HomeMy WebLinkAboutChange Order - 6Public Works
Facilities Division CONTRACT NO:CAGͲ21Ͳ180 CO NO. 6
CONTRACT CHANGE ORDER (CO)PROJECT TITLE:FAMILY FIRST COMMUNITY CENTER
TO: COMER GC, Inc. (CONTRACTOR)
Description Amount
CCD 8ͲStormwater Revisions 8,449.00$
CCD 45ͲAdd Garbage Disposal 771.00$
CCD 46ͲPͲLam Revisions To Casework 1,016.00$
CCD 49ͲAdd Valve to Oil Water Separator 10,239.00$
CCD 59ͲFlush Curb at East Lot 7,484.00$
Ͳ$
Subtotal 27,959.00$
WSST 2,823.86$
TOTAL THIS CHANGE ORDER 30,782.86$
CONTRACT SUM:
30,782.86$
(WASHINGTON STATE SALES TAX INCLUDED)
CONTRACT TIME:
0
CALENDAR DAYS
CONTRACT SUMMARY (Internal Use Only)
ORIGINAL CONTRACT SUM w/ WSST 12,474,330.00$
PREVIOUS ADDITIONS/DELETIONS 212,476.49$
PREVIOUS TOTAL 12,686,806.49$
CHANGE AMOUNT THIS CHANGE ORDER 30,782.86$
REVISED CONTRACT TOTAL 12,717,589.35$
PERCENT TOTAL CHANGE FROM ORIGINAL 1.95%
NOTICE TO PROCEED DATE February 25, 2022
PREVIOUS CONTRACT CALENDAR DAYS 0
PREVIOUS SUBSTANTIAL COMPLETION DATE February 25, 2023
REVISED CONTRACT CALENDAR DAYS THIS CHANGE ORDER 0
CURRENT SUBSTANTIAL COMPLETION DATE February 25, 2023
Architect AcknowledgementDate Contractor AcknowledgementDate
AUTHORIZING SIGNATURE DATE
The following mutually agreed to and Owner approved Contract Change Directive(s) are hereby incorporated by reference into the contract.
The foregoing amount covers everything required in connection with the change. All other provisions of the contract remain in full force and
effect.
The City of Renton hereby accepts the foregoing changes. This formal acceptance constitutes a Change to the contract only when authorizing
signature is affixed. Invoices incorporating this Change Order constitute acceptance by the Contractor as total reimbursement due in
connection with this Change Order.
OF:
CONTRACT
Description
CCD 8ͲStorm
CCD 45 ͲAdd
CCD 46 ͲPͲLa
CCD 49 ͲAdd
CCD 59 ͲFlush
The
CONTRAC
TO:
following m
NO CHANGE
INCREASE
DECREASE
NO CHANGE
INCREASE
DECREASE
1/13/20231/13/2023
CAG-21-180, CO #6-23
PUBLIC WORKS
Facilities Division Project No:CCD # 8
CONSTRUCTION CHANGE DIRECTIVE Project Name:
(CCD)
(CONTRACTOR)
You are directed to prepare a cost proposal for the work described below and/or detailed on the attachment referred to:
SOURCE OF CHANGE:
DATE PROPOSAL REQUIRED:12/6/22 CHANGE ORIGINATED BY: Contractor
(14 days from Request Date, unless other date agreed to)
PROPOSAL REQUESTED BY: Contractor
ARCHITECTCOR PM
WE AGREE TO PERFORM ALL CHANGE IN THE WORK DESCRIBED IN THE PROPOSAL REQUEST FOR:
CONTRACT SUM:
(WASHINGTON STATE SALES TAX EXCLUDED)
In accordance with the general condition, Cost Estimate Detail Sheet(s) are attached hereto.
CONTRACT TIME:
OF 0 CALENDAR DAYS
BY:
CONTRACTOR SIGNATURE DATE
We have carefully examined this proposal and find the cost to be reasonable.Therefore, we recommend acceptance.
ARCHITECT DATE HEALTHPOINT DATE
City of Renton Authorized Signature To be utilized for changes requested
by HealthPoint
CITY OF RENTON DATE
8,449.00$
CAG 21Ͳ180
Family First Community Center
TO: Comer GC, Inc.
The foregoing amount covers everything required in connection with the change. All other provisions of the contract remain in full
force and effect.
We understand that this proposal does not constitute authorization to proceed with the specified changes in the work until
incorporation of this COP into a Change Order by the City of Renton.
Revisions for stormwater systemͲbid design posed significant schedule risk due to sequencing.
03/15/22Proposal Request Date:
EXPLANATION: Per above
TO: Meredith Everist TO:Russ Woodruff
EightͲThousand FourͲHundred and FortyͲNine Dollars
WE AGREE
CONTRAC
TO:Mered
DATE PROP
(14 days from
You are direct
SOURCE OF
CONSTRU
TO:Come
Revisions
EXPLANATI
NO CHANGE
INCREASE
DECREASE
NO CHANGE
INCREASE
DECREASE
Design Contractor Owner Code/AHJUnknown Conditions HealthPoint Other
1/10/2023
COMER GC, Inc.1/13/23
1
Russ Woodruff
From:Meredith Everist <everistm@baylisarchitects.com>
Sent:Wednesday, December 14, 2022 5:22 PM
To:Russ Woodruff
Cc:16-0996 Family First Community Center
Subject:FW: FFCC - CI-008 - CCD-001 - Storm System Revisions
Attachments:FFCC - CI-008 - CCD-001 - Storm System Revisions.pdf
HIRuss,tĞbelievethecoststobereasonable.
Thanks,Meredith
Meredith Everist | AIA | NOMA | LEED AP BD+C
Principal
Pronouns: she | her
10801 Main Street, # 110 | Bellevue, WA 98004
O: 425.454.0566 D: 425.679.5205 F: 425.453.8013
everistm@baylisarchitects.com | BaylisArchitects.com
Facebook | LinkedIn | Houzz
From:MeredithEverist<everistm@baylisarchitects.com>
Sent:Tuesday,December6,20223:13PM
CAUTION: This email originated from outside the City of Renton. Do not click links, reply or open attachments unless
you know the content is safe.
2
To:KeithKruger<KeithK@cplinc.com>
Cc:16Ͳ0996FamilyFirstCommunityCenter<16Ͳ0996@baylisarchitects.com>
Subject:FW:FFCCͲCIͲ008ͲCCDͲ001ͲStormSystemRevisions
HiKeith,willyoupleasereviewandcommentifthereareanyconcernswiththeattachedchangerequest?
Thanks,Meredith
Meredith Everist | AIA | NOMA | LEED AP BD+C
Principal
Pronouns: she | her
10801 Main Street, # 110 | Bellevue, WA 98004
O: 425.454.0566 D: 425.679.5205 F: 425.453.8013
everistm@baylisarchitects.com | BaylisArchitects.com
Facebook | LinkedIn | Houzz
From:LukeComer<luke@comergc.com>
Sent:Tuesday,December6,20229:23AM
To:'RussWoodruffͲCityofRenton'<rwoodruff@rentonwa.gov>;MeredithEverist<everistm@baylisarchitects.com>
Cc:'TimComer'<tim@comergc.com>;JonScofield<jon@comergc.com>
Subject:FFCCͲCIͲ008ͲCCDͲ001ͲStormSystemRevisions
Team–
Attachedispricingfor:FFCCͲCIͲ008ͲCCDͲ001ͲStormSystemRevisions,whichrelatestothestormrevisions
primarilyrelatedtothechangetotheundergroundCuIltechSystem.Thisupfrontchangeinsystemwouldbeoneitem
theteamcanlookbackonastheprimaryreasonforbenefittingthesiteschedulefortheproject.Thissystemwasable
tobeprocuredmoretimely,andinstalledmoretimely,whichsettheprojectupforsuccess.McKeewasabletomake
thesemodificationswithnoadditionalcosts,howeverCPLhadcostsinresubmitting/redesignwhichiswhatisbeing
submittedon.
TheonlyotherminorcostassociatedistheremobilizationofourstripingsubtoreͲstripethecrosswalkoriginallydeleted
thattheRSDwantedback.
Thank you,
Luke Comer
C:425Ͳ765Ͳ4118IP:425Ͳ636Ͳ8934IF:425Ͳ285Ͳ9785
PUBLIC WORKS
Facilities Division Project No:CCD # 45
CONSTRUCTION CHANGE DIRECTIVE Project Name:
(CCD)
(CONTRACTOR)
You are directed to prepare a cost proposal for the work described below and/or detailed on the attachment referred to:
CEOFCHANGE:
DATE PROPOSAL REQUIRED:12/20/22 CHANGE ORIGINATED BY: Design team
(14 days from Request Date, unless other date agreed to)
PROPOSAL REQUESTED BY: Contractor
ARCHITECTCOR PM
WE AGREE TO PERFORM ALL CHANGE IN THE WORK DESCRIBED IN THE PROPOSAL REQUEST FOR:
CONTRACT SUM:
(WASHINGTON STATE SALES TAX EXCLUDED)
In accordance with the general condition, Cost Estimate Detail Sheet(s) are attached hereto.
CONTRACT TIME:
OF 0 CALENDAR DAYS
BY:
CONTRACTOR SIGNATURE DATE
We have carefully examined this proposal and find the cost to be reasonable.Therefore, we recommend acceptance.
ARCHITECT DATE HEALTHPOINT DATE
City of Renton Authorized Signature To be utilized for changes requested
by HealthPoint
CITY OF RENTON DATE
CAG 21Ͳ180
Family First Community Center
TO: Comer GC, Inc.
The foregoing amount covers everything required in connection with the change. All other provisions of the contract remain in full
force and effect.
We understand that this proposal does not constitute authorization to proceed with the specified changes in the work until
incorporation of this COP into a Change Order by the City of Renton.
Add garbage disposal to demonstration kitchen
08/24/22Proposal Request Date:
EXPLANATION: Per above
TO: Meredith Everist TO:Russ Woodruff
SevenͲHundred SeventyͲOne Dollars 771.00$
WE AGREE
CONTRAC
TO:Mered
DATE PROP
(14 days from
You are direct
OF CHANGE:
CONSTRU
TO:Come
Add garba
EXPLANATI
NO CHANGE
INCREASE
DECREASE
NO CHANGE
INCREASE
DECREASE
Design Contractor Owner Code/AHJUnknown Conditions HealthPoint Other
1/10/2023
COMER GC, Inc.1/13/23
1
Russ Woodruff
From:Meredith Everist <everistm@baylisarchitects.com>
Sent:Thursday, December 22, 2022 11:22 AM
To:Russ Woodruff
Cc:16-0996 Family First Community Center
Subject:FW: FFCC - CI-045 - CCD-011 - Added Garbage Disposal - Plumbing
Attachments:FFCC - CI-045 - CCD-011 - Added Garbage Disposal - Plumbing.pdf
HIRuss,thischangeitemseemsreasonable.
Thanks,Meredith
Meredith Everist | AIA | NOMA | LEED AP BD+C
Principal
Pronouns: she | her
10801 Main Street, # 110 | Bellevue, WA 98004
O: 425.454.0566 D: 425.679.5205 F: 425.453.8013
everistm@baylisarchitects.com | BaylisArchitects.com
Facebook | LinkedIn | Houzz
From:LukeComer<luke@comergc.com>
Sent:Tuesday,December20,202211:15AM
To:'RussWoodruffͲCityofRenton'<rwoodruff@rentonwa.gov>;MeredithEverist<everistm@baylisarchitects.com>
Cc:'TimComer'<tim@comergc.com>;JonScofield<jon@comergc.com>
Subject:FFCCͲCIͲ045ͲCCDͲ011ͲAddedGarbageDisposalͲPlumbing
Team–
Attachedispricingfor:FFCCͲCIͲ045ͲCCDͲ011ͲAddedGarbageDisposalͲPlumbing,whichrelatestoadded
garbagedisposal,relatedplumbinginstallandcoordinationperCCDͲ011.Noteelectricalplanshadpowertothis,so
therewerenoadditionalcostsrelatedelectrically.
Thank you,
Luke Comer
C:425Ͳ765Ͳ4118IP:425Ͳ636Ͳ8934IF:425Ͳ285Ͳ9785
CAUTION: This email originated from outside the City of Renton. Do not click links, reply or open attachments unless
you know the content is safe.
PUBLIC WORKS
Facilities Division Project No:CCD # 46
CONSTRUCTION CHANGE DIRECTIVE Project Name:
(CCD)
(CONTRACTOR)
You are directed to prepare a cost proposal for the work described below and/or detailed on the attachment referred to:
CEOFCHANGE:
DATE PROPOSAL REQUIRED:12/20/22 CHANGE ORIGINATED BY: Design team
(14 days from Request Date, unless other date agreed to)
PROPOSAL REQUESTED BY: Contractor
ARCHITECTCOR PM
WE AGREE TO PERFORM ALL CHANGE IN THE WORK DESCRIBED IN THE PROPOSAL REQUEST FOR:
CONTRACT SUM:
(WASHINGTON STATE SALES TAX EXCLUDED)
In accordance with the general condition, Cost Estimate Detail Sheet(s) are attached hereto.
CONTRACT TIME:
OF 0 CALENDAR DAYS
BY:
CONTRACTOR SIGNATURE DATE
We have carefully examined this proposal and find the cost to be reasonable.Therefore, we recommend acceptance.
ARCHITECT DATE HEALTHPOINT DATE
City of Renton Authorized Signature To be utilized for changes requested
by HealthPoint
CITY OF RENTON DATE
1,016.00$
CAG 21Ͳ180
Family First Community Center
TO: Comer GC, Inc.
The foregoing amount covers everything required in connection with the change. All other provisions of the contract remain in full
force and effect.
We understand that this proposal does not constitute authorization to proceed with the specified changes in the work until
incorporation of this COP into a Change Order by the City of Renton.
Revise PͲlam on casework in demo kitchen
08/24/22Proposal Request Date:
EXPLANATION: Per above
TO: Meredith Everist TO:Russ Woodruff
OneͲThousand and Sixteen Dollars
WE AGREE
CONTRAC
TO:Mered
DATE PROP
(14 days from
You are direct
OF CHANGE:
CONSTRU
TO:Come
Revise PͲla
EXPLANATI
NO CHANGE
INCREASE
DECREASE
NO CHANGE
INCREASE
DECREASE
Design Contractor Owner Code/AHJUnknown Conditions HealthPoint Other
1/10/2023
COMER GC, Inc.1/13/23
1
Russ Woodruff
From:Meredith Everist <everistm@baylisarchitects.com>
Sent:Thursday, December 22, 2022 9:36 AM
To:Russ Woodruff
Cc:16-0996 Family First Community Center
Subject:FW: FFCC - CI-046 - ASI-010 - PLAM Changes @ Demo Kitchen Island
Attachments:FFCC - CI-046 - ASI-010 - PLAM Changes @ Demo Kitchen Island.pdf
HIRuss,wereviewedthisChangeItemandthepricinglooksreasonable.
Thanks,Meredith
Meredith Everist | AIA | NOMA | LEED AP BD+C
Principal
Pronouns: she | her
10801 Main Street, # 110 | Bellevue, WA 98004
O: 425.454.0566 D: 425.679.5205 F: 425.453.8013
everistm@baylisarchitects.com | BaylisArchitects.com
Facebook | LinkedIn | Houzz
From:LukeComer<luke@comergc.com>
Sent:Tuesday,December20,202211:30AM
To:'RussWoodruffͲCityofRenton'<rwoodruff@rentonwa.gov>;MeredithEverist<everistm@baylisarchitects.com>
Cc:'TimComer'<tim@comergc.com>;JonScofield<jon@comergc.com>
Subject:FFCCͲCIͲ046ͲASIͲ010ͲPLAMChanges@DemoKitchenIsland
Team–
Attachedispricingfor:FFCCͲCIͲ046ͲASIͲ010ͲPLAMChanges@DemoKitchenIsland,whichrelatestoPLAM
changesattheKitchenDemoislandperASIͲ010.PLAMfortheprojecthadalreadybeenordered,thischangeincolor
requiredadditionalsheetstobeorderedandprocessed.
Thank you,
Luke Comer
C:425Ͳ765Ͳ4118IP:425Ͳ636Ͳ8934IF:425Ͳ285Ͳ9785
CAUTION: This email originated from outside the City of Renton. Do not click links, reply or open attachments unless
you know the content is safe.
PUBLIC WORKS
Facilities Division Project No:CCD # 49
CONSTRUCTION CHANGE DIRECTIVE Project Name:
(CCD)
(CONTRACTOR)
You are directed to prepare a cost proposal for the work described below and/or detailed on the attachment referred to:
CEOFCHANGE:
DATE PROPOSAL REQUIRED:12/20/22 CHANGE ORIGINATED BY: AHJ Inspector
(14 days from Request Date, unless other date agreed to)
PROPOSAL REQUESTED BY: Contractor
ARCHITECTCOR PM
WE AGREE TO PERFORM ALL CHANGE IN THE WORK DESCRIBED IN THE PROPOSAL REQUEST FOR:
CONTRACT SUM:
(WASHINGTON STATE SALES TAX EXCLUDED)
In accordance with the general condition, Cost Estimate Detail Sheet(s) are attached hereto.
CONTRACT TIME:
OF 0 CALENDAR DAYS
BY:
CONTRACTOR SIGNATURE DATE
We have carefully examined this proposal and find the cost to be reasonable.Therefore, we recommend acceptance.
ARCHITECT DATE HEALTHPOINT DATE
City of Renton Authorized Signature To be utilized for changes requested
by HealthPoint
CITY OF RENTON DATE
Family First Community Center
TO: Comer GC, Inc.
The foregoing amount covers everything required in connection with the change. All other provisions of the contract remain in full
force and effect.
We understand that this proposal does not constitute authorization to proceed with the specified changes in the work until
incorporation of this COP into a Change Order by the City of Renton.
Install added valve per direction of AHJ Inspector
08/24/22Proposal Request Date:
EXPLANATION: Per above
TO: Meredith Everist TO:Russ Woodruff
TenͲThousand TwoͲHundred and Thirty Nine Dollars 10,239.00$
CAG 21Ͳ180
WE AGREE
CONTRAC
TO:Mered
DATE PROP
(14 days from
You are direct
OF CHANGE:
CONSTRU
TO:Come
Install add
EXPLANATI
NO CHANGE
INCREASE
DECREASE
NO CHANGE
INCREASE
DECREASE
Design Contractor Owner Code/AHJUnknown Conditions HealthPoint Other
1/10/2023
COMER GC, Inc.1/13/23
1
Russ Woodruff
From:Meredith Everist <everistm@baylisarchitects.com>
Sent:Friday, January 6, 2023 1:51 PM
To:Russ Woodruff
Cc:16-0996 Family First Community Center
Subject:FW: FFCC - CI-049 - Added Valve Outside of Oil and Water Separator COR Tom Main
Attachments:FFCC - CI-049 - Added Valve Outside of Oil and Water Separator COR Tom Main.pdf
HiRuss,webelievethesecoststobefairandreasonable.
Thanks,Meredith
Meredith Everist | AIA | NOMA | LEED AP BD+C
Principal
Pronouns: she | her
10801 Main Street, # 110 | Bellevue, WA 98004
O: 425.454.0566 D: 425.679.5205 F: 425.453.8013
everistm@baylisarchitects.com | BaylisArchitects.com
Facebook | LinkedIn | Houzz
From:KeithKruger<KeithK@cplinc.com>
Sent:Friday,January6,20231:43PM
To:MeredithEverist<everistm@baylisarchitects.com>
Cc:16Ͳ0996FamilyFirstCommunityCenter<16Ͳ0996@baylisarchitects.com>
Subject:RE:FFCCͲCIͲ049ͲAddedValveOutsideofOilandWaterSeparatorCORTomMain
Yes,thosewerefine.
Keith Kruger, PE, LEED AP
Associate Principal
COUGHLINPORTERLUNDEEN
STRUCTURAL CIVIL SEISMIC ENGINEERING
801 SECOND AVE / SUITE 900 / SEATTLE WA 98104
P: 206.343.0460 / cplinc.com
From:MeredithEverist<everistm@baylisarchitects.com>
Sent:Friday,January6,20231:03PM
To:KeithKruger<KeithK@cplinc.com>
Cc:16Ͳ0996FamilyFirstCommunityCenter<16Ͳ0996@baylisarchitects.com>
Subject:FW:FFCCͲCIͲ049ͲAddedValveOutsideofOilandWaterSeparatorCORTomMain
HIKeith,dothecostslooktobefairandreasonable?
Thanks,Meredith
CAUTION: This email originated from outside the City of Renton. Do not click links, reply or open attachments unless
you know the content is safe.
PUBLIC WORKS
Facilities Division Project No:CCD # 59
CONSTRUCTION CHANGE DIRECTIVE Project Name:
(CCD)
(CONTRACTOR)
You are directed to prepare a cost proposal for the work described below and/or detailed on the attachment referred to:
SOURCE OF CHANGE:
DATE PROPOSAL REQUIRED:1/9/23 CHANGE ORIGINATED BY: Civil
(14 days from Request Date, unless other date agreed to)
PROPOSAL REQUESTED BY: Contractor
ARCHITECTCOR PM
WE AGREE TO PERFORM ALL CHANGE IN THE WORK DESCRIBED IN THE PROPOSAL REQUEST FOR:
CONTRACT SUM:
(WASHINGTON STATE SALES TAX EXCLUDED)
In accordance with the general condition, Cost Estimate Detail Sheet(s) are attached hereto.
CONTRACT TIME:
OF 0 CALENDAR DAYS
BY:
CONTRACTOR SIGNATURE DATE
We have carefully examined this proposal and find the cost to be reasonable.Therefore, we recommend acceptance.
ARCHITECT DATE HEALTHPOINT DATE
City of Renton Authorized Signature To be utilized for changes requested
by HealthPoint
CITY OF RENTON DATE
Family First Community Center
TO: Comer GC, Inc.
The foregoing amount covers everything required in connection with the change. All other provisions of the contract remain in full
force and effect.
We understand that this proposal does not constitute authorization to proceed with the specified changes in the work until
incorporation of this COP into a Change Order by the City of Renton.
Add flush curb at bioswale to protect asphalt
09/28/22Proposal Request Date:
EXPLANATION: Per above
TO: Meredith Everist TO:Russ Woodruff
SevenͲThousand FourͲHundred and EightyͲFour Dollars 7,484.00$
CAG 21Ͳ180
WE AGREE
CONTRAC
TO:Mered
DATE PROP
(14 days from
You are direct
SOURCE OF
CONSTRU
TO:Come
Add flush
EXPLANATI
NO CHANGE
INCREASE
DECREASE
NO CHANGE
INCREASE
DECREASE
Design Contractor Owner Code/AHJUnknown Conditions HealthPoint Other
1/12/2023
COMER GC, Inc.1/13/23
1
Russ Woodruff
From:Meredith Everist <everistm@baylisarchitects.com>
Sent:Wednesday, January 11, 2023 8:49 AM
To:Russ Woodruff
Cc:16-0996 Family First Community Center
Subject:FW: FFCC - CI-059 - Flush Concrete Curb in lieu of mulch at east parking lot
Attachments:FFCC - CI-059 - Flush Concrete Curb in lieu of mulch at east parking lot
HiRuss,wetakenoexceptionstothischangeitem.
Thanks,Meredith
Meredith Everist | AIA | NOMA | LEED AP BD+C
Principal
Pronouns: she | her
10801 Main Street, # 110 | Bellevue, WA 98004
O: 425.454.0566 D: 425.679.5205 F: 425.453.8013
everistm@baylisarchitects.com | BaylisArchitects.com
Facebook | LinkedIn | Houzz
From:KeithKruger<KeithK@cplinc.com>
Sent:Tuesday,January10,20239:05PM
To:MeredithEverist<everistm@baylisarchitects.com>
Cc:16Ͳ0996FamilyFirstCommunityCenter<16Ͳ0996@baylisarchitects.com>
Subject:RE:FFCCͲCIͲ059ͲFlushConcreteCurbinlieuofmulchateastparkinglot
Meredith,
Thiscostisreasonable.
thanks
Keith Kruger, PE, LEED AP
Associate Principal
COUGHLINPORTERLUNDEEN
STRUCTURAL CIVIL SEISMIC ENGINEERING
801 SECOND AVE / SUITE 900 / SEATTLE WA 98104
P: 206.343.0460 / cplinc.com
From:MeredithEverist<everistm@baylisarchitects.com>
Sent:Tuesday,January10,20239:16AM
To:KeithKruger<KeithK@cplinc.com>
Cc:16Ͳ0996FamilyFirstCommunityCenter<16Ͳ0996@baylisarchitects.com>
Subject:FW:FFCCͲCIͲ059ͲFlushConcreteCurbinlieuofmulchateastparkinglot
CAUTION: This email originated from outside the City of Renton. Do not click links, reply or open attachments unless
you know the content is safe.
2
HiKeith,willyoupleasereviewcostsonthisChangeItem?
Thanks,Meredith
Meredith Everist | AIA | NOMA | LEED AP BD+C
Principal
Pronouns: she | her
10801 Main Street, # 110 | Bellevue, WA 98004
O: 425.454.0566 D: 425.679.5205 F: 425.453.8013
everistm@baylisarchitects.com | BaylisArchitects.com
Facebook | LinkedIn | Houzz
From:LukeComer<luke@comergc.com>
Sent:Monday,January9,20232:16PM
To:'RussWoodruff'<RWoodruff@Rentonwa.gov>;MeredithEverist<everistm@baylisarchitects.com>
Cc:'TimComer'<tim@comergc.com>;JonScofield<jon@comergc.com>
Subject:FFCCͲCIͲ059ͲFlushConcreteCurbinlieuofmulchateastparkinglot
Team–
Attachedispricingfor:FFCCͲCIͲ059ͲFlushConcreteCurbinlieuofmulchateastparkinglot,whichrelatesto
theedgeconditionatthebioretentionwithintheeastparkinglot.CityofRentonhadamulchdetail,buttherewas
concernwiththeasphaltnotabuttingasolidsurface,andpotentiallyseeinglongtermeffectsofitbreakingoff.Aflush
concretecurbwasinstalledtohavetheasphaltabutasolidsurface.
Thank you,
Luke Comer
C:425Ͳ765Ͳ4118IP:425Ͳ636Ͳ8934IF:425Ͳ285Ͳ9785