HomeMy WebLinkAbout20180398E003_Renton_ES_16_2023-03-02_TESC_044 www.aesgeo.com This document is considered DRAFT until reviewed and initialed by an AESI Project Manager Temporary Erosion and Sediment Control Monitoring DATE PROJECT NAME AESI PROJECT NO. TESC REPORT NO. 3/02/2023 Renton ES 16 20180398E003 044 LOCATION CITY MUNICIPALITY CSWGP 1075 Duvall Ave NE Renton Renton WAR310781 PREVIOUS SITE VISIT CLIENT/OWNER WEATHER 24 HOUR RAINFALL PAST WEEK RAINFALL 2/23/2023 Renton School District 403 Rain, 40's 0.16" 0.65" AESI FIELD REP Catherine Ikeda AESI PROJECT MANAGER Bruce Guenzler Catherine Ikeda QUALITY/CONDITION (SEE SWPPP FOR BMP LOCATIONS) CONSTRUCTION ENTRANCE SITE RESTRICTED ACCESS Paved/Gravel, quarry spalls Locked chain link fences WHEEL WASH SEDIMENT TRACK OUT N/A City construction in right of way, not under this permit ROADWAY SURFACE CATCH BASIN Crushed rock, quarry spalls Silt socks installed in catch basins LIMITS BUFFER AREA STABILIZATION Marked by chain link fences N/A SILT FENCING CONCRETE WORK (Sidewalks, curbing, foundation) Installed along the N, W perimeters None observed COVER MEARSURES OVERALL STRAW Good, hydroseed/straw/plastic sheeting Covering exposed soils and slopes PLASTIC SHEETING HYDROSEED Onsite, covering stockpiles and exposed soils Hydroseed covering exposed soils on N and W end of site CONVEYENCE CHANNEL CHECK DAMS Temporary channels on north and south end of site directing water to catch basin Temporary check dams and swale on NE end of site STOCKPILE COVER PIPE SLOPE DRAINS Active or covered N/A LEVEL SPREADER LANDSCAPE/MULCH N/A N/A SEDIMENT POND TRAP SEDIMENT POND INLET/OUTLET Temporary sediment ponds on NE and W end of site N/A SEDIMENT POND SIDE SLOPES SURFACE WATER OBSERVATION (Creek, Wetland, or Lake) (Clear, Turbid, Sheen) Covered with hydroseed and quarry spalls little surface water WATER QUALITY SAMPLE TURBIDITY (NTU) pH OVERALL No N/A N/A BMP's adequate SAMPLE LOCATION AREAS OF CONCERN Temporary swale in NE corner of site none CORRECTIVE ACTIONS none PAST CORRECTIVE ACTIONS None Is this site in compliance with the terms and conditions of the SWPP and CSWGP discharge Permit? Yes www.aesgeo.com TESC REPORT DATE CSWGP PROJECT NO. TESC REPORT NO. 2/23/2023 WAR310781 20180398E003 043 Sample Location Approximate Flow Turbidity NTU/Transparency pH Compliance Temporary NE swale ADDITIONAL COMMENTS: No discharge was observed at the time of visit. The contractor is using temporary swales and a Baker tank to impound onsite water and received a permit to discharge construction storm water to King County sanitary sewer. A water sample was taken from the NE swale; the sample had a turbidity of 34 NTU. AESI reminded the contractor the cover stockpiles prior to the oncoming rain this weekend. AESI will return next week.