HomeMy WebLinkAboutChange Order - 6Public Works Facilities Division CONTRACT NO:CAGͲ21Ͳ180 CO NO. 6 CONTRACT CHANGE ORDER (CO)PROJECT TITLE:FAMILY FIRST COMMUNITY CENTER TO: COMER GC, Inc. (CONTRACTOR) Description Amount CCD 8ͲStormwater Revisions 8,449.00$ CCD 45ͲAdd Garbage Disposal 771.00$ CCD 46ͲPͲLam Revisions To Casework 1,016.00$ CCD 49ͲAdd Valve to Oil Water Separator 10,239.00$ CCD 59ͲFlush Curb at East Lot 7,484.00$ Ͳ$ Subtotal 27,959.00$ WSST 2,823.86$ TOTAL THIS CHANGE ORDER 30,782.86$ CONTRACT SUM: 30,782.86$ (WASHINGTON STATE SALES TAX INCLUDED) CONTRACT TIME: 0 CALENDAR DAYS CONTRACT SUMMARY (Internal Use Only) ORIGINAL CONTRACT SUM w/ WSST 12,474,330.00$ PREVIOUS ADDITIONS/DELETIONS 212,476.49$ PREVIOUS TOTAL 12,686,806.49$ CHANGE AMOUNT THIS CHANGE ORDER 30,782.86$ REVISED CONTRACT TOTAL 12,717,589.35$ PERCENT TOTAL CHANGE FROM ORIGINAL 1.95% NOTICE TO PROCEED DATE February 25, 2022 PREVIOUS CONTRACT CALENDAR DAYS 0 PREVIOUS SUBSTANTIAL COMPLETION DATE February 25, 2023 REVISED CONTRACT CALENDAR DAYS THIS CHANGE ORDER 0 CURRENT SUBSTANTIAL COMPLETION DATE February 25, 2023 Architect AcknowledgementDate Contractor AcknowledgementDate AUTHORIZING SIGNATURE DATE The following mutually agreed to and Owner approved Contract Change Directive(s) are hereby incorporated by reference into the contract. The foregoing amount covers everything required in connection with the change. All other provisions of the contract remain in full force and effect. The City of Renton hereby accepts the foregoing changes. This formal acceptance constitutes a Change to the contract only when authorizing signature is affixed. Invoices incorporating this Change Order constitute acceptance by the Contractor as total reimbursement due in connection with this Change Order. OF: CONTRACT Description CCD 8ͲStorm CCD 45 ͲAdd CCD 46 ͲPͲLa CCD 49 ͲAdd CCD 59 ͲFlush The CONTRAC TO: following m NO CHANGE INCREASE DECREASE NO CHANGE INCREASE DECREASE 1/13/20231/13/2023             CAG-21-180, CO #6-23 PUBLIC WORKS Facilities Division Project No:CCD # 8 CONSTRUCTION CHANGE DIRECTIVE Project Name: (CCD) (CONTRACTOR) You are directed to prepare a cost proposal for the work described below and/or detailed on the attachment referred to: SOURCE OF CHANGE: DATE PROPOSAL REQUIRED:12/6/22 CHANGE ORIGINATED BY: Contractor (14 days from Request Date, unless other date agreed to) PROPOSAL REQUESTED BY: Contractor ARCHITECTCOR PM WE AGREE TO PERFORM ALL CHANGE IN THE WORK DESCRIBED IN THE PROPOSAL REQUEST FOR: CONTRACT SUM: (WASHINGTON STATE SALES TAX EXCLUDED) In accordance with the general condition, Cost Estimate Detail Sheet(s) are attached hereto. CONTRACT TIME: OF 0 CALENDAR DAYS BY: CONTRACTOR SIGNATURE DATE We have carefully examined this proposal and find the cost to be reasonable.Therefore, we recommend acceptance. ARCHITECT DATE HEALTHPOINT DATE City of Renton Authorized Signature To be utilized for changes requested by HealthPoint CITY OF RENTON DATE 8,449.00$ CAG 21Ͳ180 Family First Community Center TO: Comer GC, Inc. The foregoing amount covers everything required in connection with the change. All other provisions of the contract remain in full force and effect. We understand that this proposal does not constitute authorization to proceed with the specified changes in the work until incorporation of this COP into a Change Order by the City of Renton. Revisions for stormwater systemͲbid design posed significant schedule risk due to sequencing. 03/15/22Proposal Request Date: EXPLANATION: Per above TO: Meredith Everist TO:Russ Woodruff EightͲThousand FourͲHundred and FortyͲNine Dollars WE AGREE CONTRAC TO:Mered DATE PROP (14 days from You are direct SOURCE OF CONSTRU TO:Come Revisions EXPLANATI NO CHANGE INCREASE DECREASE NO CHANGE INCREASE DECREASE Design Contractor Owner Code/AHJUnknown Conditions HealthPoint Other 1/10/2023 COMER GC, Inc.1/13/23                                                                   1 Russ Woodruff From:Meredith Everist <everistm@baylisarchitects.com> Sent:Wednesday, December 14, 2022 5:22 PM To:Russ Woodruff Cc:16-0996 Family First Community Center Subject:FW: FFCC - CI-008 - CCD-001 - Storm System Revisions Attachments:FFCC - CI-008 - CCD-001 - Storm System Revisions.pdf HIRuss,tĞbelievethecoststobereasonable. Thanks,Meredith Meredith Everist | AIA | NOMA | LEED AP BD+C Principal Pronouns: she | her 10801 Main Street, # 110 | Bellevue, WA 98004 O: 425.454.0566 D: 425.679.5205 F: 425.453.8013 everistm@baylisarchitects.com | BaylisArchitects.com Facebook | LinkedIn | Houzz From:MeredithEverist<everistm@baylisarchitects.com> Sent:Tuesday,December6,20223:13PM CAUTION: This email originated from outside the City of Renton. Do not click links, reply or open attachments unless you know the content is safe.          2 To:KeithKruger<KeithK@cplinc.com> Cc:16Ͳ0996FamilyFirstCommunityCenter<16Ͳ0996@baylisarchitects.com> Subject:FW:FFCCͲCIͲ008ͲCCDͲ001ͲStormSystemRevisions HiKeith,willyoupleasereviewandcommentifthereareanyconcernswiththeattachedchangerequest? Thanks,Meredith Meredith Everist | AIA | NOMA | LEED AP BD+C Principal Pronouns: she | her 10801 Main Street, # 110 | Bellevue, WA 98004 O: 425.454.0566 D: 425.679.5205 F: 425.453.8013 everistm@baylisarchitects.com | BaylisArchitects.com Facebook | LinkedIn | Houzz From:LukeComer<luke@comergc.com> Sent:Tuesday,December6,20229:23AM To:'RussWoodruffͲCityofRenton'<rwoodruff@rentonwa.gov>;MeredithEverist<everistm@baylisarchitects.com> Cc:'TimComer'<tim@comergc.com>;JonScofield<jon@comergc.com> Subject:FFCCͲCIͲ008ͲCCDͲ001ͲStormSystemRevisions Team– Attachedispricingfor:FFCCͲCIͲ008ͲCCDͲ001ͲStormSystemRevisions,whichrelatestothestormrevisions primarilyrelatedtothechangetotheundergroundCuIltechSystem.Thisupfrontchangeinsystemwouldbeoneitem theteamcanlookbackonastheprimaryreasonforbenefittingthesiteschedulefortheproject.Thissystemwasable tobeprocuredmoretimely,andinstalledmoretimely,whichsettheprojectupforsuccess.McKeewasabletomake thesemodificationswithnoadditionalcosts,howeverCPLhadcostsinresubmitting/redesignwhichiswhatisbeing submittedon. TheonlyotherminorcostassociatedistheremobilizationofourstripingsubtoreͲstripethecrosswalkoriginallydeleted thattheRSDwantedback. Thank you, Luke Comer C:425Ͳ765Ͳ4118IP:425Ͳ636Ͳ8934IF:425Ͳ285Ͳ9785          PUBLIC WORKS Facilities Division Project No:CCD # 45 CONSTRUCTION CHANGE DIRECTIVE Project Name: (CCD) (CONTRACTOR) You are directed to prepare a cost proposal for the work described below and/or detailed on the attachment referred to: CEOFCHANGE: DATE PROPOSAL REQUIRED:12/20/22 CHANGE ORIGINATED BY: Design team (14 days from Request Date, unless other date agreed to) PROPOSAL REQUESTED BY: Contractor ARCHITECTCOR PM WE AGREE TO PERFORM ALL CHANGE IN THE WORK DESCRIBED IN THE PROPOSAL REQUEST FOR: CONTRACT SUM: (WASHINGTON STATE SALES TAX EXCLUDED) In accordance with the general condition, Cost Estimate Detail Sheet(s) are attached hereto. CONTRACT TIME: OF 0 CALENDAR DAYS BY: CONTRACTOR SIGNATURE DATE We have carefully examined this proposal and find the cost to be reasonable.Therefore, we recommend acceptance. ARCHITECT DATE HEALTHPOINT DATE City of Renton Authorized Signature To be utilized for changes requested by HealthPoint CITY OF RENTON DATE CAG 21Ͳ180 Family First Community Center TO: Comer GC, Inc. The foregoing amount covers everything required in connection with the change. All other provisions of the contract remain in full force and effect. We understand that this proposal does not constitute authorization to proceed with the specified changes in the work until incorporation of this COP into a Change Order by the City of Renton. Add garbage disposal to demonstration kitchen 08/24/22Proposal Request Date: EXPLANATION: Per above TO: Meredith Everist TO:Russ Woodruff SevenͲHundred SeventyͲOne Dollars 771.00$ WE AGREE CONTRAC TO:Mered DATE PROP (14 days from You are direct OF CHANGE: CONSTRU TO:Come Add garba EXPLANATI NO CHANGE INCREASE DECREASE NO CHANGE INCREASE DECREASE Design Contractor Owner Code/AHJUnknown Conditions HealthPoint Other 1/10/2023 COMER GC, Inc.1/13/23                                                                            1 Russ Woodruff From:Meredith Everist <everistm@baylisarchitects.com> Sent:Thursday, December 22, 2022 11:22 AM To:Russ Woodruff Cc:16-0996 Family First Community Center Subject:FW: FFCC - CI-045 - CCD-011 - Added Garbage Disposal - Plumbing Attachments:FFCC - CI-045 - CCD-011 - Added Garbage Disposal - Plumbing.pdf HIRuss,thischangeitemseemsreasonable.  Thanks,Meredith  Meredith Everist | AIA | NOMA | LEED AP BD+C Principal Pronouns: she | her 10801 Main Street, # 110 | Bellevue, WA 98004 O: 425.454.0566 D: 425.679.5205 F: 425.453.8013 everistm@baylisarchitects.com | BaylisArchitects.com Facebook | LinkedIn | Houzz  From:LukeComer<luke@comergc.com> Sent:Tuesday,December20,202211:15AM To:'RussWoodruffͲCityofRenton'<rwoodruff@rentonwa.gov>;MeredithEverist<everistm@baylisarchitects.com> Cc:'TimComer'<tim@comergc.com>;JonScofield<jon@comergc.com> Subject:FFCCͲCIͲ045ͲCCDͲ011ͲAddedGarbageDisposalͲPlumbing  Team– Attachedispricingfor:FFCCͲCIͲ045ͲCCDͲ011ͲAddedGarbageDisposalͲPlumbing,whichrelatestoadded garbagedisposal,relatedplumbinginstallandcoordinationperCCDͲ011.Noteelectricalplanshadpowertothis,so therewerenoadditionalcostsrelatedelectrically.   Thank you,  Luke Comer C:425Ͳ765Ͳ4118IP:425Ͳ636Ͳ8934IF:425Ͳ285Ͳ9785  CAUTION: This email originated from outside the City of Renton. Do not click links, reply or open attachments unless you know the content is safe.           PUBLIC WORKS Facilities Division Project No:CCD # 46 CONSTRUCTION CHANGE DIRECTIVE Project Name: (CCD) (CONTRACTOR) You are directed to prepare a cost proposal for the work described below and/or detailed on the attachment referred to: CEOFCHANGE: DATE PROPOSAL REQUIRED:12/20/22 CHANGE ORIGINATED BY: Design team (14 days from Request Date, unless other date agreed to) PROPOSAL REQUESTED BY: Contractor ARCHITECTCOR PM WE AGREE TO PERFORM ALL CHANGE IN THE WORK DESCRIBED IN THE PROPOSAL REQUEST FOR: CONTRACT SUM: (WASHINGTON STATE SALES TAX EXCLUDED) In accordance with the general condition, Cost Estimate Detail Sheet(s) are attached hereto. CONTRACT TIME: OF 0 CALENDAR DAYS BY: CONTRACTOR SIGNATURE DATE We have carefully examined this proposal and find the cost to be reasonable.Therefore, we recommend acceptance. ARCHITECT DATE HEALTHPOINT DATE City of Renton Authorized Signature To be utilized for changes requested by HealthPoint CITY OF RENTON DATE 1,016.00$ CAG 21Ͳ180 Family First Community Center TO: Comer GC, Inc. The foregoing amount covers everything required in connection with the change. All other provisions of the contract remain in full force and effect. We understand that this proposal does not constitute authorization to proceed with the specified changes in the work until incorporation of this COP into a Change Order by the City of Renton. Revise PͲlam on casework in demo kitchen 08/24/22Proposal Request Date: EXPLANATION: Per above TO: Meredith Everist TO:Russ Woodruff OneͲThousand and Sixteen Dollars WE AGREE CONTRAC TO:Mered DATE PROP (14 days from You are direct OF CHANGE: CONSTRU TO:Come Revise PͲla EXPLANATI NO CHANGE INCREASE DECREASE NO CHANGE INCREASE DECREASE Design Contractor Owner Code/AHJUnknown Conditions HealthPoint Other 1/10/2023 COMER GC, Inc.1/13/23                                                                   1 Russ Woodruff From:Meredith Everist <everistm@baylisarchitects.com> Sent:Thursday, December 22, 2022 9:36 AM To:Russ Woodruff Cc:16-0996 Family First Community Center Subject:FW: FFCC - CI-046 - ASI-010 - PLAM Changes @ Demo Kitchen Island Attachments:FFCC - CI-046 - ASI-010 - PLAM Changes @ Demo Kitchen Island.pdf HIRuss,wereviewedthisChangeItemandthepricinglooksreasonable.  Thanks,Meredith  Meredith Everist | AIA | NOMA | LEED AP BD+C Principal Pronouns: she | her 10801 Main Street, # 110 | Bellevue, WA 98004 O: 425.454.0566 D: 425.679.5205 F: 425.453.8013 everistm@baylisarchitects.com | BaylisArchitects.com Facebook | LinkedIn | Houzz  From:LukeComer<luke@comergc.com> Sent:Tuesday,December20,202211:30AM To:'RussWoodruffͲCityofRenton'<rwoodruff@rentonwa.gov>;MeredithEverist<everistm@baylisarchitects.com> Cc:'TimComer'<tim@comergc.com>;JonScofield<jon@comergc.com> Subject:FFCCͲCIͲ046ͲASIͲ010ͲPLAMChanges@DemoKitchenIsland  Team– Attachedispricingfor:FFCCͲCIͲ046ͲASIͲ010ͲPLAMChanges@DemoKitchenIsland,whichrelatestoPLAM changesattheKitchenDemoislandperASIͲ010.PLAMfortheprojecthadalreadybeenordered,thischangeincolor requiredadditionalsheetstobeorderedandprocessed.   Thank you,  Luke Comer C:425Ͳ765Ͳ4118IP:425Ͳ636Ͳ8934IF:425Ͳ285Ͳ9785  CAUTION: This email originated from outside the City of Renton. Do not click links, reply or open attachments unless you know the content is safe.           PUBLIC WORKS Facilities Division Project No:CCD # 49 CONSTRUCTION CHANGE DIRECTIVE Project Name: (CCD) (CONTRACTOR) You are directed to prepare a cost proposal for the work described below and/or detailed on the attachment referred to: CEOFCHANGE: DATE PROPOSAL REQUIRED:12/20/22 CHANGE ORIGINATED BY: AHJ Inspector (14 days from Request Date, unless other date agreed to) PROPOSAL REQUESTED BY: Contractor ARCHITECTCOR PM WE AGREE TO PERFORM ALL CHANGE IN THE WORK DESCRIBED IN THE PROPOSAL REQUEST FOR: CONTRACT SUM: (WASHINGTON STATE SALES TAX EXCLUDED) In accordance with the general condition, Cost Estimate Detail Sheet(s) are attached hereto. CONTRACT TIME: OF 0 CALENDAR DAYS BY: CONTRACTOR SIGNATURE DATE We have carefully examined this proposal and find the cost to be reasonable.Therefore, we recommend acceptance. ARCHITECT DATE HEALTHPOINT DATE City of Renton Authorized Signature To be utilized for changes requested by HealthPoint CITY OF RENTON DATE Family First Community Center TO: Comer GC, Inc. The foregoing amount covers everything required in connection with the change. All other provisions of the contract remain in full force and effect. We understand that this proposal does not constitute authorization to proceed with the specified changes in the work until incorporation of this COP into a Change Order by the City of Renton. Install added valve per direction of AHJ Inspector 08/24/22Proposal Request Date: EXPLANATION: Per above TO: Meredith Everist TO:Russ Woodruff TenͲThousand TwoͲHundred and Thirty Nine Dollars 10,239.00$ CAG 21Ͳ180 WE AGREE CONTRAC TO:Mered DATE PROP (14 days from You are direct OF CHANGE: CONSTRU TO:Come Install add EXPLANATI NO CHANGE INCREASE DECREASE NO CHANGE INCREASE DECREASE Design Contractor Owner Code/AHJUnknown Conditions HealthPoint Other 1/10/2023 COMER GC, Inc.1/13/23                                        1 Russ Woodruff From:Meredith Everist <everistm@baylisarchitects.com> Sent:Friday, January 6, 2023 1:51 PM To:Russ Woodruff Cc:16-0996 Family First Community Center Subject:FW: FFCC - CI-049 - Added Valve Outside of Oil and Water Separator COR Tom Main Attachments:FFCC - CI-049 - Added Valve Outside of Oil and Water Separator COR Tom Main.pdf HiRuss,webelievethesecoststobefairandreasonable. Thanks,Meredith Meredith Everist | AIA | NOMA | LEED AP BD+C Principal Pronouns: she | her 10801 Main Street, # 110 | Bellevue, WA 98004 O: 425.454.0566 D: 425.679.5205 F: 425.453.8013 everistm@baylisarchitects.com | BaylisArchitects.com Facebook | LinkedIn | Houzz From:KeithKruger<KeithK@cplinc.com> Sent:Friday,January6,20231:43PM To:MeredithEverist<everistm@baylisarchitects.com> Cc:16Ͳ0996FamilyFirstCommunityCenter<16Ͳ0996@baylisarchitects.com> Subject:RE:FFCCͲCIͲ049ͲAddedValveOutsideofOilandWaterSeparatorCORTomMain Yes,thosewerefine. Keith Kruger, PE, LEED AP Associate Principal COUGHLINPORTERLUNDEEN STRUCTURAL CIVIL SEISMIC ENGINEERING 801 SECOND AVE / SUITE 900 / SEATTLE WA 98104 P: 206.343.0460 / cplinc.com From:MeredithEverist<everistm@baylisarchitects.com> Sent:Friday,January6,20231:03PM To:KeithKruger<KeithK@cplinc.com> Cc:16Ͳ0996FamilyFirstCommunityCenter<16Ͳ0996@baylisarchitects.com> Subject:FW:FFCCͲCIͲ049ͲAddedValveOutsideofOilandWaterSeparatorCORTomMain HIKeith,dothecostslooktobefairandreasonable? Thanks,Meredith CAUTION: This email originated from outside the City of Renton. Do not click links, reply or open attachments unless you know the content is safe.          PUBLIC WORKS Facilities Division Project No:CCD # 59 CONSTRUCTION CHANGE DIRECTIVE Project Name: (CCD) (CONTRACTOR) You are directed to prepare a cost proposal for the work described below and/or detailed on the attachment referred to: SOURCE OF CHANGE: DATE PROPOSAL REQUIRED:1/9/23 CHANGE ORIGINATED BY: Civil (14 days from Request Date, unless other date agreed to) PROPOSAL REQUESTED BY: Contractor ARCHITECTCOR PM WE AGREE TO PERFORM ALL CHANGE IN THE WORK DESCRIBED IN THE PROPOSAL REQUEST FOR: CONTRACT SUM: (WASHINGTON STATE SALES TAX EXCLUDED) In accordance with the general condition, Cost Estimate Detail Sheet(s) are attached hereto. CONTRACT TIME: OF 0 CALENDAR DAYS BY: CONTRACTOR SIGNATURE DATE We have carefully examined this proposal and find the cost to be reasonable.Therefore, we recommend acceptance. ARCHITECT DATE HEALTHPOINT DATE City of Renton Authorized Signature To be utilized for changes requested by HealthPoint CITY OF RENTON DATE Family First Community Center TO: Comer GC, Inc. The foregoing amount covers everything required in connection with the change. All other provisions of the contract remain in full force and effect. We understand that this proposal does not constitute authorization to proceed with the specified changes in the work until incorporation of this COP into a Change Order by the City of Renton. Add flush curb at bioswale to protect asphalt 09/28/22Proposal Request Date: EXPLANATION: Per above TO: Meredith Everist TO:Russ Woodruff SevenͲThousand FourͲHundred and EightyͲFour Dollars 7,484.00$ CAG 21Ͳ180 WE AGREE CONTRAC TO:Mered DATE PROP (14 days from You are direct SOURCE OF CONSTRU TO:Come Add flush EXPLANATI NO CHANGE INCREASE DECREASE NO CHANGE INCREASE DECREASE Design Contractor Owner Code/AHJUnknown Conditions HealthPoint Other 1/12/2023 COMER GC, Inc.1/13/23                                                          1 Russ Woodruff From:Meredith Everist <everistm@baylisarchitects.com> Sent:Wednesday, January 11, 2023 8:49 AM To:Russ Woodruff Cc:16-0996 Family First Community Center Subject:FW: FFCC - CI-059 - Flush Concrete Curb in lieu of mulch at east parking lot Attachments:FFCC - CI-059 - Flush Concrete Curb in lieu of mulch at east parking lot HiRuss,wetakenoexceptionstothischangeitem.  Thanks,Meredith  Meredith Everist | AIA | NOMA | LEED AP BD+C Principal Pronouns: she | her 10801 Main Street, # 110 | Bellevue, WA 98004 O: 425.454.0566 D: 425.679.5205 F: 425.453.8013 everistm@baylisarchitects.com | BaylisArchitects.com Facebook | LinkedIn | Houzz  From:KeithKruger<KeithK@cplinc.com> Sent:Tuesday,January10,20239:05PM To:MeredithEverist<everistm@baylisarchitects.com> Cc:16Ͳ0996FamilyFirstCommunityCenter<16Ͳ0996@baylisarchitects.com> Subject:RE:FFCCͲCIͲ059ͲFlushConcreteCurbinlieuofmulchateastparkinglot  Meredith,  Thiscostisreasonable.  thanks  Keith Kruger, PE, LEED AP Associate Principal COUGHLINPORTERLUNDEEN STRUCTURAL CIVIL SEISMIC ENGINEERING 801 SECOND AVE / SUITE 900 / SEATTLE WA 98104 P: 206.343.0460 / cplinc.com  From:MeredithEverist<everistm@baylisarchitects.com> Sent:Tuesday,January10,20239:16AM To:KeithKruger<KeithK@cplinc.com> Cc:16Ͳ0996FamilyFirstCommunityCenter<16Ͳ0996@baylisarchitects.com> Subject:FW:FFCCͲCIͲ059ͲFlushConcreteCurbinlieuofmulchateastparkinglot CAUTION: This email originated from outside the City of Renton. Do not click links, reply or open attachments unless you know the content is safe.           2  HiKeith,willyoupleasereviewcostsonthisChangeItem?  Thanks,Meredith  Meredith Everist | AIA | NOMA | LEED AP BD+C Principal Pronouns: she | her 10801 Main Street, # 110 | Bellevue, WA 98004 O: 425.454.0566 D: 425.679.5205 F: 425.453.8013 everistm@baylisarchitects.com | BaylisArchitects.com Facebook | LinkedIn | Houzz  From:LukeComer<luke@comergc.com> Sent:Monday,January9,20232:16PM To:'RussWoodruff'<RWoodruff@Rentonwa.gov>;MeredithEverist<everistm@baylisarchitects.com> Cc:'TimComer'<tim@comergc.com>;JonScofield<jon@comergc.com> Subject:FFCCͲCIͲ059ͲFlushConcreteCurbinlieuofmulchateastparkinglot  Team– Attachedispricingfor:FFCCͲCIͲ059ͲFlushConcreteCurbinlieuofmulchateastparkinglot,whichrelatesto theedgeconditionatthebioretentionwithintheeastparkinglot.CityofRentonhadamulchdetail,buttherewas concernwiththeasphaltnotabuttingasolidsurface,andpotentiallyseeinglongtermeffectsofitbreakingoff.Aflush concretecurbwasinstalledtohavetheasphaltabutasolidsurface.    Thank you,  Luke Comer C:425Ͳ765Ͳ4118IP:425Ͳ636Ͳ8934IF:425Ͳ285Ͳ9785