HomeMy WebLinkAboutAdden 4Supplemental Agreement
Number
Organization and Address
Phone:
Original Agreement Number
Project Number Execution Date Completion Date
Project Title New Maximum Amount Payable
Description of Work
The Local Agency of
desires to supplement the agreement entered in to with
and executed on DQGLGHQWL¿HGDV$JUHHPHQW1R
$OOSURYLVLRQVLQWKHEDVLFDJUHHPHQWUHPDLQLQHႇHFWH[FHSWDVH[SUHVVO\PRGL¿HGE\WKLVVXSSOHPHQW
The changes to the agreement are described as follows:
I
Section 1, SCOPE OF WORK, is hereby changed to read:
II
6HFWLRQ,97,0()25%(*,11,1*$1'&203/(7,21LVDPHQGHGWRFKDQJHWKHQXPEHURIFDOHQGDUGD\V
for completion of the work to read:
III
6HFWLRQ93$<0(17VKDOOEHDPHQGHGDVIROORZV
DVVHWIRUWKLQWKHDWWDFKHG([KLELW$DQGE\WKLVUHIHUHQFHPDGHDSDUWRIWKLVVXSSOHPHQW
If you concur with this supplement and agree to the changes as stated above, please sign in the Appropriate
VSDFHVEHORZDQGUHWXUQWRWKLVRႈFHIRU¿QDODFWLRQ
By:By:
Consultant Signature Approving Authority Signature
Date
DOT Form 140-063
Revised 09/2005
City of Renton
WSP USA, Inc. (formerly BergerABAM Inc.)
06/22/2017 CAG-17-074
This Supplemental Agreement does not change the Scope of Work.
Change contract completion date from Dec. 31, 2022 to Dec. 31, 2025.
This Supplement Agreement does not change the maximum amount payable.
4
CAG-17-074
WSP USA, Inc.
33301 Ninth Avenue S., Suite 300
Federal Way, WA 98003
206-431-2300
TED4003843 06/22/2017 12/31/2025
NE 31st St Bridge Replacement $322,364 (no change)
Extend the contract completion date.
WSP USA, Inc. Martin Pastucha, Public Works Administrator
CAG-17-074, Adden #4-22