FIELD REPORT
Date Project Name Project No. Report No.
08/18/2022 Renton Elementary School 16 20180398E003 052
Location Municipality AESI Project Manager AESI Field Rep
1075 Duvall Ave NE Renton Bruce Guenzler, L.E.G. Samantha Parker
Permit No. Client/Owner Attn Requested By
B21004604 Renton School District No. 403 Ed Thomson Contractor
Engineer/Architect General Contractor Grading Contractor Weather
CPL / Hutteball + Oremus Cornerstone/Kyle Continental Dirt Contractors/ Jerry Jr. Cloudy, 80’s
THE FOLLOWING WAS NOTED:
Associated Earth Sciences Inc. (AESI) was onsite in the morning to observe progress on Detention Facility #1B. Upon arrival, we met
with Jerry Jr. of CDC.
Detention Facility #1B
AESI observed that placement of stormwater chambers was complete in Facility #1B. While onsite, we observed a Telebelt being
used to place aggregate around and 0.5’ above the stormwater chambers. Approximately half of the aggregate had been installed at
the time of our visit. CDC informed AESI that they plan to compact the top 0.5’ of aggregate with a plate compactor. In our opinion,
based on our observations, the installation of Detention Facility #1B appears consisted with project plans and our recommendations.
See Figure 1 for location of observed areas.
Photos 1. Progress observed in Facility #1B.
16
Date Project Name Project No. Report No.
08/18/2022 Renton ES 16 20180398E003 052
Page 2 of 2
FIELD REPORT
From sheet C2.1 Facility #1B progress observed today. North is to the right.
Facility #1B – Chamber
installation complete and aggregate installation
underway.