HomeMy WebLinkAboutQuestions & Answers No. 3 (12-12-2022)1 of 1 Park Ave N. Extension December 12, 2022 The responses to bidder inquiries, unless incorporated into a formal addendum to the contract, are not part of the contract and are provided for the bidders’ convenience only. The responses may be considered along with all other information furnished to prospective bidders for the purpose of bidding on the project. The use of information provided in the responses to bidder inquiries is not to be construed in any way as a waiver of the provisions nor excuse the contractor from full compliance with the contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given and any such subsequent response or addenda should be taken into consideration when submitting a bid for the project. Questions and Answers No. 3 1.Question: Plan sheet IL1 includes the luminaire schedule which refers to plan sheet ST2 for the foundation design. On IL1 construction note #1 calls out that the poles IL1 & IL5 shall match Renton std 117.1 Then when you review plan sheet ST2 for the foundation design it notes that IL1 and IL5 shall use foundation design TYPE 1A 2 of 1 Foundation type 1A refers to Renton Standard 117.1A, which is a chambered pole with a 6 bolt base plate compared to the 117.1 pole which is a non-chambered pole standard 4 bolt base plate shown. My question is, which pole is required 117.1 or 117.1A? Answer: The pole shown on Renton Standard 117.1 is required. All poles shall use 4 anchor bolts. Poles IL1 and IL5 shall have a foundation per Renton Standard 117.1A (to accommodate future loading). End of Questions and Answers No. 3