HomeMy WebLinkAboutSR_Tier1_TUP_Night_Work_230320DEPARTMENT OF COMMUNITY AND ECONOMIC DEVELOPMENT SR_Tier1_TUP_Night_Work_230320 PLANNING DIVISION TIER 1 TEMPORARY USE PERMIT EVALUATION FORM & DECISION DATE OF DECISION: March 20, 2023 PROJECT NUMBER: LUA23-000084, TP PROJECT NAME: Rainier Ave S Corridor Improvements - Phase 4 Night Work PROJECT MANAGER: Clark H. Close, Principal Planner APPLICANT/CONTACT: Michelle Faltaous, Project Manager 1055 S Grady Way Renton, WA 98057 OWNER: City of Renton 1055 S Grady Way Renton, WA 98057 PROJECT LOCATION: Approximately from S 3rd St to NW 3rd Pl, Renton WA 98057 DATE OF EXPIRATION: September 20, 2023 PROJECT DESCRIPTION: The applicant, City of Renton Public Works Department Transportation Design Engineering Division (“Transportation Division”), is requesting a Tier 1 Temporary Use Permit (TUP) to work non-consecutive nights beyond the hours permitted in Renton Municipal Code (RMC) 4-4-030C.3 in order to begin construction on the Rainier Ave S Corridor Improvements – Phase 4 project. The proposed night time work along Rainier Ave S would be from approximately S 3rd St to NW 3rd Pl (Exhibits 1 and 2). The night time work is being proposed for safety purposes and to minimize congestion impacts to drivers, businesses, and residents during the day within this busy traffic and commerce corridor. It is anticipated that the night time work would be required at various times throughout the duration of the 500 working days needed to complete the project by March 2025. The project contractor, Pivetta Brother’s Construction, Inc., is anticipating that night work would begin during the 12th week 2023 with items identified in the five (5) week lookahead schedule (Exhibit 3). Examples of proposed night time work activities would include potholing, tree removal, median removal, temporary striping, and Joint Utility Trench (JUT) installation. As part of the construction management contract, the City is working with a public outreach firm. The project goals include the following: • Improvement of transit mobility, pedestrian accessibility, and safety. • Benefits to the overall traffic flow and safety through access management, traffic signal upgrades and coordination. DocuSign Envelope ID: BA9B37E0-31B1-450C-94CC-E6B738B5A66F City of Renton Department of Community & Economic Development Temporary Use Permit Rainier Ave S Corridor Improvements - Phase 4 Night Work LUA23-000084, TP Permit Date: March 20, 2023 Page 2 of 3 SR_Tier1_TUP_Night_Work_230320 • Improvement of the pedestrian environment and safety resulting in an aesthetically vibrant transportation corridor. • Intersection improvements at S 3rd St and S 2nd St in preparation of the two-way conversion. • Extension of the southbound Business Access Transit Lane (BAT Lane) from S 2nd St to S 3rd St. • Construction of a segment of a regional pedestrian/bike path trail (Lake Washington Loop Trail) from Airport Way to 1,000 feet north of Airport Way. • Installation of pedestrian activated traffic signals (HAWK) at SW Victoria St and NW 3rd Pl. • Sidewalk widening with streetscaping, decorative roadway and pedestrian-scale illumination, landscaped buffers and median. • Improvement of the city water and wastewater systems concurrently with the transportation project improvements. The Temporary Use Permit is hereby Approved with Conditions* and subject to the following conditions: *CONDITIONS OF APPROVAL: 1. All vehicles shall be equipped with broadband backup warning devices. 2. All trucks performing export haul shall have well maintained bed liners to reduce noise impacts. 3. During construction cleanup operations, all material spilled within the work zone shall be removed by hand methods or sweeping when feasible. 4. Truck tailgate banging is prohibited. All truck tailgates must be secured to prevent excessive noise from banging. 5. Any unwanted material shall be removed by sweeping. No scraping type equipment shall be used during nighttime work to clean up unwanted materials in lieu of hand or street sweepers. Other normal construction uses of front-end loaders, track hoes, and dozers are allowed. 6. Construction equipment operating under stationary conditions, such as but not limited to; saw cutters, front loaders, light plants, jackhammers, and generators, are allowed provided temporary noise shields are used. The Contractor shall use accepted acoustic noise blankets, or other means available for noise shielding as approved by the Engineer. 7. The applicant shall provide to the City of Renton, contractor contact information: name(s) and email(s) to respond to night time noise complaints. 8. The applicant or contractor shall provide a live person to address any complaints during the night time work. Complaints shall be responded to promptly by the designated contact person. 9. The applicant or contractor shall notify residents of night work if work is within a 500-foot radius of the night work. 10. Contractor vehicles and construction equipment shall be parked only in city approved designated areas. 11. Idling vehicles are not allowed. 12. If the same resident continues to have complaints about excessive noise levels, the contractor or applicant shall provide additional mitigation, such as, but not limited to, shielding of noise source, reducing use of certain types of equipment, providing ear plugs, providing white noise machines, or providing motel accommodations. 13. The applicant shall apply for a Hearing Examiner Noise Variance Application for the Rainier Ave S Corridor Improvements - Phase 4 Project night work by April 20, 2023, unless otherwise determined by the Community and Economic Development Administrator. DocuSign Envelope ID: BA9B37E0-31B1-450C-94CC-E6B738B5A66F City of Renton Department of Community & Economic Development Temporary Use Permit Rainier Ave S Corridor Improvements - Phase 4 Night Work LUA23-000084, TP Permit Date: March 20, 2023 Page 3 of 3 SR_Tier1_TUP_Night_Work_230320 SIGNATURE AND DATE OF DECISION: ________________________________________ ____________________________________ Vanessa Dolbee, Planning Director Date RECONSIDERATION: Within 14 days of the decision date, any party may request that the decision be reopened by the approval body. The approval body may modify his decision if material evidence not readily discoverable prior to the original decision is found or if he finds there was misrepresentation or fact. After review of the Reconsideration request, if the approval body finds sufficient evidence to amend the original decision, there will be no further extension of the appeal period. Any person wishing to take further action must file a formal appeal within the 14-day appeal time frame. APPEALS: Appeals of permit issuance must be filed in writing on or before 5:00 p.m. on April 3, 2023. Appeals must be submitted electronically to the City Clerk at cityclerk@rentonwa.gov or delivered to City Hall 1st floor Lobby Hub Monday through Friday. The appeal fee, normally due at the time an appeal is submitted, will be collected at a future date if your appeal is submitted electronically. The appeal submitted in person may be paid on the first floor in our Finance Department. Appeals to the Hearing Examiner are governed by RMC 4-8- 110 and additional information regarding the appeal process may be obtained from the City Clerk’s Office, cityclerk@rentonwa.gov. EXPIRATION: The Temporary Use Permit is valid for up to six (6) months from the effective date of the permit. The applicant can request that a permit be valid for up to five (5) years at time of application or prior to permit expiration. EXTENSIONS: Extension requests do not require additional fees and shall be requested in writing to the Community and Economic Development Administrator. DocuSign Envelope ID: BA9B37E0-31B1-450C-94CC-E6B738B5A66F 3/20/2023 | 5:46 PM PDT EXHIBIT 1 DocuSign Envelope ID: BA9B37E0-31B1-450C-94CC-E6B738B5A66F EXHIBIT 2 DocuSign Envelope ID: BA9B37E0-31B1-450C-94CC-E6B738B5A66F Job#LEGEND Contract #BEGINNING:February 26, 2023 X Day ?Tenative Project Name:Rainier Ave S - Phase 4 ENDING:April 1, 2023 N Night M Material sun mon tue wed thu fri sat sun mon tue wed thu fri sat sun mon tue wed thu fri sat sun mon tue wed thu fri sat sun mon tue wed thu fri sat sun mon tue wed thu fri sat 2/19 2/20 2/21 2/22 2/23 2/24 2/25 2/26 2/27 2/28 3/1 3/2 3/3 3/4 3/5 3/6 3/7 3/8 3/9 3/10 3/11 3/12 3/13 3/14 3/15 3/16 3/17 3/18 3/19 3/20 3/21 3/22 3/23 3/24 3/25 3/26 3/27 3/28 3/29 3/30 3/31 4/1 1 Renton Preconstruction Meeting X 2 Renton Receive Notice to Proceed X 3 Renton Utility Preconstruction Meeting ? 4 5 Mobilization 6 Pivetta Setup/Install Temporary Field Offices Laydown X X X X X X X X X X 7 Pivetta Setup School Yard Laydown Area School Laydown 8 PSE PSE Energize Power Laydown ???? 9 Pivetta Install Project Signs Project M X 10 North Peak Survey Existing Topography (Flyover)Project X X 11 Pivetta Setup GPS Project X 12 North Peak Stake Control Points Project X X 13 Utilities Utility Locates Project X X X X X 14 Pivetta Perform Existing Condition Survey Project X X X X X X X X X X 15 Pivetta TBD - Lanes Utility Potholing - Day Project X X X X X X X X X X X X X X X 16 Pivetta TBD - Lanes Utility Potholing - Night Project N N N N N N N N 17 18 Pivetta Setup Business Signs Project M Setup As Needed 19 Pivetta TBD - Lanes Install Catch Basin Filters Project X 20 Pivetta Install Silt Fence/Tree Protection Stage 1 X 21 22 Stage 1 Channelization 23 Evergreen TCP #1 Sawcut Median Rainier/3rd Ave N 24 Pivetta TCP #1 Remove Median (STA 14+00 to STA 15+50) & Temp HMA Rainier/3rd Ave N N N 25 Pivetta In Work Layout for Temp Striping/Channelization Project N N 26 27 Golden Gate Pull wire for temp camera signal installation Project X X X X X 28 Golden Gate Stage Portable Signal System Rainier/S 2nd St X 29 SPM In Work Install Temp Striping for Stage 1 Rainier/S 2nd St N N N 30 Golden Gate In Work Adjust Signal Cameras and Install Temp Cameras 3rs st/2nd st/Airport N N N 31 Golden Gate Install Portable Signal System Rainier/S 2nd St N 32 Pivetta Install Barrier at Signal System Rainier/S 2nd St N 33 Stage 1 Channelization Complete X X 34 35 Removals 36 Pivetta Fence Removal Rainier/3rd Ave Fill In Work - As Time Allows 37 Pivetta/COR Tag Trees for Removal Project X X X 38 Pacific Tree In Work Remove Trees Project N N N N 39 Pivetta In Work Remove East Sidewalk not ADA Compliant (Patch with HMA)East 21+00 to 28+00 N N N 40 41 42 Joint Utility Trench 43 North Peak Stake Utility Structures Project X X X 44 Pivetta Provide Request for Structures and Conduit Project X 45 46 Utilities Receive Utility Structures 2nd St X-ing X X 47 Evergreen TCP 4 & 5, TBD Sawcut for JUT 2nd St X-ing N N 48 Pivetta Install JUT Vaults for 2nd St Crossing 2nd St X-ing N N N N 49 Golden Gate TCP 4 & 5, TBD Install JUT Conduit 2nd St X-ing N N 50 51 Utilities Receive Utility Structures 15+25 to 18+40 X X 52 Pivetta Install JUT Utility Structures 15+25 to 18+40 X X 53 Golden Gate Install JUT Conduit 15+25 to 18+40 54 55 Sewer Line 56 Insituform Clean and Video Existing Sewer Project 57 58 Submitted By Description of Material 59 60 61 62 63 64 Submitted By Description of Submittal 65 66 Past Week Look Ahead Week 1 Look Ahead Week 2 Look Ahead Week 3 Look Ahead Week 4 5 WEEK LOOKAHEAD SCHEDULE2022-148 CAG-22-163 Date Submitted Date Submitted Submittals/material Procurement Needed RFI's Pending Responsibility TC REQ.TESTING / INSP. ActivityLine No.Location Current Week 2.27.23 5-week Look-ahead 2/28/2023 1 of 1 EXHIBIT 3 DocuSign Envelope ID: BA9B37E0-31B1-450C-94CC-E6B738B5A66F