Parks Planning and Natural Resources FIELD REPORT
Field Report No. FR-048
CAG-22-013 Site Date/Time:2.8.2023 8:00 AM
Kiwanis Park Improvements Project Location:Kiwanis Park
To:Vern Orr, TDI Copy To:File
Chris Polk, TDI M. Faulkner, BDA
BDA Sherryl Sales, BDA
Pat Decaro, COR
Weather/Temperature:Mostly Sunny XX0
Alan J. Wyatt, COR PPNR
Meeting:Site Conditions:Workable Areas
Chris Polk, Kevin Kern, TDI
Contractor:Terra Dynamics, Inc.
Item:Observations/Remarks:Action/Status:
1 Infield mix of rubber/sand place in synthetic turf completed.TDI
2 Placement of soil for rough grading berms along first base line and south walk. TDI
3 Outfield finish grading and preparation for sodding. TDI
4 Pavilion structure being erected within the Parent Plaza area.TDI
5 Excavation for walk curbs for walk between tennis court and playground. TDI
6 Rough grading of berm between tennis court and playground. TDI
7 Decorative fence posts installed along north planting area. TDI
8 Drainage grate installed at entry plaza at Union Avenue.TDI
We believe the above record to be an accurate summary of decisions and related discussions. We would appreciate notification of exceptions
to this record within ten (10) days of receipt. Failing such notification, we will consider this a statement of fact with which you concur.
Alan J. Wyatt 2/9/2023
Submitted by:Date:
Present at Site/
February 9, 2023Date:
Contract No.
Project Name:
City of Renton
1055 S. Grady Way
Renton, WA 98057 1
City of Renton Parks and Recreation
Parks Planning and Natural Resources FIELD REPORT
1 BALLFIELD
Infield mix of
rubber/sand applied
to synthetic turf.
Closeup photo of
sand/rubber mix in
synthetic turf.
2 PARENT PLAZA
Pavilion structure
started to be
erected on-site.
City of Renton
1055 S. Grady Way
Renton, WA 98057 2
City of Renton Parks and Recreation
Parks Planning and Natural Resources FIELD REPORT
3 PARENT PLAZA
Pavilion structure
being erected
on-site.
4 SITE
Berm rough graded
between tennis
court and playground.
City of Renton
1055 S. Grady Way
Renton, WA 98057 3
City of Renton Parks and Recreation
Parks Planning and Natural Resources FIELD REPORT
5 SITE
Excavation for
curb walls for walk
between tennis
court and playground.
Berm rough graded
between tennis
court and playground.
6 SITE
Excavation for
curb walls for walk
between tennis
court and playground.
Berm rough graded
between tennis
court and playground.
City of Renton
1055 S. Grady Way
Renton, WA 98057 4
City of Renton Parks and Recreation
Parks Planning and Natural Resources FIELD REPORT
7 SITE
Excavation for
curb walls for walk
between tennis
court and playground.
Berm rough graded
between tennis
court and playground.
8 UNION AVENUE
Entrance Plaza
Photo shows walk
from south side of
park site coming
down to the
entrance plaza at
Union Avenue.
City of Renton
1055 S. Grady Way
Renton, WA 98057 5
City of Renton Parks and Recreation
Parks Planning and Natural Resources FIELD REPORT
9 UNION AVENUE
Entrance Plaza
Installation of
drainage grating at
entrance plaza at
Union Avenue.
10 UNION AVENUE
Entrance Plaza
Installation of
drainage grating at
entrance plaza at
Union Avenue.
City of Renton
1055 S. Grady Way
Renton, WA 98057 6
City of Renton Parks and Recreation
Parks Planning and Natural Resources FIELD REPORT
11 UNION AVENUE
Image shows
installation of
decorative fence
posts for planting
area along north
retaining wall along
Union Avenue.
12 UNION AVENUE
Image shows
installation of
decorative fence
posts for planting
area along north
retaining wall along
Union Avenue.
City of Renton
1055 S. Grady Way
Renton, WA 98057 7
City of Renton Parks and Recreation
Parks Planning and Natural Resources FIELD REPORT
13 SITE
Rough grading
of park site, west
of park entry off
Union Avenue.
14 BALLFIELD
Finish grading and
sod preparation at
outfield for ballfield.
City of Renton
1055 S. Grady Way
Renton, WA 98057 8
City of Renton Parks and Recreation
Parks Planning and Natural Resources FIELD REPORT
15 SITE
Placement of soil
for berms along
first base line at
south side of park.
16 SITE
Rough grading and
placement of soil
for berms along
first base line on
south side of park,
between south walk
and ballfield.
City of Renton
1055 S. Grady Way
Renton, WA 98057 9