Loading...
HomeMy WebLinkAboutChange Order - 04CONTRACT: CITY OF RENTON Parks and Recreation Department CONTRACT CHANGE ORDER AGREEMENT Kiwanis Park Improvements CAG-22-013 CONTRACTOR: Terra Dynamics, Inc. CHANGE ORDER: Four (4) SUMMARY OF PROPOSED CHANGE: Reason/Justification. Date: March 22, 2023 Rev 1 1) RPA Box enclosure required larger size to accommodate the Backflow Prevention Assembly required for 4-lnch Irrigation supply Installed. 2) Light pole coupling conversions required to adapt square base bolts to circular light pole base. 3) Park signage modifications to meet City park adopted standards for signage, Extension of contract time of sixty-one calendar days to complete work. DESCRIPTION: Item No. Qty. Description 1 1 TDI COP #15, 2/21/2023, RPA Box Englargement 2 1 TDI COP #16, 2/21/2023, Light Pole Conversion Couplings 3 1 TDI COP #17, 3/21/2023, Park Signage Modifications I I I ORIGINAL CONTRACT CURRENT CONTRACT NET CHANGE AMOUNT AMOUNT THIS ORDER $ 4,780,000.00 $ 4,821,942.00 $ w/oWSST w/oWSST Additional Calendar Days: Sixty-one (61) calendar days added to Contract Time• Contract Date May 31, 2023. Unit Price Amount w/oWSST w/oWSST $1,651.50 $ 1,651.50 $2,169.86 $ 2,169.86 $13,676.05 $ 13,676.05 Total this Change Order: $ 17,497.41 REVISED CONTRACT TOTAL AFTER CHANGE 17,497.41 $ 4,839,439.41 w/oWSST w/oWSST The payment specified and agreed to in this change order includes every claim by the contractor for any extra payment with respect to the work described 1n this change order, The work covered by this change order must be performed under the same terms and conditions as that included In the original agreement. All of the other terms of the original agreement remain in effect. SIGNATURES: Contractor: Project Manager: Approved By: X�E� Jarod E Emerson CA. CLT, PM A&ut.-S;j: W�g:tr� t1 r� Date. 3/29/23 Date 3/29/2023 Oare: 3/�/2.3 CAG-22-013, CO #4-23 Kiwanis Park Renton - COP #15 - RPA Box Enlargement 2/21/2023 Labor Rate/MH No.Hours Subtotal -$ -$ -$ -$ -$ -$ -$ Labor Subtotal -$ Small Tools 3%-$ Health and Safety 2%-$ Supervision 5%-$ Labor Total -$ Equipment Rate/MH No.Hours Subtotal Equipment -$ Equipment Total -$ Materials Qty Unit Cost/Unit Subtotal Origional 60" Enclosure 1.00 EA (2,385.88)$ (2,385.88)$ New 75" Enclosure 1.00 EA 3,776.97$ 3,776.97$ Materials 1,391.09$ Materials Total 1,391.09$ Subtotal of Contractor Work 1,391.09$ Overhead < $50,000 12%166.93$ Overhead > $50,000 4% Profit of Contractor Work 6%93.48$ Contractor Subtotal 1,651.50$ Subcontractors Qty Unit Cost/Unit Subtotal -$ -$ -$ -$ -$ -$ Subcontractors -$ Subcontractor Sub Total -$ Overhead < $50,000 4%-$ Overhead > $50,000 2%-$ Profit on Subcontractors 4%-$ Subcontractor Subtotal -$ GRAND TOTAL 1,651.50$ Contract Days Required 0 Vernon Orr Vern Orr Project Manager Kiwanis Park Renton - COP #16 - Light Pole Conversion Couplings 2/21/2023 Labor Rate/MH No.Hours Subtotal -$ -$ -$ -$ -$ -$ -$ Labor Subtotal -$ Small Tools 3%-$ Health and Safety 2%-$ Supervision 5%-$ Labor Total -$ Equipment Rate/MH No.Hours Subtotal Equipment -$ Equipment Total -$ Materials Qty Unit Cost/Unit Subtotal Materials -$ Materials Total -$ Subtotal of Contractor Work -$ Overhead < $50,000 12%-$ Overhead > $50,000 4% Profit of Contractor Work 6%-$ Contractor Subtotal -$ Subcontractors Qty Unit Cost/Unit Subtotal Accurate Electric 1 LS 2,006.16$ 2,006.16$ -$ -$ -$ -$ -$ Subcontractors 2,006.16$ Subcontractor Sub Total 2,006.16$ Overhead < $50,000 4%80.25$ Overhead > $50,000 2%-$ Profit on Subcontractors 4%83.46$ Subcontractor Subtotal 2,169.86$ GRAND TOTAL 2,169.86$ Contract Days Required 1 Vernon Orr Vern Orr Project Manager Kiwanis Park Renton - COP #17 - Project Signage Adjustments 3/21/2023 Labor Rate/MH No.Hours Subtotal General Labor 60.14$ 2 -1.5 (180.42)$ -$ -$ -$ -$ -$ -$ Labor Subtotal (180.42)$ Labor Total (180.42)$ Equipment Rate/MH No.Hours Subtotal Equipment -$ Equipment Total -$ Materials Qty Unit Cost/Unit Subtotal Way Finding Sign -1.00 EA 826.00$ (826.00)$ Single Side only Adjustment -1.00 EA 450.00$ (450.00)$ Additional Plan Revisions 3.00 EA 660.00$ 1,980.00$ Signage Material adjustments 1.00 LS 10,996.00$ 10,996.00$ Materials 11,700.00$ Materials Total 11,700.00$ Subtotal of Contractor Work 11,519.58$ Overhead < $50,000 12%1,382.35$ Overhead > $50,000 4% Profit of Contractor Work 6%774.12$ Contractor Subtotal 13,676.05$ Subcontractors Qty Unit Cost/Unit Subtotal -$ -$ -$ -$ -$ -$ Subcontractors -$ Subcontractor Sub Total -$ Overhead < $50,000 4%-$ Overhead > $50,000 2%-$ Profit on Subcontractors 4%-$ Subcontractor Subtotal -$ GRAND TOTAL 13,676.05$ Contract Days Required 2 Vernon Orr Vern Orr Project Manager