FIELD REPORT
Date Project Name Project No. Report No.
08/15/2022 Renton Elementary School 16 20180398E003 050
Location Municipality AESI Project Manager AESI Field Rep
1075 Duvall Ave NE Renton Bruce Guenzler, L.E.G. Samantha Parker
Permit No. Client/Owner Attn Requested By
B21004604 Renton School District No. 403 Ed Thomson Contractor
Engineer/Architect General Contractor Grading Contractor Weather
CPL / Hutteball + Oremus Cornerstone/Kyle Continental Dirt Contractors/ Jerry Jr. Sunny, 80’s
THE FOLLOWING WAS NOTED:
Associated Earth Sciences Inc. (AESI) was onsite in the afternoon to observe progress on detention facilities #1A and #1B.
Detention Facilities #1A and #1B
AESI observed, that installation of base aggregate had been completed and placement of stormwater chambers was underway in
Facility #1B. In Facility #1A, CDC had completed placement of aggregate around and 0.5’ above stormwater chambers. CDC informed
AESI that a plate compactor had been used to compact the top 0.5’ of aggregate and a Telebelt was used for aggregate placement.
The installation of geotextile fabric over the top of the aggregate was partially completed. See Figure 1 for location of observed
areas.
Photo 1. Progress observed in Facility #1B.
16
Date Project Name Project No. Report No.
08/15/2022 Renton ES 16 20180398E003 050
Page 2 of 2
FIELD REPORT
Photo 2. Progress observed in Facility #1A.
From sheet C2.1 Facilities #1A and #1B progress observed today. North is to the right.
Facility #1B – Leveling
pad placement complete
and chamber installation
underway.
Facility #1A – Placement
of aggregate around and
above chambers
complete and installation
of geotextile fabric
underway.