HomeMy WebLinkAboutChange Order - 01CITY OF RENTON
Parks and Recreation Department
CONTRACT CHANGE ORDER AGREEMENT
CONTRACT: CAG-22-365 Vegetation Management at Multiple Sites
Date: U/14/2022
CO#l
CONTRACTOR: Tim's Complete Landscape Management
CHANGE ORDER: 1 (per Attachment "A-1")
SUMMARY OF PROPOSED CHANGE: Labor and materials to perform landscaping
Reason/Justification:
Initial request was to perform landscaping on a portion of a line of shrubs at Liberty Park. When this
was complete Parks staff preferred that the entire line of shrubs be landscaped. This change order
adds that portion of the line of shrubs that had not been included in the initial scope of work.
DESCRIPTION:
Item Qty. Description Unit Price Amount
No. w/WSST
1 90' Trim and skirt arborvitae plants $ 19.20 $ 1,728.00
Total this Change Order: $ 1,728.00
ORIGINAL CONTRACT CURRENT CONTRACT NET CHANGE REVISED CONTRACT
AMOUNT (W/ WSST) AMOUNT THIS ORDER (W/ WSST) TOTAL AFTER CHANGE
$ 24,849.57 $ 24,849.57 $ 1,902.53 $ 26,752.10
The payment specified and agreed to in this change order includes every claim by the contractor for any
extra payment with respect to the work described in this change order. The work covered by this change
order must be performed under the same terms and conditions as that included in the original
aereement. All of the other terms of the ori11inal aereement remain in effect.
SIGNATURES: --t2.//'l/?e Contractor: Date:
"'-"• o.m,-. cm
Project Manager: � f-l� Date 12/19/2022
Approved By: Date: 1 2/2-0 Z.2..
CAG-22-365, CO #1-22