HomeMy WebLinkAboutCO 5PublicWorks FacilitiesDivision CONTRACTNO:CAGͲ21Ͳ180 CONO. 5 CONTRACTCHANGEORDER(CO)PROJECTTITLE:FAMILYFIRSTCOMMUNITYCENTER TO: COMERGC,Inc. (CONTRACTOR) Description Amount CCD23ͲWindowRevisions 3,022.00$ CCD30ͲApplianceAdd 5,601.00$ CCD31ͲAddFenceEnclosure 2,116.00$ CCD32ͲIncreasedPipingSize 4,209.00$ CCD33ͲAdditionalOverexAboveAllowance 11,726.00$ CCD34ͲAdditionalAsphaltDemo/Replace 13,980.00$ CCD35ͲHangersatFallͲArrests 7,519.00$ CCD37ͲAdditionalDemoAsphaltforADARamps 14,799.00$ Subtotal 62,972.00$ WSST 6,360.17$ TOTALTHISCHANGEORDER 69,332.17$ CONTRACTSUM: 69,332.17$ (WASHINGTONSTATESALESTAXINCLUDED) CONTRACTTIME: 0 CALENDARDAYS CONTRACTSUMMARY(InternalUseOnly) ORIGINALCONTRACTSUMw/WSST 12,474,330.00$ PREVIOUSADDITIONS/DELETIONS 124,113.53$ PREVIOUSTOTAL 12,598,443.53$ CHANGEAMOUNTTHISCHANGEORDER 69,332.17$ REVISEDCONTRACTTOTAL 12,667,775.70$ PERCENTTOTALCHANGEFROMORIGINAL 1.55% NOTICETOPROCEEDDATE February25,2022 PREVIOUSCONTRACTCALENDARDAYS 0 PREVIOUSSUBSTANTIALCOMPLETIONDATE February25,2023 REVISEDCONTRACTCALENDARDAYSTHISCHANGEORDER 0 CURRENTSUBSTANTIALCOMPLETIONDATE February25,2023 ArchitectAcknowledgementDate ContractorAcknowledgementDate AUTHORIZINGSIGNATURE DATE ThefollowingmutuallyagreedtoandOwnerapprovedContractChangeDirective(s)areherebyincorporatedbyreferenceintothecontract. Theforegoingamountcoverseverythingrequiredinconnectionwiththechange.Allotherprovisionsofthecontractremaininfullforceand effect. TheCityofRentonherebyacceptstheforegoingchanges.ThisformalacceptanceconstitutesaChangetothecontractonlywhenauthorizing signatureisaffixed.InvoicesincorporatingthisChangeOrderconstituteacceptancebytheContractorastotalreimbursementduein connectionwiththisChangeOrder. OF: NO CHANGE INCREASE DECREASE NO CHANGE INCREASE DECREASE          CAG-21-180, CO #5-23 1/11/2023 PUBLIC WORKS Facilities Division Project No:CCD # 23 CONSTRUCTION CHANGE DIRECTIVE Project Name: (CCD) (CONTRACTOR) You are directed to prepare a cost proposal for the work described below and/or detailed on the attachment referred to: SOURCE OF CHANGE: DATE PROPOSAL REQUIRED:8/22/22 CHANGE ORIGINATED BY: Architect (14 days from Request Date, unless other date agreed to) PROPOSAL REQUESTED BY: Contractor ARCHITECTCOR PM WE AGREE TO PERFORM ALL CHANGE IN THE WORK DESCRIBED IN THE PROPOSAL REQUEST FOR: CONTRACT SUM: (WASHINGTON STATE SALES TAX EXCLUDED) In accordance with the general condition, Cost Estimate Detail Sheet(s) are attached hereto. CONTRACT TIME: OF 0 CALENDAR DAYS BY: CONTRACTOR SIGNATURE DATE We have carefully examined this proposal and find the cost to be reasonable.Therefore, we recommend acceptance. ARCHITECT DATE HEALTHPOINT DATE City of Renton Authorized Signature To be utilized for changes requested by HealthPoint Armondo Pavone, Mayor DATE 3,022.00$ CAG 21Ͳ180 Family First Community Center TO: Comer GC, Inc. The foregoing amount covers everything required in connection with the change. All other provisions of the contract remain in full force and effect. We understand that this proposal does not constitute authorization to proceed with the specified changes in the work until incorporation of this COP into a Change Order by the City of Renton. Revise and add window caulking 05/25/22Proposal Request Date: EXPLANATION: Per aboive TO: Meredith Everist TO:Russ Woodruff Three Thousand and Twenty Two WE AGREE CONTRACT TO:Mered DATE PROP (14 days from You are direct SOURCE OF C CONSTRUC TO:Comer Revise and EXPLANATIO NO CHANGE INCREASE DECREASE NO CHANGE INCREASE DECREASE Design Contractor Owner Code/AHJUnknown Conditions HealthPoint Other 11/2/2022 COMER GC, Inc.11/02/2022          ATTEST: Jason A. Seth, City Clerk 1/11/2023                         !"#$%!" & ' !(!$    ! "#  ')"'')!!"    $    % $$ &     '  '   $   & $ %  $    '  $(  $   $   ) ' ' (  $%     $    %   $  & *)  +*    &  ,$$ * %    $ '  $  '-    $#   (      (   ' (   %    *)  +*    &      %  (  ($           %   %  '-  ).  /.  *) 0 1!  ). .) *) 0 2 2 * ). 34/" 5 *) 0 6 &  0 7!2 * )8 9 : 5: ");/ <2=> 0 77 4).* +, 9 * : 4*)5* *)  0 ?262-- !".  0@-- 0@-- &   0 ?262  )8 9 : 5: ");/ )5 4*)5* *) <=> 0 ?2? 4).* /00, ; )5: <+* )5.A> 0 !277 + +. /545* 0 66!2 9 4 .. /545* 0 1?? / 4/.: B /C /545* 0 6 6 4).* 121,30 !."!"4!5 * /, *)5* / :D4 56!!"'!  77". .  /8, *)5*) 5 5: /. 9::.- *( "# % :             *)" 5 ;<=.  /8,"# ')"'')!!"!!""8"  >&  . ?) 6   @6 .&   @.& @A. 6 .& @A. .& ?6 6 .& ?6  .& . @.&        !"#$ %& '!'(&   )*(%%     +((**,+((* -%    . @.&                                                                  1 Russ Woodruff From:Meredith Everist <everistm@baylisarchitects.com> Sent:Tuesday, October 18, 2022 10:16 AM To:Russ Woodruff Cc:16-0996 Family First Community Center Subject:FW: FFCC - CI-023R1 - Additional Caulking & Flashings @ Fiberglass Windows per Submittal Review Attachments:FFCC - CI-023R1 - Additional Caulking & Flashings @ Fiberglass Windows per Submittal Review.pdf HiRuss,thisistheCOthatgotwhittledfrom$12kdownto$3kafterdiscussionswithMetroGlassandCascadia.Ithink thisaddedflashingisagoodapproachforconcealingacaulkjointandgivingthisareaamorefinishedlook.Pleaselet meknowifyouhavequestionsorwanttoreviewittogether.  Thanks,Meredith  Meredith Everist | AIA | NOMA | LEED AP BD+C Principal Pronouns: she | her 10801 Main Street, # 110 | Bellevue, WA 98004 O: 425.454.0566 D: 425.679.5205 F: 425.453.8013 everistm@baylisarchitects.com | BaylisArchitects.com Facebook | LinkedIn | Houzz  From:LukeComer<luke@comergc.com> Sent:Monday,August22,202211:50AM To:MeredithEverist<everistm@baylisarchitects.com>;'RussWoodruffͲCityofRenton'<rwoodruff@rentonwa.gov> Cc:'TimComer'<tim@comergc.com>;'JonScofield'<jon@comergc.com>;16Ͳ0996FamilyFirstCommunityCenter<16Ͳ 0996@baylisarchitects.com> Subject:RE:FFCCͲCIͲ023R1ͲAdditionalCaulking&Flashings@FiberglassWindowsperSubmittalReview  Team– AttachedisrevisedpricingwhichessentiallysummarizesthemeetingwehadwithCascadia.Metro’sCORͲ001 getsremovedandvoidedandthisisonlyfortheCORͲ002costsperthenotebelow.Letmeknowifyouhaveany questions.    Thank you,  Luke Comer C:425Ͳ765Ͳ4118IP:425Ͳ636Ͳ8934IF:425Ͳ285Ͳ9785   CAUTION: This email originated from outside the City of Renton. Do not click links, reply or open attachments unless you know the content is safe.           2 From:LukeComer<luke@comergc.com> Sent:Thursday,July7,20222:07PM To:'MeredithEverist'<everistm@baylisarchitects.com>;'RussWoodruffͲCityofRenton'<rwoodruff@rentonwa.gov> Cc:'TimComer'<tim@comergc.com>;'JonScofield'<jon@comergc.com>;'16Ͳ0996FamilyFirstCommunityCenter'<16Ͳ 0996@baylisarchitects.com> Subject:RE:FFCCͲCIͲ023ͲAdditionalCaulking&Flashings@FiberglassWindowsperSubmittalReview  Soundsgood,I’dliketoextendittoMetroaswellsinceCascadiaissubcontractedthroughthem.Letmeknowtiming, andIwillletthemknowaswell.  Thank you,  Luke Comer C:425Ͳ765Ͳ4118IP:425Ͳ636Ͳ8934IF:425Ͳ285Ͳ9785   From:MeredithEverist<everistm@baylisarchitects.com> Sent:Thursday,July7,20221:13PM To:LukeComer<luke@comergc.com>;'RussWoodruffͲCityofRenton'<rwoodruff@rentonwa.gov> Cc:'TimComer'<tim@comergc.com>;JonScofield<jon@comergc.com>;16Ͳ0996FamilyFirstCommunityCenter<16Ͳ 0996@baylisarchitects.com> Subject:RE:FFCCͲCIͲ023ͲAdditionalCaulking&Flashings@FiberglassWindowsperSubmittalReview  HILuke,IamsettingupameetingwithJoyceandNathanwithCascadiatoreviewthedetails.Oncethetimeissetup,I willletyouknow.  Thanks,Meredith  Meredith Everist | AIA | NOMA | LEED AP BD+C Principal Pronouns: she | her 10801 Main Street, # 110 | Bellevue, WA 98004 O: 425.454.0566 D: 425.679.5205 F: 425.453.8013 everistm@baylisarchitects.com | BaylisArchitects.com Facebook | LinkedIn | Houzz  From:LukeComer<luke@comergc.com> Sent:Thursday,July7,202211:07AM To:'RussWoodruffͲCityofRenton'<rwoodruff@rentonwa.gov>;MeredithEverist<everistm@baylisarchitects.com> Cc:'TimComer'<tim@comergc.com>;JonScofield<jon@comergc.com> Subject:FFCCͲCIͲ023ͲAdditionalCaulking&Flashings@FiberglassWindowsperSubmittalReview  Russ/Meredith– Attachedisformalpricing(FFCCͲCIͲ023ͲAdditionalCaulking&Flashings@FiberglassWindowsperSubmittal Review),relatedtothesetwoitemsnotedbelow.IbelievethereistimetodirectMetro/Cascadiatonotinstallperthe modifieddetailsfromtheshopsifdesired,inparticularthedetailfromsheet5.1,asthatrelatestocaulking.Thedetail from5.2IbelievewillneedsomesortofclosureflashingtocloseoffthislocationbetweenSF’s.          3  Thank you,  Luke Comer C:425Ͳ765Ͳ4118IP:425Ͳ636Ͳ8934IF:425Ͳ285Ͳ9785   From:LukeComer<luke@comergc.com> Sent:Wednesday,July6,20229:47AM To:'RussWoodruffͲCityofRenton'<rwoodruff@rentonwa.gov>;'MeredithEverist'<everistm@baylisarchitects.com> Cc:'TimComer'<tim@comergc.com>;JonScofield<jon@comergc.com> Subject:FFCCCascadia/MetroAddedScopeperSubmittalReview  Russ/Meredith– Asdiscussed,belowarethedetailsMetrohassubmittedcostsfor,persubmittalreview.SummarizedROMSfor eachitem,whichlookslikewillbelessthanmyROMfromthechangelog.  Addedcaulkper2&4/5.1isapproximately~$8,500  Addedgenericflashingper5&6/A5.2isapproximately~$4,000            4 Thank you,  Luke Comer C:425Ͳ765Ͳ4118IP:425Ͳ636Ͳ8934IF:425Ͳ285Ͳ9785            PUBLIC WORKS Facilities Division Project No:CCD # 30 CONSTRUCTION CHANGE DIRECTIVE Project Name: (CCD) (CONTRACTOR) You are directed to prepare a cost proposal for the work described below and/or detailed on the attachment referred to: SOURCE OF CHANGE: DATE PROPOSAL REQUIRED:11/2/22 CHANGE ORIGINATED BY: Contractor (14 days from Request Date, unless other date agreed to) PROPOSAL REQUESTED BY: Architect ARCHITECTCOR PM WE AGREE TO PERFORM ALL CHANGE IN THE WORK DESCRIBED IN THE PROPOSAL REQUEST FOR: CONTRACT SUM: (WASHINGTON STATE SALES TAX EXCLUDED) In accordance with the general condition, Cost Estimate Detail Sheet(s) are attached hereto. CONTRACT TIME: OF 0 CALENDAR DAYS BY: CONTRACTOR SIGNATURE DATE We have carefully examined this proposal and find the cost to be reasonable.Therefore, we recommend acceptance. ARCHITECT DATE HEALTHPOINT DATE City of Renton Authorized Signature To be utilized for changes requested by HealthPoint CITY OF RENTON DATE Family First Community Center TO: Comer GC, Inc. The foregoing amount covers everything required in connection with the change. All other provisions of the contract remain in full force and effect. We understand that this proposal does not constitute authorization to proceed with the specified changes in the work until incorporation of this COP into a Change Order by the City of Renton. Add wall oven in demonstration kitchen 06/07/22Proposal Request Date: EXPLANATION: Per above TO: Meredith Everist TO:Russ Woodruff FiveͲThousand SixͲHundred and One Dollars 5,601.00$ CAG 21Ͳ180 WE AGREE CONTRAC TO:Mered DATE PROP (14 days from You are direct SOURCE OF CONSTRU TO:Come Add wall o EXPLANATI NO CHANGE INCREASE DECREASE NO CHANGE INCREASE DECREASE Design Contractor Owner Code/AHJUnknown Conditions HealthPoint Other 11/16/2022 COMER GC, Inc.11/28/2022                               *)" 5 567#  )+"# $%$&%&&  89  # :% 2   ;2 #9   ;#9 ;<# 2 #9 ;<# #9 :2 2 #9 :2  #9 # ;#9                                                           !"##              !$%#        $ % &'()"%*       % &*            +              ,#-,% .            # ;#9                  11/2/22, 12:16 PM GE Profile™ 30" Smart Built-In Convection Single Wall Oven with No Preheat Air Fry and Precision Cooking - PTS7000SNSS - … https://www.geappliances.com/appliance/GE-Profile-30-Smart-Built-In-Convection-Single-Wall-Oven-with-No-Preheat-Air-Fry-and-Precision-Cooking-P…1/8 Model #: PTS7000SNSS GE Profile™ 30" Smart Built-In Convection Single Wall Oven with No Preheat Air Fry and Precision Cooking 4.6 (570) $3,332.00 Starting at $162/mo with . Prequalify now Built-In WiFi, Powered by SmartHQ App GE Profile Connect + No Preheat Air Fry Dimensions: 28 5/8 H x 29 3/4 W x 26 3/4 D Learn More > Color: Stainless Steel  FIND STORES ABOUT THIS PRODUCT Built-In WiFi, Powered by SmartHQ App Feedback         11/2/22, 12:16 PM GE Profile™ 30" Smart Built-In Convection Single Wall Oven with No Preheat Air Fry and Precision Cooking - PTS7000SNSS - … https://www.geappliances.com/appliance/GE-Profile-30-Smart-Built-In-Convection-Single-Wall-Oven-with-No-Preheat-Air-Fry-and-Precision-Cooking-P…6/8 Color Appearance Stainless Steel Oven Door Features Big View Oven Window Handle Brushed Stainless Designer Style Installation Above Warming Drawer Side-by-Side Under Built-In Advantium Under Built-In Microwave Under Cooktop Undercounter CAPACITY Total Capacity (cubic feet) 5.0 cu ft FEATURES Configuration Single Oven Cooking System True European Convection with Direct Air Oven Cleaning Type Self-Clean with Steam Clean Option Cleaning Time Va riable with Delay Clean Option Oven Cooking Modes Convection Bake Convection Bake Multi-Rack Convection Broil Hi/Lo Convection Roast No Preheat Air Fry Precision Cooking Modes Thermal Bake Thermal Broil Hi/Lo Self-Clean Oven Door Lock Automatic Control Type 7" Full-Color To uch LCD Screen Oven Features 10-Pass Bake Element 10-Pass Dual Broil Element Closed Door Broiling Feedback         11/2/22, 12:16 PM GE Profile™ 30" Smart Built-In Convection Single Wall Oven with No Preheat Air Fry and Precision Cooking - PTS7000SNSS - … https://www.geappliances.com/appliance/GE-Profile-30-Smart-Built-In-Convection-Single-Wall-Oven-with-No-Preheat-Air-Fry-and-Precision-Cooking-P…7/8 Oven Rack Features 1 Self-Clean Heavy-Duty Flat Oven Rack 1 Self-Clean Roller Rack 6 Embossed Rack Positions Product Type Single Oven Oven Control Features 12-Hour Shut-Off Capability Audible Preheat Signal Auto Recipe Conversion Certified Sabbath Mode Control Lock Capability Cook Time C° or F° Programmable Delay Time Electronic Clock & Kitchen Timer Mis-Wire Detection Proof Mode Remote Enabled Temperature Probe Wa rm Mode WiFi Connect Built-In Connected Capabilities Amazon Alexa Fresco IFTTT Innit Sonos The Google Assistant Cooking Technology Convection Fuel Type Electric Oven Interior 2 Halogen Interior Oven Lights Black Gloss Finish Hidden Bake Sabbath Mode Ye s POWER / RATINGS Amp Rating at 208V 20 Amp Rating at 240V 20 Bake Wattage 2850W Broiler Wattage 4300W Feedback         11/2/22, 12:16 PM GE Profile™ 30" Smart Built-In Convection Single Wall Oven with No Preheat Air Fry and Precision Cooking - PTS7000SNSS - … https://www.geappliances.com/appliance/GE-Profile-30-Smart-Built-In-Convection-Single-Wall-Oven-with-No-Preheat-Air-Fry-and-Precision-Cooking-P…8/8 Convection Wattage 2400W KW Rating at 208V 3.2 KW Rating at 240V 4.2 WARRANTY Parts Wa rranty Limited 1-year entire appliance Labor Wa rranty Limited 1-year entire appliance Wa rranty Notes See written warranty for full details WEIGHTS & DIMENSIONS Net Weight 161.0 lb Overall Height 28.625 in Overall Width 29.75 in Overall Depth 26.75 in Cabinet Width 30.0 in Cutout Dimensions (w x h x d) (in.) 28-5/8 x 27-5/16 x 23-1/2 Oven Interior Dimensions (W x H x D) (in.) 25 x 17-3/8 x 20-1/4 Feedback         1 Russ Woodruff From:Meredith Everist <everistm@baylisarchitects.com> Sent:Wednesday, November 16, 2022 12:17 PM To:Russ Woodruff Cc:16-0996 Family First Community Center Subject:FW: FFCC - CI-030 - Appliance Change Added Wall Oven Attachments:FFCC - CI-030 - Appliance Change Added Wall Oven.pdf HIRuss,IreviewedthisChangeItemforthewallovenandtakenoexceptions.  Thanks,Meredith  Meredith Everist | AIA | NOMA | LEED AP BD+C Principal Pronouns: she | her 10801 Main Street, # 110 | Bellevue, WA 98004 O: 425.454.0566 D: 425.679.5205 F: 425.453.8013 everistm@baylisarchitects.com | BaylisArchitects.com Facebook | LinkedIn | Houzz  From:LukeComer<luke@comergc.com> Sent:Wednesday,November2,202212:36PM To:'RussWoodruffͲCityofRenton'<rwoodruff@rentonwa.gov>;MeredithEverist<everistm@baylisarchitects.com> Cc:'TimComer'<tim@comergc.com>;JonScofield<jon@comergc.com> Subject:FFCCͲCIͲ030ͲApplianceChangeAddedWallOven  Team– Attachedispricingfor:FFCCͲCIͲ030ͲApplianceChangeAddedWallOven,whichrelatestotheaddedwall ovenperthedivision11submittalreviewoftheresidentialappliances.Thepricingincludesfurnishingandinstallingthe newGEProfileWallOven.  Thank you,  Luke Comer C:425Ͳ765Ͳ4118IP:425Ͳ636Ͳ8934IF:425Ͳ285Ͳ9785  CAUTION: This email originated from outside the City of Renton. Do not click links, reply or open attachments unless you know the content is safe.           PUBLIC WORKS Facilities Division Project No:CCD # 31 CONSTRUCTION CHANGE DIRECTIVE Project Name: (CCD) (CONTRACTOR) You are directed to prepare a cost proposal for the work described below and/or detailed on the attachment referred to: SOURCE OF CHANGE: DATE PROPOSAL REQUIRED:7/11/22 CHANGE ORIGINATED BY: Architect (14 days from Request Date, unless other date agreed to) PROPOSAL REQUESTED BY: Contractor ARCHITECTCOR PM WE AGREE TO PERFORM ALL CHANGE IN THE WORK DESCRIBED IN THE PROPOSAL REQUEST FOR: CONTRACT SUM: (WASHINGTON STATE SALES TAX EXCLUDED) In accordance with the general condition, Cost Estimate Detail Sheet(s) are attached hereto. CONTRACT TIME: OF 0 CALENDAR DAYS BY: CONTRACTOR SIGNATURE DATE We have carefully examined this proposal and find the cost to be reasonable.Therefore, we recommend acceptance. ARCHITECT DATE HEALTHPOINT DATE City of Renton Authorized Signature To be utilized for changes requested by HealthPoint CITY OF RENTON DATE 2,116.00$ CAG 21Ͳ180 Family First Community Center TO: Comer GC, Inc. The foregoing amount covers everything required in connection with the change. All other provisions of the contract remain in full force and effect. We understand that this proposal does not constitute authorization to proceed with the specified changes in the work until incorporation of this COP into a Change Order by the City of Renton. Add chainlink fence enclosure to server/network area in Fitness Storage 07/08/22Proposal Request Date: EXPLANATION: Per above TO: Meredith Everist TO:Russ Woodruff TwoͲThousand OneͲHundred Sixteen WE AGREE CONTRACT TO:Mered DATE PROP (14 days from You are direct SOURCE OF C CONSTRUC TO:Comer Add chainl EXPLANATIO NO CHANGE INCREASE DECREASE NO CHANGE INCREASE DECREASE Design Contractor Owner Code/AHJUnknown Conditions HealthPoint Other 11/2/2022 COMER GC, Inc.11/2/2022          $2,116.00                                              PUBLIC WORKS Facilities Division Project No:CCD # 32 CONSTRUCTION CHANGE DIRECTIVE Project Name: (CCD) (CONTRACTOR) You are directed to prepare a cost proposal for the work described below and/or detailed on the attachment referred to: SOURCE OF CHANGE: DATE PROPOSAL REQUIRED:11/2/22 CHANGE ORIGINATED BY: Contractor (14 days from Request Date, unless other date agreed to) PROPOSAL REQUESTED BY: Architect ARCHITECTCOR PM WE AGREE TO PERFORM ALL CHANGE IN THE WORK DESCRIBED IN THE PROPOSAL REQUEST FOR: CONTRACT SUM: (WASHINGTON STATE SALES TAX EXCLUDED) In accordance with the general condition, Cost Estimate Detail Sheet(s) are attached hereto. CONTRACT TIME: OF 0 CALENDAR DAYS BY: CONTRACTOR SIGNATURE DATE We have carefully examined this proposal and find the cost to be reasonable.Therefore, we recommend acceptance. ARCHITECT DATE HEALTHPOINT DATE City of Renton Authorized Signature To be utilized for changes requested by HealthPoint CITY OF RENTON DATE 4,209.00$ CAG 21Ͳ180 Family First Community Center TO: Comer GC, Inc. The foregoing amount covers everything required in connection with the change. All other provisions of the contract remain in full force and effect. We understand that this proposal does not constitute authorization to proceed with the specified changes in the work until incorporation of this COP into a Change Order by the City of Renton. Revisions to piping to support the systems 08/24/22Proposal Request Date: EXPLANATION: Per above TO: Meredith Everist TO:Russ Woodruff FourͲThousand TwoͲHundred and Nine Dollars WE AGREE CONTRAC TO:Mered DATE PROP (14 days from You are direct SOURCE OF CONSTRU TO:Come Revisions EXPLANATI NO CHANGE INCREASE DECREASE NO CHANGE INCREASE DECREASE Design Contractor Owner Code/AHJUnknown Conditions HealthPoint Other COMER GC, Inc.11/8/2022 11/8/2022                                                                                                                                                 PUBLIC WORKS Facilities Division Project No:CCD # 33 CONSTRUCTION CHANGE DIRECTIVE Project Name: (CCD) (CONTRACTOR) You are directed to prepare a cost proposal for the work described below and/or detailed on the attachment referred to: SOURCE OF CHANGE: DATE PROPOSAL REQUIRED:11/30/22 CHANGE ORIGINATED BY: Geotechincal Engineer (14 days from Request Date, unless other date agreed to) PROPOSAL REQUESTED BY: Contractor ARCHITECTCOR PM WE AGREE TO PERFORM ALL CHANGE IN THE WORK DESCRIBED IN THE PROPOSAL REQUEST FOR: CONTRACT SUM: (WASHINGTON STATE SALES TAX EXCLUDED) In accordance with the general condition, Cost Estimate Detail Sheet(s) are attached hereto. CONTRACT TIME: OF 0 CALENDAR DAYS BY: CONTRACTOR SIGNATURE DATE We have carefully examined this proposal and find the cost to be reasonable.Therefore, we recommend acceptance. ARCHITECT DATE HEALTHPOINT DATE City of Renton Authorized Signature To be utilized for changes requested by HealthPoint CITY OF RENTON DATE 11,726.00$ CAG 21Ͳ180 Family First Community Center TO: Comer GC, Inc. The foregoing amount covers everything required in connection with the change. All other provisions of the contract remain in full force and effect. We understand that this proposal does not constitute authorization to proceed with the specified changes in the work until incorporation of this COP into a Change Order by the City of Renton. OverͲexcavation of unsuitable soils as required by the geotechnical engineer.Amount of material was over the allowance amounts per contract.Unit costs conform to contract amounts. 07/13/22Proposal Request Date: EXPLANATION: Per above TO: Meredith Everist TO:Russ Woodruff ElevenͲThousand SevenͲHundred and Twenty Six Dollars WE AGREE CONTRAC TO:Mered DATE PROP (14 days from You are direct SOURCE OF OverͲexca over the a EXPLANATI CONSTRU TO:Come NO CHANGE INCREASE DECREASE NO CHANGE INCREASE DECREASE Design Contractor Owner Code/AHJUnknown Conditions HealthPoint Other COMER GC, Inc.11/30/22 11/30/2022                                                                                           PUBLIC WORKS Facilities Division Project No:CCD # 34 CONSTRUCTION CHANGE DIRECTIVE Project Name: (CCD) (CONTRACTOR) You are directed to prepare a cost proposal for the work described below and/or detailed on the attachment referred to: SOURCE OF CHANGE: DATE PROPOSAL REQUIRED:11/3/22 CHANGE ORIGINATED BY: Owner/Architect (14 days from Request Date, unless other date agreed to) PROPOSAL REQUESTED BY: Contractor ARCHITECTCOR PM WE AGREE TO PERFORM ALL CHANGE IN THE WORK DESCRIBED IN THE PROPOSAL REQUEST FOR: CONTRACT SUM: (WASHINGTON STATE SALES TAX EXCLUDED) In accordance with the general condition, Cost Estimate Detail Sheet(s) are attached hereto. CONTRACT TIME: OF 0 CALENDAR DAYS BY: CONTRACTOR SIGNATURE DATE We have carefully examined this proposal and find the cost to be reasonable.Therefore, we recommend acceptance. ARCHITECT DATE HEALTHPOINT DATE City of Renton Authorized Signature To be utilized for changes requested by HealthPoint CITY OF RENTON DATE Family First Community Center TO: Comer GC, Inc. The foregoing amount covers everything required in connection with the change. All other provisions of the contract remain in full force and effect. We understand that this proposal does not constitute authorization to proceed with the specified changes in the work until incorporation of this COP into a Change Order by the City of Renton. Additional asphalt demolition and replacement at drive entranceways 08/15/22Proposal Request Date: EXPLANATION: Per above TO: Meredith Everist TO:Russ Woodruff ThirteenͲThousand NineͲHundred and Eighty Dollars 13,980.00$ CAG 21Ͳ180 WE AGREE CONTRACT TO:Mered DATE PROP (14 days from You are direct SOURCE OF C CONSTRUC TO:Comer Additional EXPLANATIO NO CHANGE INCREASE DECREASE NO CHANGE INCREASE DECREASE Design Contractor Owner Code/AHJUnknown Conditions HealthPoint Other COMER GC, Inc.11/8/2022 11/8/2022                                                       1 Russ Woodruff From:Meredith Everist <everistm@baylisarchitects.com> Sent:Friday, November 4, 2022 3:52 PM To:Russ Woodruff Cc:16-0996 Family First Community Center Subject:FW: FFCC - CI-034 - Additional Asphalt Demo and New @ SW entrance and Tie-in to School Attachments:FFCC - CI-034 - Additional Asphalt Demo and New @ SW entrance and Tie-in to School.pdf HiRuss,WehavereviewedthisChangeItemandbelievethecoststobereasonable.  Thanks,Meredith  Meredith Everist | AIA | NOMA | LEED AP BD+C Principal Pronouns: she | her 10801 Main Street, # 110 | Bellevue, WA 98004 O: 425.454.0566 D: 425.679.5205 F: 425.453.8013 everistm@baylisarchitects.com | BaylisArchitects.com Facebook | LinkedIn | Houzz  From:KeithKruger<KeithK@cplinc.com> Sent:Thursday,November3,20224:55PM To:MeredithEverist<everistm@baylisarchitects.com> Cc:16Ͳ0996FamilyFirstCommunityCenter<16Ͳ0996@baylisarchitects.com> Subject:RE:FFCCͲCIͲ034ͲAdditionalAsphaltDemoandNew@SWentranceandTieͲintoSchool  Meredith,  Thislooksreasonable.  Thanks  Keith Kruger, PE, LEED AP Associate Principal COUGHLINPORTERLUNDEEN STRUCTURAL CIVIL SEISMIC ENGINEERING 801 SECOND AVE / SUITE 900 / SEATTLE WA 98104 P: 206.343.0460 / cplinc.com  From:MeredithEverist<everistm@baylisarchitects.com> Sent:Thursday,November3,20229:39AM To:KeithKruger<KeithK@cplinc.com> Cc:16Ͳ0996FamilyFirstCommunityCenter<16Ͳ0996@baylisarchitects.com> Subject:FW:FFCCͲCIͲ034ͲAdditionalAsphaltDemoandNew@SWentranceandTieͲintoSchool CAUTION: This email originated from outside the City of Renton. Do not click links, reply or open attachments unless you know the content is safe.           2  HiKeith,willyoupleasereviewtheattachedandletmeknowifthepricinglooksreasonable?  Thanks,Meredith  Meredith Everist | AIA | NOMA | LEED AP BD+C Principal Pronouns: she | her 10801 Main Street, # 110 | Bellevue, WA 98004 O: 425.454.0566 D: 425.679.5205 F: 425.453.8013 everistm@baylisarchitects.com | BaylisArchitects.com Facebook | LinkedIn | Houzz  From:LukeComer<luke@comergc.com> Sent:Thursday,November3,20229:16AM To:'RussWoodruffͲCityofRenton'<rwoodruff@rentonwa.gov>;MeredithEverist<everistm@baylisarchitects.com> Cc:'TimComer'<tim@comergc.com>;JonScofield<jon@comergc.com> Subject:FFCCͲCIͲ034ͲAdditionalAsphaltDemoandNew@SWentranceandTieͲintoSchool  Team– Attachedispricingfor:FFCCͲCIͲ034ͲAdditionalAsphaltDemoandNew@SWentranceandTieͲintoSchool, whichrelatestothecostsassociatedwithadditionalsawͲcutting/demoandnewasphaltattheSWentranceperLCand RWdiscussion,aswellassawͲcutting/demoandnewasphaltattieͲintoexistingCascadeES.ThetieͲinportionwas necessaryinensuringproperdrainagewhenthenewasphaltwaslaid.  Thank you,  Luke Comer C:425Ͳ765Ͳ4118IP:425Ͳ636Ͳ8934IF:425Ͳ285Ͳ9785           PUBLIC WORKS Facilities Division Project No:CCD # 35 CONSTRUCTION CHANGE DIRECTIVE Project Name: (CCD) (CONTRACTOR) You are directed to prepare a cost proposal for the work described below and/or detailed on the attachment referred to: CEOFCHANGE: DATE PROPOSAL REQUIRED:11/1/22 CHANGE ORIGINATED BY: Structural Engineer (14 days from Request Date, unless other date agreed to) PROPOSAL REQUESTED BY: Contractor ARCHITECTCOR PM WE AGREE TO PERFORM ALL CHANGE IN THE WORK DESCRIBED IN THE PROPOSAL REQUEST FOR: CONTRACT SUM: (WASHINGTON STATE SALES TAX EXCLUDED) In accordance with the general condition, Cost Estimate Detail Sheet(s) are attached hereto. CONTRACT TIME: OF 0 CALENDAR DAYS BY: CONTRACTOR SIGNATURE DATE We have carefully examined this proposal and find the cost to be reasonable.Therefore, we recommend acceptance. ARCHITECT DATE HEALTHPOINT DATE City of Renton Authorized Signature To be utilized for changes requested by HealthPoint CITY OF RENTON DATE Family First Community Center TO: Comer GC, Inc. The foregoing amount covers everything required in connection with the change. All other provisions of the contract remain in full force and effect. We understand that this proposal does not constitute authorization to proceed with the specified changes in the work until incorporation of this COP into a Change Order by the City of Renton. Specified hangers for fall arrests had to be revised/reordered to fit with structure` 07/06/22Proposal Request Date: EXPLANATION: Per above TO: Meredith Everist TO:Russ Woodruff SevenͲThousand FiveͲHundred and Nineteen Dollars 7,519.00$ CAG 21Ͳ180 WE AGREE CONTRAC TO:Mered DATE PROP (14 days from You are direct OF CHANGE: CONSTRU TO:Come Specified h EXPLANATI NO CHANGE INCREASE DECREASE NO CHANGE INCREASE DECREASE Design Contractor Owner Code/AHJUnknown Conditions HealthPoint Other COMER GC. Inc.11/29/22 11/29/2022                                                                         1 Russ Woodruff From:Russ Woodruff Sent:Monday, November 28, 2022 4:26 PM To:Russ Woodruff Subject:FW: FFCC - CI-035 - RFI-024 - Hangers @ Fall Arrests - Replacement hangers  From:MeredithEverist<everistm@baylisarchitects.com> Sent:Tuesday,November22,202212:56PM To:RussWoodruff<RWoodruff@Rentonwa.gov> Cc:16Ͳ0996FamilyFirstCommunityCenter<16Ͳ0996@baylisarchitects.com> Subject:FW:FFCCͲCIͲ035ͲRFIͲ024ͲHangers@FallArrestsͲReplacementhangers  HiRuss,hereisCPL’scommentonthisRFI.Comerhasclarifiedthatthereisnocreditfor  From:KellyLowe<kellyl@cplinc.com> Sent:Wednesday,November9,202212:36PM To:MeredithEverist<everistm@baylisarchitects.com>;BenBarlow<BenB@cplinc.com> Cc:16Ͳ0996FamilyFirstCommunityCenter<16Ͳ0996@baylisarchitects.com> Subject:RE:FFCCͲCIͲ035ͲRFIͲ024ͲHangers@FallArrestsͲReplacementhangers  HiMeredith,  Overallcostseemsreasonable.  Givemeacallifyouwouldliketodiscuss!  Kelly Lowe (she/her) COUGHLINPORTERLUNDEEN  From:MeredithEverist<everistm@baylisarchitects.com> Sent:Thursday,November3,20229:38AM To:KellyLowe<kellyl@cplinc.com>;BenBarlow<BenB@cplinc.com> Cc:16Ͳ0996FamilyFirstCommunityCenter<16Ͳ0996@baylisarchitects.com> Subject:FW:FFCCͲCIͲ035ͲRFIͲ024ͲHangers@FallArrestsͲReplacementhangers  HiKellyandBen,willyoupleasereviewthepricingandletusknowifitlooksreasonabletoyou?  Thanks,Meredith  Meredith Everist | AIA | NOMA | LEED AP BD+C Principal Pronouns: she | her CAUTION: This email originated from outside the City of Renton. Do not click links, reply or open attachments unless you know the content is safe.           2 10801 Main Street, # 110 | Bellevue, WA 98004 O: 425.454.0566 D: 425.679.5205 F: 425.453.8013 everistm@baylisarchitects.com | BaylisArchitects.com Facebook | LinkedIn | Houzz  From:LukeComer<luke@comergc.com> Sent:Thursday,November3,20229:32AM To:'RussWoodruffͲCityofRenton'<rwoodruff@rentonwa.gov>;MeredithEverist<everistm@baylisarchitects.com> Cc:'TimComer'<tim@comergc.com>;JonScofield<jon@comergc.com> Subject:FFCCͲCIͲ035ͲRFIͲ024ͲHangers@FallArrestsͲReplacementhangers  Team– Attachedispricingfor:FFCCͲCIͲ035ͲRFIͲ024ͲHangers@FallArrestsͲReplacementhangers,whichrelatesto thecostsassociatedwithpurchasingnewhangers@fallarrestsperRFIͲ024response.  Thank you,  Luke Comer C:425Ͳ765Ͳ4118IP:425Ͳ636Ͳ8934IF:425Ͳ285Ͳ9785