DeCaro 8/12/2019
Contractor is working on excavating for the building foundation.Patrick DeCaro 8/9/2019
Contractor is grading material on site.Patrick DeCaro 8/8/2019
Contractor continues excavating for the vault on the front side of the job site.Patrick DeCaro 8/7/2019
Contractor continues excavating for the vault on the front side of the job site.Patrick DeCaro 8/5/2019
Contractor continues excavating for the vault on the front side of the job site.Patrick DeCaro 7/29/2019
Contractor continues excavating for the vault on the front side of the job site.Patrick DeCaro 7/26/2019
Contractor continues excavating for the vault on the front side of the job site.Patrick DeCaro 7/25/2019
Contractor continues excavating for the vault on the front side of the job site.Patrick DeCaro 7/24/2019
Contractor is excavating for the vault on the front side of the job site.Patrick DeCaro 7/23/2019
Did not see contractor working on the site today.Patrick DeCaro 7/17/2019
Contractor is starting to install traffic control jersey barriers on the front of the job site.Patrick DeCaro 7/16/2019
Did not see contractor working on the site today.Patrick DeCaro 7/15/2019
Contractor is grading material on site.Patrick DeCaro 7/3/2019
Contractor is installing storm pipe and structures. Backfilling and compacting.Patrick DeCaro 7/2/2019
Contractor is grading material on site.Patrick DeCaro 7/1/2019
Did not see contractor working on the site today.Patrick DeCaro 6/27/2019
Contractor is unloading storm pipe and structures.Patrick DeCaro 6/26/2019
Did not see contractor working on the site today.Patrick DeCaro 6/24/2019
Did not see contractor working on the site today.Patrick DeCaro 6/21/2019
6-20-2019. Contractor is working on installing storm.Patrick DeCaro 6/21/2019
Contractor is pressure testing the sewer system from Manhole #7 to Manhole #8. Passed.Patrick DeCaro 6/18/2019
Contractor is working on installing storm.Patrick DeCaro 6/17/2019
6/13/2019. Contractor has pressure tested the sewer line from Manhole #4 to Manhole #5. Passed.
6/14/2019. Contractor is backfilling over the sewer line.
Patrick DeCaro 6/14/2019
Did not see contractor working on the site today.Patrick DeCaro 6/12/2019
Did not see contractor working on the site today.Patrick DeCaro 6/11/2019
Contractor continues grading material and installing sewer pipe and structures on the job site.Patrick DeCaro 6/10/2019
Contractor continues grading material and installing sewer pipe and structures on the job site.Patrick DeCaro 6/4/2019
Contractor continues grading material and installing sewer pipe and structures on the job site.Patrick DeCaro 6/3/2019
Did not see contractor working on the site today.Patrick DeCaro 5/31/2019
Did not see contractor working on the site today.Patrick DeCaro 5/30/2019
Contractor continues grading material and installing sewer pipe and structures on the job site.Patrick DeCaro 5/29/2019
Contractor continues grading material and installing sewer pipe and structures on the job site.Patrick DeCaro 5/28/2019
Contractor continues grading material on the job site.Patrick DeCaro 5/24/2019
Contractor is grading material on the job site.Patrick DeCaro 5/23/2019
Did not see contractor working on the site today.Patrick DeCaro 5/22/2019
Did not see contractor working on the site today.Patrick DeCaro 5/21/2019
Contractor continues installing sewer pipe.Patrick DeCaro 5/17/2019
Contractor continues installing sewer pipe.Patrick DeCaro 5/16/2019
Contractor continues installing sewer pipe.Patrick DeCaro 5/15/2019
Did not see contractor working on the site today.Patrick DeCaro 5/14/2019
Contractor continues installing sewer pipe.Patrick DeCaro 5/13/2019
Contractor continues installing sewer pipe.Patrick DeCaro 5/9/2019
Contractor continues installing sewer pipe.Patrick DeCaro 5/8/2019
Contractor has installed 1 Manhole and sewer pipe on the job site.Patrick DeCaro 5/7/2019
Contractor continues loading out material from the job site.Patrick DeCaro 5/6/2019
Contractor continues loading out material from the job site.Patrick DeCaro 5/3/2019
Contractor continues loading out material from the job site.Patrick DeCaro 5/2/2019
Contractor was loading out material from the job site.Patrick DeCaro 5/1/2019
Did not see contractor working on the site today. Erosion control looked good.Patrick DeCaro 4/30/2019
I was out sick all last week. Did not see contractor working on the site today. Erosion control looked
good.
Patrick DeCaro 4/29/2019
Contractor continues excavating for the storm vault.Patrick DeCaro 4/19/2019
Contractor continues excavating for the on site storm vault.Patrick DeCaro 4/18/2019
Contractor continues excavating for the storm vault.Patrick DeCaro 4/17/2019
Contractor is meeting on site with the owner to discuss excavation problems with the vault.Patrick DeCaro 4/16/2019
Contractor continues excavating for the storm vault.Patrick DeCaro 4/15/2019
Contractor is excavating for the storm vault.Patrick DeCaro 4/12/2019
Did not see contractor working on the site today. Erosion control looked good.Patrick DeCaro 4/11/2019
Contractor continues removing the stockpiled material from the job site.Patrick DeCaro 4/10/2019
Contractor continues removing the stockpiled material from the job site.Patrick DeCaro 4/9/2019
Contractor is removing the stockpiled material from the job site.Patrick DeCaro 4/8/2019
Contractor has started mobilizing machinery on site.Patrick DeCaro 4/4/2019
Did not see contractor working on the site today. Erosion control looked good.Patrick DeCaro 4/3/2019
Did not see contractor working on the site today. Erosion control looked good.Patrick DeCaro 4/2/2019
Did not see contractor working on the site today. Erosion control looked good.Patrick DeCaro 4/1/2019
Did not see contractor working on the site today. Erosion control looked good.Patrick DeCaro 3/29/2019
Did not see contractor working on the site today. Erosion control looked good.Patrick DeCaro 3/28/2019
Did not see contractor working on the site today. Erosion control looked good.Patrick DeCaro 3/27/2019
Did not see contractor working on the site today. Erosion control looked good.Patrick DeCaro 3/26/2019
Did not see contractor working on the site today. Erosion control looked good.Patrick DeCaro 3/25/2019
Did not see contractor working on the site today. Erosion control looked good.Patrick DeCaro 3/22/2019
Did not see contractor working on the site today. Erosion control looked good.Patrick DeCaro 3/21/2019
Contractor has a vactor truck on site to pot hole for utilities.Patrick DeCaro 3/19/2019
Did not see contractor working on the site today. Erosion control looked good.Patrick DeCaro 3/18/2019
Did not see contractor working on the site today. Erosion control looked good.Patrick DeCaro 3/15/2019
Did not see contractor working on the site today. Erosion control looked good. Erosion control looked
good. Earth Solutions did a check on the site and everything was fine.
Patrick DeCaro 3/12/2019
Did not see contractor working on the site today. Erosion control looked good.Patrick DeCaro 3/8/2019
Did not see contractor working on the site today. Erosion control looked good.Patrick DeCaro 3/7/2019
Did not see contractor working on the site today. Erosion control looked good.Patrick DeCaro 3/6/2019
Did not see contractor working on the site today. Erosion control looked good.Patrick DeCaro 3/5/2019
Did not see contractor working on the site today. Erosion control looked good.Patrick DeCaro 3/4/2019
Did not see contractor working on the site today. Erosion control looked good.Patrick DeCaro 3/1/2019
Did not see contractor working on the site today. Erosion control looked good.Patrick DeCaro 2/27/2019
Did not see contractor working on the site today. Erosion control looked good.Patrick DeCaro 2/26/2019
Did not see contractor working on the site today. Erosion control looked good.Patrick DeCaro 2/25/2019
Did not see contractor working on the site today. Erosion control looked good.Patrick DeCaro 2/21/2019
Did not see contractor working on the site today.Patrick DeCaro 2/20/2019
Did not see contractor working on the site today.Patrick DeCaro 2/19/2019
Snow and ice, no one is working today.Patrick DeCaro 2/15/2019
Snow and ice, no one is working today.Patrick DeCaro 2/12/2019
Did not see contractor working on the site today. Snow and ice covering site.Patrick DeCaro 2/7/2019
Did not see contractor working on the site today. Snow and ice covering site.Patrick DeCaro 2/6/2019
Did not see contractor working on the site today.Patrick DeCaro 2/1/2019
Did not see contractor working on the site today.Patrick DeCaro 1/31/2019
Met on site with Brianne (COR) and Rohini (COR) to check status of erosion control. Everything looks
good and pictures were taken. Still no word on the permission for the contractor to pump water next
door on the PSE property.
Patrick DeCaro 1/30/2019
Did not see contractor working on the site today.Patrick DeCaro 1/29/2019
Did not see contractor working on the site today.Patrick DeCaro 1/28/2019
Did not see contractor working on the site today.Patrick DeCaro 1/24/2019
Contractor was on site pumping the water from the vault area onto PSE property. I asked if they had
written permission to do so and was told they didn't know. Asked Rohini (COR) to contact owner to
see if he has received written permission.
Patrick DeCaro 1/23/2019
Did not see contractor working on the site today. The material stockpile has been covered with Jute
matting and straw. The entire site has been covered with straw for erosion control.
Patrick DeCaro 1/22/2019
Contractor on site installing straw and erosion control measures.Patrick DeCaro 1/18/2019
Did not see contractor working on the site today.Patrick DeCaro 1/17/2019
Talked to contractor who said they have ordered more straw for erosion control and will place it on
Thursday.
Patrick DeCaro 1/16/2019
Contractor on site maintaining erosion control items.Patrick DeCaro 1/15/2019
1/14/19. Did not see contractor working on the site today.Patrick DeCaro 1/15/2019
Did not see contractor working on the site today.Patrick DeCaro 1/11/2019
Contractor was on site installing Jute mat over the material stockpile, placing quarry spalls in the
excavated vault area to anchor the slopes, and installing straw over the entire job site for erosion
control.
Patrick DeCaro 1/10/2019
Did not see contractor working on the site today. Stock pile of material has the plastic sheeting blown
off.
Patrick DeCaro 1/9/2019
Met on site with Brianne (COR), Rohini (COR), site owner, and site contractor. Discussed erosion
control issues we noticed and informed them that they need to come up with a plan to fix them. They
have sent Rohini a list of items they are starting to work on.
Patrick DeCaro 1/8/2019
Did not see contractor working on the site today. Stock pile of material has the plastic sheeting
blowing off. Met on site with Brianne (COR) and Rhohini (COR) to do an erosion control site walk
through. We noticed a lot of things that were not in compliance with our erosion control specifications.
Rhohini sent the owner and contractor a message that we need to meet ASAP on site to identify and
resolve all the issues.
Patrick DeCaro 1/7/2019
Contractor has pumped down the vault area and re-covered the material pile on site. Talked to them
today and they said the material pile would be flattened on Monday and covered with Jute matting.
Patrick DeCaro 1/4/2019
I went to the job site again today and found that the stock pile is still not covered, the pond is very
close to overflowing, and the water leaving the site at the bottom of the silt fence tested at 70 NTU.
When I was there the CECSL arrived and also took a water sample to test. He told me that the things
he recommended in his Field Report were still not all done. The site is not being maintained per our
standards and needs to be addressed.
Patrick DeCaro 1/3/2019
Did not see contractor working on the site today. Stock pile of material has the plastic sheeting
blowing off. Sent the owner and contractor another message asking when they would be working on
the outstanding erosion control issues.
Patrick DeCaro 1/2/2019
Did not see the contractor working on the site today.Patrick DeCaro 12/28/2018
Did not see the contractor working on the site today.Patrick DeCaro 12/27/2018
Contractor is on site re-covering the material stock pile with plastic and pumping down the excavated
vault area.
Patrick DeCaro 12/26/2018
Did not see contractor working on the site today. Stock pile of material has the plastic sheeting
blowing off. Sent the owner and contractor a message asking when they would be working on the
outstanding erosion control issues. They said they were looking into it.
Patrick DeCaro 12/21/2018
Did not see contractor working on the site today. Stock pile of material has the plastic sheeting
blowing off. Called contractor about fixing it.
Patrick DeCaro 12/20/2018
Did not see contractor working on the site today. Stock pile of material has the plastic sheeting
blowing off.
Patrick DeCaro 12/19/2018
Contractor working on erosion control items. Their CESCL took a turbidity test of water leaving the site
and it was 197. They have recommended things for them to do to fix this and will re-check. Contractor
wants to either remove the material stockpile or flatten it down and cover it with Jute mat. Waiting to
hear which way they want to go.
Patrick DeCaro 12/18/2018
Did not see contractor working on the site today. The Catch Basin socks in the roadway across from
the project are full and holding water on the roadway.
Patrick DeCaro 12/17/2018
Did not see contractor working on the site today.Patrick DeCaro 12/14/2018
Did not see contractor on site but the plastic sheeting covering the material stockpile has been fixed.
Did not see any other erosion repair being made.
Patrick DeCaro 12/13/2018
Did not see contractor working on the site today. Stock pile of material has the plastic sheeting
blowing off.
Patrick DeCaro 12/12/2018
Did not see contractor working on the site today.Patrick DeCaro 12/11/2018
Did not see contractor working on the site today. Called them about when they will fulfill the
requirements set out by the CESCL. They said they would be coming out to work on them if the next
few days.
Patrick DeCaro 12/10/2018
Did not see contractor working on the site today. Looks like they have done some of the things
requested by their CESCL.
Patrick DeCaro 12/6/2018
Time did not allow for a site visit today.Patrick DeCaro 12/5/2018
Did not see contractor working on the site today. I have the recommendations from their CESCL
about what needs to be done to the site and have not seen anyone working on them yet.
Patrick DeCaro 12/4/2018
Did not see contractor working on the site today.Patrick DeCaro 12/3/2018
Saw contractor on site continuing to work on erosion control with quarry spalls and straw wattles.Patrick DeCaro 11/30/2018
Contractor on site today and they were having quarry spalls delivered to help shore up the site.Patrick DeCaro 11/29/2018
Saw contractor on site today and they were having quarry spalls delivered to help shore up the site.
They have also started to pump out the vault area. They are pumping the water to the top of the job
site and letting it filter through the straw back down to the excavated vault area. Took pictures of where
they had a discharge from the site yesterday.
Patrick DeCaro 11/28/2018
I checked the site this afternoon and saw no one there. The plastic covering the material pile is
starting to come off and I saw water approximately 1' from the top of the vault area excavation.
Patrick DeCaro 11/27/2018
Pat Miller called contractor this morning and told them to check erosion control on site (Specifically
the excavated area for their vault). I checked the site this afternoon and saw no one there. The plastic
covering the material pile is starting to come off and I saw water about 3' from the top of the vault area
excavation.
Patrick DeCaro 11/26/2018
Contractor was not working on site today. Stockpile remained covered with plastic and site is still
covered with straw.
Patrick DeCaro 11/9/2018
Contractor was not working on site today. Stockpile remained covered with plastic and site is still
covered with straw.
Patrick DeCaro 11/7/2018
Contractor was not working on site today. Stockpile remained covered with plastic and site is still
covered with straw.
Patrick DeCaro 11/6/2018
Contractor was not on the site today when I arrived. Called and left a message to tell them that the
material stockpile they had covered with plastic had blown off. Came back later that day and the
stockpile was re-covered.
Patrick DeCaro 11/5/2018
Contractor was not on the site today when I arrived. Called to tell them that the material stockpile they
had covered with plastic had blown off. The said they would send someone out to re-cover the
stockpile.
Patrick DeCaro 11/2/2018
Contractor is on site covering the material stock pile with plastic and spreading more straw for
erosion control.
Patrick DeCaro 11/1/2018
Contractor is installing chain link fence around the excavated vault for safety. Had a meeting today
with Rhohini (COR), the site owner, and the site contractor. Reminded them that per their permit as of
tomorrow all work (with the exception of Erosion Control Issues) will stop until April 1st.
Patrick DeCaro 10/31/2018
Contractor continues sloping the excavated area for their vault for safety until the chain link arrives.Patrick DeCaro 10/30/2018
Contractor is sloping the excavated area for their vault for safety until the chain link arrives.Patrick DeCaro 10/29/2018
Met contractor this morning and they still have not received the chain link fence for the excavated vault
area. They were going to lay the slope back so it is safer. They are also installing straw over the entire
job site for erosion control of the exposed material.
Patrick DeCaro 10/26/2018
Met contractor on site and they said they have ordered chain link fence for the excavated hole. I told
them that if it doesn't arrive and is installed by tomorrow, they need to slope the excavated hole so it is
safer. Also reminded them that the entire site still needs plastic or straw for erosion control.
Patrick DeCaro 10/25/2018
Contractor continues excavating for a vault and are now stockpiling the material. The contractor has
graded the entire area where they had previously hydro seeded so now it is bare material. I told them
it needs to be covered per our Winter erosion control standards. Also told them they needed chain
link fence to protect the open hole they have excavated for the vault.
Patrick DeCaro 10/24/2018
Contractor continues excavating for a vault and hauling off the material.Patrick DeCaro 10/23/2018
Contractor continues excavating for a vault and hauling off the material.Patrick DeCaro 10/22/2018
Contractor continues excavating for a vault and hauling off the material.Patrick DeCaro 10/19/2018
Contractor continues excavating for a vault and hauling off the material.Patrick DeCaro 10/18/2018
Contractor continues excavating for a vault and hauling off the material. Reminded them about
covering exposed dirt that will not be worked for 2 days.
Patrick DeCaro 10/17/2018
Contractor continues excavating for a vault and hauling off the material.Patrick DeCaro 10/16/2018
Contractor continues excavating for a vault and hauling off the material.Patrick DeCaro 10/15/2018
Contractor continues excavating for a vault and hauling off the material.Patrick DeCaro 10/12/2018
Contractor continues installing a Quarry Spall road and turn around area. They are also excavating for
a vault and hauling off the material. Reminded them about getting a sweeper on site for the track out.
Patrick DeCaro 10/11/2018
Contractor continues installing a Quarry Spall road and turn around area.Patrick DeCaro 10/10/2018
Contractor is installing a Quarry Spall road and turn around area.Patrick DeCaro 10/8/2018
Did not see contractor working on site today. Talked to them and they are planning to work next week
starting with a quarry spall access road and turn around area.
Patrick DeCaro 10/5/2018
Did not see contractor working on site today.Patrick DeCaro 10/4/2018
Did not see contractor working on site today.Patrick DeCaro 10/3/2018
Contractor is shooting elevations of the existing utilities that may be in conflict at the entrance of the
job site.
Patrick DeCaro 10/2/2018
Time did not allow a site visit today.Patrick DeCaro 10/1/2018
Contractor continues excavating for the rock wall at the back of the job site.Patrick DeCaro 9/27/2018
Contractor continues excavating for the rock wall at the back of the job site.Patrick DeCaro 9/26/2018
Contractor has started excavating for the rock wall at the back of the job site.Patrick DeCaro 9/25/2018
Contractor has covered the entire job site with Hydroseed.Patrick DeCaro 9/24/2018
Contractor is removing the cement concrete house foundation from the job site.Patrick DeCaro 9/21/2018
Did not see contractor working on the site today.Patrick DeCaro 9/20/2018
Contractor continues to remove material and brush from the job site. Reminded contractor about
hydro seeding before September 23 for wet season erosion control.
Patrick DeCaro 9/19/2018
Contractor continues to remove wood and brush from the job site.Patrick DeCaro 9/18/2018
Contractor is knocking down the existing house on the site and installing the last of their silt fence. I
reminded them about the erosion control for the wet season.
Patrick DeCaro 9/17/2018
Did not see contractor working on the site today.Patrick DeCaro 9/14/2018
Did not see contractor working on the site today.Patrick DeCaro 9/13/2018
Did not see contractor working on the site today.Patrick DeCaro 9/12/2018
Time did not allow for a site visit today.Patrick DeCaro 9/11/2018
Contractor continues to clear and grub job site.Patrick DeCaro 9/10/2018
Contractor continues to clear and grub job site.Patrick DeCaro 9/7/2018
Contractor went and got a water meter and fire hose for dust control of site. They are now continuing
to clear and grub site.
Patrick DeCaro 9/6/2018
Contractor was clearing and grubbing on site when I pulled up. I had to shut them down because of
excessive dust and no water truck or meter on site. I informed them not to work until some kind of
dust control was available.
Patrick DeCaro 9/5/2018
8/30/2018. Contractor has started clearing and grubbing on job site.
8/31/2018. Contractor continues clearing and grubbing. Also installing silt fence.
9/4/2018. Contractor continues clearing and grubbing. Also installing silt fence.
Patrick DeCaro 9/4/2018
October 24, 2022 Page 31 of 31