FIELD REPORT
Date Project Name Project No. Report No.
09/13/2022 Renton Elementary School 16 20180398E003 061
Location Municipality AESI Project Manager AESI Field Rep
1075 Duvall Ave NE Renton Bruce Guenzler, L.E.G. Samantha Parker
Permit No. Client/Owner Attn Requested By
B21004604 Renton School District No. 403 Ed Thomson Contractor
Engineer/Architect General Contractor Grading Contractor Weather
CPL / Hutteball + Oremus Cornerstone/Kyle Continental Dirt Contractors/ Jerry Jr. Sunny, 70’s
THE FOLLOWING WAS NOTED:
Associated Earth Sciences Inc. (AESI) was on-site in the morning for observation of asphalt placement and Stormwater Detention
Facility 2 progress, at the request of Jerry Jr. of CDC.
Asphalt Placement – Chelan Ave NE
While onsite, AESI observed placement of 4” inches of asphalt in a section across Chelan Ave NE. AESI observed that Olympic Paving
placed two 2” lifts of HMA (Figure 1). Puget Paving used multiple passes with a plate compactor and double drum vibratory roller to
compact each lift of HMA. The Rice Value provided by Olympic Paving was 158.4. AESI completed compaction tests on each lift that
exceeded the 92% minimum standard for compaction (Table 1). Based on our observations and test results, we found the HMA
placed today to be suitably compacted.
Table 1: HMA compaction Test Results
Test No. Location
Depth Below
Existing Road
Surface (in)
Rice
Value
Density
(pcf) Compaction % Pass/Fail
1 See Figure 1 -2 158.4 148.5 94 Pass
2 See Figure 1 -2 158.4 145.7 92 Pass
3 See Figure 1 -2 158.4 151.5 96 Pass
4 See Figure 1 0 158.4 152.1 96 Pass
5 See Figure 1 0 158.4 150.6 95 Pass
6 See Figure 1 0 158.4 148.6 94 Pass
Stormwater Detention Facility 2
While on-site, AESI observed progress on Stormwater Detention Facility 2. We noted that the installation of aggregate around the
stormwater chambers and 1’ above was completed for Phase 1 and that a separation liner had been placed over the top of the
aggregate, as per plan. We observed that the contractor had placed approximately 2’ of backfill over the completed section of the
facility. The backfill, consisting of onsite soils, was compacted with a large single drum vibratory roller. AESI used a density gauge to
test the newly backfilled section. Test results met or exceeded 95% compaction (Table 2). In our opinion, based on our observations
and test results, we found the observed area of backfill, to be firm and unyielding and suitable for support of planned hardscape areas. See Figure 2 for location of observed area today.
16
Date Project Name Project No. Report No.
09/13/2022 Renton ES 16 20180398E003 061
Page 2 of 4
FIELD REPORT
Table 2: Compaction Test Results
Test
No. Location
Approximate Backfill Depth
Relative to Existing
Ground Surface/
Top of Aggregate (ft)
Proctor
(ASTM D1557)
Dry Density
(pcf)
Moisture
%
Compaction
% Pass/Fail Notes
7 See Figure 2 0/+2 126.9/10.5 121.2 8.9 96 Pass
8 See Figure 2 0/+2 126.9/10.5 120.1 8.3 95 Pass
9 See Figure 2 0/+2 126.9/10.5 120.8 8.3 95 Pass
10 See Figure 2 0/+2 126.9/10.5 122.5 7.6 97 Pass
11 See Figure 2 0/+2 126.9/10.5 120.0 8.9 95 Pass
12 See Figure 2 0/+2 126.9/10.5 121.1 8.4 95 Pass
Figure 1. Sheet C2.1 The location of storm line backfill is indicated in blue.
Tests 1 & 4 Tests 2 & 5
Tests 3 & 6
16
Date Project Name Project No. Report No.
09/13/2022 Renton ES 16 20180398E003 061
Page 3 of 4
FIELD REPORT
Figure 2. Sheet C2.0 The observed area of Stormwater Detention Facility #2. North is to the right of the figure.
Photo 1. Facility #2 progress observed today.
Facility #2 – Missing section of PVC liner. Facility #2 – Installation of storm chambers, aggregate around storm chambers
and 1’ of over the top and separation liner
completed.
Facility #2 – Area of
backfill observed today. 12
8 9 7
10
11
16
Date Project Name Project No. Report No.
09/13/2022 Renton ES 16 20180398E003 061
Page 4 of 4
FIELD REPORT
Photo 2. The contractor compacting HMA with a double drum vibratory roller.