January 24, 2023
City of Renton
Department of Community and Economic Development
Planning Division
1055 South Grady Way, 6th Floor
Renton, WA 98057
425-430-7200
RE: Code Interpretation: PRE 22-000411
Planning Staff:
A pre-application meeting (PRE 22-000411) for a small new construction project located at 400 S. 43rd
Street (Valley Medical Center Campus) was held on January 19th, 2023 at 10:00am. The proposed project
is a new 500 square foot accessory use storage building. CLARK | BARNES PLLC prepared Meeting
Minutes which are attached for reference.
During the meeting it was conveyed by City Planner Andrew Van Gordon, that the proposed 500 gross
square foot development would trigger SEPA Environmental Review per RMC 4-9-070, as well as site plan
review per RMC 4-9-200(B)(2)(a), refer to section 5.7 of Meeting Minutes. We believe this evaluation to be
inaccurate, since the proposed project satisfies the categorical exemption identified by RMC 4-9-
070(G)(1)(c).
RMC 4-9-070(G)(1)(c): For office, commercial, or service buildings in WAC 197-11-800(1)(b)(iv): four
thousand (4,000) square feet or less of gross floor area; changes of use of four thousand
(4,000) square feet or less when located in an existing office, commercial, or service building of
four thousand (4,000) square feet or larger.
1. Justification
The proposed building, which is 500 gross square feet, is under the 4,000 square foot threshold identified
by RMC 4-9-070(G)(1)(c). Furthermore, nothing in the code (Renton Municipal Code or Washington
Administrative Code) suggests that the area requirement is accumulative among multiple existing
buildings on the same site or is based upon accumulative use for an entire site, which is what was stated
during the pre-application meeting and noted on page 5 of the DCED memorandum provided to the
applicant prior to the meeting. The memorandum section states:
Environmental Review: The proposal would require environmental review pursuant to the State
Environmental Policy Act (SEPA) as the gross square floor area of the use exceeds 4,000 square
feet of floor area.
The RMC 4-9-070(G)(1)(c) code section identifies two separate exemption conditions governed by area
thresholds – one for buildings less than 4,000 gross square feet, and the other for change of use less than
4,000 gross square feet. The proposal is for a new building under 4,000 gross square feet. We believe the
reference provided within the DCED memorandum is a misinterpretation of the code, as it appears to
January 24, 2023 CLARK | BARNES 2
combine the language from both exemption conditions. “Gross square floor area of the use” does not
appear in the code.
RMC 4-9-070(G)(1)(c) specifically states “gross floor area”, and gross floor area as defined in Chapter 2 of
the current 2018 International Building Code is “The floor area within the inside perimeter of the exterior
walls of the building under consideration”. The code is referring to a singular building (new or existing) and
not an accumulative area.
2. Conclusion
Because the proposed building is less than four thousand (4,000) square feet, we believe the project
complies with the code language and intent outlined by local exemption ‘c’ per RMC 4-9-070(G)(1)(c) and
is therefore a SEPA Exempt Development per RMC 4-9-200(C)(2)(b). As a SEPA Exempt Development, the
project should also be exempt from Site Plan Review.
The purpose of this letter is to confirm with the City Planning staff that our interpretation of the RMC 4-9-
070(G)(1)(c) code section is correct and that SEPA and Site Plan Review are not required for the proposed
development.
Respectfully,
W. Scott Clark, Partner, AIA, NCARB, AIBC
CLARK | BARNES PLLC
CC: Thomas McDaniel – Valley Medical Center
Becky Hardi – Valley Medical Center
Andrew Van Gordon – City of Renton Planning Division
Chip Vincent – City of Renton Planning Division
1.1 Meeting Minutes
Project: VMC Haz-Mat Storage Building
Meeting Date: January 19, 2023
Meeting Location: Microsoft Teams Meeting
Meeting Attendees:
Andrew Van Gordon (AG), Planner, City of Renton
Scott Warlick (SW), Public Works, City of Renton
Corey Thomas (CT), Fire Prevention, Renton Regional Fire Authority
Thomas McDaniel (TM), Senior Project Manager, Valley Medical Center
Becky Hardi (BH), Manager, Valley Medical Center
Johnathon Cave (JC), Project Manager, Clark|Barnes
ITEM ACTION
2.0 Schedule
2.1 Pre-application meeting held on 01/19/2023 @ 10:00am INFO
3.0 General Discussion
3.1 Andrew Van Gordon (AG) (City planner) hosted and led the meeting INFO
3.2 Attendee introductions INFO
4.0 Project Description
4.1 The scope of work consists of building a new 500 sf, Type V-A construction, single-story
accessory use storage building within the existing Valley Medical Center Campus located
at 400 South 43rd Street. INFO
5.0 Pre-application Discussion
5.1 Cory Thomas (CT) reviewed the fire-related requirements for the project outlined in the
pre-application memo. The preliminary fire flow is 1,500 gpm, and two fire hydrants are
required. Based on the existing site documentation, there are sufficient fire hydrants to
meet the requirement. Fire impact fees are $0.15 per square foot of storage space and is
due at the time of building permit issuance. An approved fire sprinkler and fire alarm
VMC Haz-Mat Storage Building CLARK | BARNES Page 2 of 3
Meeting Minutes 01/24/23
system is required for the building. Existing fire department access roadways will be
maintained. COR
5.2 A Hazardous Materials Inventory Statement is required before building permit issuance. COR
· Johnathon Cave (JC) to follow up with (CT) via email to determine if the level of
information shown in our feasibility narrative for the existing material inventory is
sufficient for the Hazardous Materials Inventory Statement. C|B
5.3 Scott Warlick (SW) reviewed the water, sewer, storm drainage and transportation/
street requirements for the project outlined in the pre-application memo. Domestic
fixtures, i.e. eye wash station, will require a new ¾” domestic meter with a reduced
pressure backflow assembly. As noted by (CT), an approved fire sprinkler system is
required for the building, and a dedicated fire service line from the existing 12” water
main will be needed. As a result, the existing water main may need to be extended.
As noted in the pre-application memo for sewer and storm drainage, any service lines
that are currently running under the proposed building will need to be re-routed
around the new building foundation. Utility line separation requirements were
provided and address the design teams pre-app question. COR
· (JC) and Becky Hardi (BH) asked if there were any exceptions for the re-routing of
the existing sewer and storm drainage lines under the proposed site, as the cost
to relocate those utilities will drastically impact whether or not the project moves
forward. (SW) explained that an exception would be unlikely, but requested that
the design team follow up with an email and (SW) would review in further detail
and discuss with other Public Works Department staff. C|B
5.4 (SW) noted in the pre-application memo for transportation that the proposed project
does not trigger frontage improvements. COR
5.5 (AG) reviewed the general land use requirements for the project outlined in the pre-
application memo. Because the scope of work consists of constructing a new building,
the project will need to demonstrate how the existing parking complies with the
parking requirements for new construction. COR
5.6 (AG) explained that because the scope of work includes the removal a significant tree
located in the middle of the site (trees greater than 6-inch caliper), a tree inventory
and retention plan, as well as an arborist report shall be provided as part of the land
use application. COR
5.7 (AG) noted that because the gross square floor area of the use of the property
exceeds 4,000 square feet, SEPA environmental review would be required. As a result
of developing in the CO Zone per RMC 4-9-200, Administrative Site Plan Review would
also be required. (AG) explained that Site Plan Review and approval would be needed
prior to submitting for the Building and Land Use permits; however, SEPA
VMC Haz-Mat Storage Building CLARK | BARNES Page 3 of 3
Meeting Minutes 01/24/23
environmental review can be submitted and reviewed in tandem with the Site Plan
Review. COR
· (BH) and (JC) asked for clarification on the exceptions for SEPA and Site Plan
Review. (AG) explained that the project would only be exempt from Site Plan
Review if SEPA environmental review was not required. (JC) explained that per
RMC 4-9-070(G)(1)(c), the project is under the 4,000 gross square footage
threshold, and (BH) noted that per previous conversations and review with
Renton Senior Planner Clark Close, a building under 4,000 gross square feet
would be exempt from Site Plan Review, on the basis that it would be a SEPA
Exempt Development per RMC 4-9-200(C)(2)(b). (BH) asked (AG) for clarification
on whether this prior exemption was strictly due to the fact that the proposal at
that time was an addition and not a new structure. (AG) explained that he could
not provide clarification for a determination provided by another reviewer for a
separate project. (JC) stated that he would review the municipal code sections
pertaining to categorical exemptions and SEPA Exempt Development and follow
up with (AG) and the rest of the team via email or official letter.
· (BH) asked (AG) what the anticipated review timeline would be for the
Administrative Site Plan Review if required. (AG) responded with 6-8 weeks from
the application submittal. C|B
5.8 (JC) asked for clarification on which permits would be applicable to the proposed
project, as outlined in the applicant’s pre-application letter (in particular separate
permits for Civil Construction, Grading, and Preload/Site Prep). (AG) explained that it
would be best to either send a follow up email to (SW) asking for confirmation of the
required permits or reaching out to a Renton permit tech. (JC) to follow up. C|B
· (AG) explained that it would be best to either send a follow up email to (SW) asking
for confirmation of the required permits or reaching out to a Renton permit tech.
(JC) to follow up. COR
Prepared By: Issued: 01/24/23
Johnathon Cave, CLARK | BARNES
These meeting minutes represent CLARK | BARNES understanding of the items discussed at the meeting.
We shall rely upon the contents unless notified of any discrepancies or inaccuracies within one week of
the final issuance date posted at the end of these minutes.