FIELD REPORT
Date Project Name Project No. Report No.
09/8/2022 Renton Elementary School 16 20180398E003 060
Location Municipality AESI Project Manager AESI Field Rep
1075 Duvall Ave NE Renton Bruce Guenzler, L.E.G. Samantha Parker
Permit No. Client/Owner Attn Requested By
B21004604 Renton School District No. 403 Ed Thomson Contractor
Engineer/Architect General Contractor Grading Contractor Weather
CPL / Hutteball + Oremus Cornerstone/Kyle Continental Dirt Contractors/ Jerry Jr. Sunny, 70’s
THE FOLLOWING WAS NOTED:
Associated Earth Sciences Inc. (AESI) was on-site in the morning for observation of Stormwater Detention Facility 2 progress, at the
request of Jerry Jr. of CDC.
Stormwater Detention Facility 2
While on-site, AESI observed progress on Stormwater Detention Facility 2. We noted that the installation of aggregate around the
stormwater chambers and 1’ above was still underway, progress moving from west to east. AESI observed the contractor using a
plate compactor to compact the top of the 1’ of installed aggregate. We observed that a separation liner had been placed over areas
where the placement of aggregate was complete, as per plan. See Figure 1 for location of observed area today.
Photo 1. Facility #2 progress observed today.
16
Date Project Name Project No. Report No.
09/08/2022 Renton ES 16 20180398E003 060
Page 2 of 2
FIELD REPORT
Figure 1. Sheet C2.0 The observed area of Stormwater Detention Facility #2. North is to the right of the figure.
Facility #2 – Missing section of PVC liner. Facility #2 – Installation of storm chambers underway.
Facility #2 – Aggregate
installed around storm chambers and 1’ of over
the top. Installation of separation liner over the
aggregate underway.