HomeMy WebLinkAboutEstimate (30%)30% Opinion (Estimate) of Probable Cost
Project Name
Duvall Avenue NE Improvements, NE 10th Street to Sunset Boulevard
Location
Renton, WA
Owner
City of Renton
Estimated By:
Date:
ITEM
NO.
1
2
3
4
5
6
7
8
9
10
11
12
13
SPEC
SECTION
1-04
1-05
1-05
1-07
1-07
1-07
1-10
1-10
1-10
1-10
1-10
1-10
1-10
SECTION
7-05
SECTION
M. Kendall
12/29/16
DESCRIPTION
Common Div 1 Bid Items
Minor Changes
Roadway Surveying
Record Drawings
Property Restoration
SPCC Plan
Utility Potholing
Flaggers and Spotters
Pedestrian Traffic Control
Uniformed Police Officer
Portable Changeable Message Sign
Construction Sign Class A
Traffic Control Supervisor
Other Temporary Traffic Control
DESCRIPTION
Storm Treatment
Storm Detention and Treatment (placeholder from grant estimate)
DESCRIPTION
ROW/Easements
5 ft Utility/slope/construction easement
DESCRIPTION
Segment Totals
Schedule A - 10th to Sunset Total
Schedule B - Missing sidewalk S of 10th
Schedule C - Missing sidewalk N of 4th
TOTAL OF ALL PROJECT SECTIONS
Common Div 1 Bid Items
Storm Detention and Treatment (placeholder)
5 ft Utility/slope/construction easement
Schedule A-C Totals
TOTAL
Project No.
214-1779-045
Checked By:
Date:
QTY
1
1
1
1
1
1
2000
1
20
800
100
1
1
Construction Cost
20% Contingency
TOTAL COST
QTY
1
Construction Cost
20% Contingency
TOTAL COST
QTY
1
Construction Cost
20% Contingency
TOTAL COST
QTY
1
1
1
TOTAL COST (+20% already included)
TOTAL COST
277800
0
0
2808648.9083
3086448.9083
C.Schott
UNIT
FA
LS
LS
LS
LS
EST
HR
LS
HR
HR
SF
LS
LS
UNIT
EST
UNIT
EST
UNIT
EA
EA
EA
Date
12/29/2016
UNIT PRICE
30000
10000
1000
15000
2500
5000
50
6000
100
20
40
25000
15000
UNIT PRICE
0
UNIT PRICE
0
UNIT PRICE
2623808.203
140838.1157
44002.5895
TOTAL COST
30000
10000
1000
15000
2500
5000
100000
6000
2000
16000
4000
25000
15000
231500
46300
277800
TOTAL COST
0
0
0
0
TOTAL COST
0
0
0
0
TOTAL COST
2623808.203
140838.1157
44002.5895
2808648.9083
sf
disturbed area, wsdot standard
sf
.17 acre
0.3
QTY
1
1
1
1
1
1
1
1
QTY
1
NOTES
*Price Included in SCH A, B, & C Estimates
30% Opinion (Estimate) of Probable Cost
Project Name
Duvall Avenue NE Improvements, NE 10th Street to Sunset Boulevard
Location
Renton, WA
Owner
City of Renton
Estimated By:
Date:
ITEM
NO.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
WSDOT
STD ITEM
1
35
49
110
108
100
120
50
310
431
7006
7017
5100
5767
5711
3602
3608
3151
3091
9605
3848
6414
6407
6579
6700
6707
6701
7059
7059
6882
6884
7088
7102
7045
7058
7058
6904
6890
6833
6866
6857
6859
6828
208
187
7164
ITEM
TYPE
SI
SI, GSP
SP
GSP
SP
SP
GSP
SI, GSP
SI
SI
SI
SI
SI
SI, GSP
SI
SI
SI
SI
SI
SI
SP
SI
SI
SP
SP
SP
SI
SI
SI
SI
SI
SI
SI
SI
SI
SI
SI
SI
SP
SI
SI
SI
SI
SI
SI
SP
SI
GSP
SPEC
SECTION
1-09
2-01
2-02
2-02
2-02
2-02
2-02
2-02
2-02
2-02
2-03
2-03
2-09
2-09
4-04
4-04
4-04
5-04
5-04
5-04
7-04
7-04
7-04
7-05
7-05
7-06
7-08
7-14
8-01
8-01
8-01
8-02
8-02
8-02
8-04
8-04
8-04
8-06
8-06
8-09
8-09
8-12
8-12
8-12
8-13
8-14
8-14
8-14
8-14
8-20
8-20
8-21
8-22
8-22
8-22
8-22
8-22
8-22
8-23
8-24
M. Kendall
12/29/16
DESCRIPTION
SCHEDULE A - 10TH TO SUNSET
Mobilization
Clearing and Grubbing
Removing Drainage Structure
Removing Storm Sewer Pipe/Culvert
Removing Cement Conc. Curb
Removing Cement Conc. Curb and Gutter
Removing Cement Conc. Sidewalk
Removing Asphalt Conc. Pavement
Removal of Structures and Obstructions
Chain Link Fence Repair
Roadway Excavation Incl. Haul
Gravel Borrow Incl. Haul
Structure Excavation Class B Incl. Haul
Gravel Backfill for Pipe Zone Bedding
Crushed Surfacing Top Course
Recycled Pavement
Infiltration Base Rock, Incl. Haul
HMA CL 1/2 In. PG 64-22
HMA CL 1/2 In. PG 64-22 - Driveway Repair
Planing Bituminous Pavement
Corrugated Polyethylene Storm Sewer Pipe 12 In. Diam.
Corrugated Polyethylene Storm Sewer Pipe 24 In. Diam.
Testing Storm Sewer Pipe
Catch Basin Type 1
Connection to Drainage Structure
4'x6' Biofiltration Vault
Filling Pipe With CDF
Resetting Existing Hydrant
Total of all TESC Related Items
Irrigation System Restoration
Seeding, Fertilizing, and Mulching
Topsoil Type A
Shrubs for Landscaping + Plant Establishment
Bark Mulch
Cement Conc. Traffic Curb and Gutter
Cement Concrete Pedestrian Curb
Cement Concrete Traffic Curb
Cement Conc. Driveway Entrance Type 1
Cement Conc. Driveway Entrance Type 3
Raised Pavement Marker Type 1
Raised Pavement Marker Type 2
Coated Chain Link Fence Type 4
Wood Fence
Double 14 Ft. Chain Link Gate
Monument Case and Cover
Pervious Cement Conc. Sidewalk
Cement Conc. Sidewalk Thickened Edge
Cement Conc. Curb Ramp Type Parallel
Cement Conc. Curb Ramp Type Single Direction
Illumination System, Complete
Electrical System, Complete
Permanent Signing
Plastic Traffic Arrow
Painted Bicycle Lane Symbol
Plastic Crosswalk Line
Plastic Stop Line
Painted Wide Lane Line
Removing Raised Pavement Marker
Removing Paint Line
Gravity Block Wall
Project No.
214-1779-045
Checked By:
Date:
QTY
1
1
7
143
175
845
488
380
1
1
4180
385
1270
960
1420
2780
220
5470
145
4630
1727
57
1784
10
3
3
972
2
1
1
6.51974288337925E-02
210
1
40
1870
80
175
143
28
28.5575
3.2425
225
380
1
2
1070
225
3
1
1
1
1
21
19
315
170
4760
3.5
700
460
Construction Cost
20% Contingency
TOTAL COST
C.Schott
UNIT
LS
LS
Each
LF
LF
LF
SY
SY
LS
LS
CY
TON
CY
CY
TON
TON
TON
TON
TON
SY
LF
LF
LF
EA
EA
EA
LF
EA
LS
LS
AC
CY
LS
CY
LF
LF
LF
SY
SY
HUND
HUND
LF
LF
EA
EA
SY
LF
EA
EA
LS
LS
LS
EA
EA
SF
LF
LF
HUND
LF
SF
Date
12/29/2016
UNIT PRICE
198773.3487
8000
250
8
5
5
10
7.5
8000
9000
35
20
15
35
25
35
30
95
110
4
55
110
5
1900
500
20000
15
1500
149000
0
5000
40
36000
45
20
25
30
40
40
200
400
25
40
1000
500
60
50
2000
2000
336900
100000
3000
65
50
15
15
2
150
0.5
40
TOTAL COST
198773.3487
8000
1750
1144
875
4225
4880
2850
8000
9000
146300
7700
19050
33600
35500
97300
6600
519650
15950
18520
94985
6270
8920
19000
1500
60000
14580
3000
149000
0
325.9871
8400
36000
1800
37400
2000
5250
5720
1120
5711.5
1297
5625
15200
1000
1000
64200
11250
6000
2000
336900
100000
3000
1365
950
4725
2550
9520
525
350
18400
2186506.8359
437301.3672
2623808.203
4000
sf
47017
195 CY
600 CY
0.1
138
$100 day
10480
new pavement
36537
6"
0.3
QTY
1
3900
1
635
1620
30
1
400
1
21
21
1
NOTES
10% of construction cost
SP Note 8
SP Note 10, includes removed culvert and pipe
SP Note 11
SP Note 11
west side 12th-Sunset sidewalk, one ramp
five driveways
See removal tab
Remove top rail of fence, repair damaged fence and posts in existing sidewalk
[10" under existing HMA for new roadway section (3021 CY) + DE cut/fill estimate (861 cy) - c&g (40 cy) - sidewalk (42 cy)] x 110%
DE cut/fill estimate x 110%
storm line (3.5' wide x 5' deep), CBs (5' x 5' x 7' deep), for wall (2' wide, 1' deep)
2' deep x 2' wide over pipe zone bedding for storm
2" over recycled pavement (1120 ton), 9" under curb and gutter (145 ton), 6" under driveways (150 ton)
5" deep average under full depth areas, includes pulverization
4" under pervious sidewalk
2" overlay depth per City meeting notes (42410 sf), 8" full depth per geotech (97364 sf)
6 DW entrances, assumes 8" full depth (2863 sf)
2" depth per City meeting notes
replace existing at new flow line, includes bedding
SP Note 4
5.0% of construction cost based on previous projects
assume 2' width behind sidewalk/wall, 6" deep
Restoration and plantings at back of new sidewalk
assume similar to 3rd-4th
at new ramps
at driveway entrances
5 commercial entrances per std plan 104, area behind back of walk separate, 10" deep concrete
1 residential entrance per std plan 104.3, area behind back of walk separate, 10" deep concrete
lane line per std plan H002 (7 per 48'), approach line per std plan H002 (14 per 24'), twlt line per std plan H001 (22 per 48') and center line per std plan H001 (18 per 30')
lane line per std plan H002 (1 per 48'), approach line per std plan H002 (2 per 24'), twlt line per std plan H001 (2 per 48') and center line per std plan H001 (2 per 30')
On top of thickened edge/fill wall
At each intersection
4" 4000psi concrete per std plan 102, new 6' width on west side, omit driveways and ramps (9624 sf)
new roadway and ped light standards
relocate hawk pole, type 1 ped pole, ppb, signal cabinets, variable speed limit sign upgrade, school flashing beacon
relocate 5 independent sign posts, all others on illum/signal poles, new bike lane signs on both sides of Duvall
twlt arrow spacing per H001 (250'), 2 arrows per turn lane
symbol per H009.2
at 10th and 12th, per std plan 127
at 10th and 12th
bike lane lines
lane line per std plan H002 (8 per 48') and center line per std plan H001 (20 per 30'), S of 10th
S of 10th
81583.3333333333
3021.60493827161
861
38.8888888888889
43.2098765432099
3800.50617283951
4180.55679012346
385
30% Opinion (Estimate) of Probable Cost
Project Name
Duvall Avenue NE Improvements, NE 10th Street to Sunset Boulevard
Location
Renton, WA
Owner
City of Renton
Estimated By:
Date:
ITEM
NO.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
SPEC
SECTION
1-09
2-01
2-02
2-02
2-03
2-03
2-09
2-09
4-04
4-04
5-04
7-04
7-04
7-05
7-05
8-01
8-01
8-02
8-04
8-04
8-14
8-14
8-20
8-24
M. Kendall
12/29/16
DESCRIPTION
SCHEDULE B - SIDEWALK EXTENSION SOUTH OF 10TH
Mobilization
Clearing and Grubbing
Removing Asphalt Conc. Pavement
Removal of Structure and Obstruction
Roadway Excavation Incl. Haul
Gravel Borrow Incl. Haul
Structure Excavation Class B Incl. Haul
Gravel Backfill for Pipe Zone Bedding
Crushed Surfacing Top Course
Infiltration Base Rock, Incl. Haul
HMA CL 1/2 In. PG 64-22
Corrugated Polyethylene Storm Sewer Pipe 8 In. Diam.
Testing Storm Sewer Pipe
Catch Basin Type 1
Connection to Drainage Structure
Total of all TESC Related Items
Seeding, Fertilizing, and Mulching
Topsoil Type A
Cement Conc. Traffic Curb and Gutter
Cement Concrete Pedestrian Curb
Pervious Cement Conc. Sidewalk
Cement Conc. Curb Ramp Type Parallel
Illumination System, Complete
Gravity Block Wall
Project No.
214-1779-045
Checked By:
Date:
QTY
1
1
70
1
67
20
10
10
50
32
32
271
271
1
1
1
1.10192837465565E-02
3
310
20
152
1
1
255
Construction Cost
20% Contingency
TOTAL COST
C.Schott
UNIT
LS
LS
SY
LS
CY
TON
CY
CY
TON
TON
TON
LF
LF
EA
EA
LS
AC
CY
LF
LF
SY
EA
LS
SF
Date
12/29/2016
UNIT PRICE
11000
4000
7.5
2000
35
20
15
35
25
30
95
45
5
1900
500
8000
5000
40
20
25
60
2000
39200
40
TOTAL COST
11000
4000
525
2000
2345
400
150
350
1250
960
3040
12195
1355
1900
500
8000
55.0964
120
6200
500
9120
2000
39200
10200
117365.0964
23473.0193
140838.1157
sf
600 CY
0.1
$100 day
new pavement
36537
0.3
QTY
1
1620
30
400
1
467
21
1
NOTES
10% of construction cost
appx 10 ft width from back of ex asphalt to ROW line, 5 trees
2' along new curb line
sawcutting
See DE surfaces
See DE surfaces
storm line (3.5' wide x 5' deep), CBs (5' x 5' x 7' deep), for wall (2' wide, 1' deep)
2' deep x 2' wide over pipe zone bedding for storm
7" under full depth per geotech (620 sf), 9" under curb and gutter (465 sf)
4" under pervious sidewalk
8" full depth per geotech
5.0% of construction cost based on previous projects
Based on cut/fill lines behind back of walk
Based on cut/fill lines behind back of walk
west side
at back of new ramp
4" 4000psi concrete per std plan 102, new 5' width on west side, omit ramps (1364 sf)
4 light standards, junction boxes, conduit, new foundations
30% Opinion (Estimate) of Probable Cost
Project Name
Duvall Avenue NE Improvements, NE 10th Street to Sunset Boulevard
Location
Renton, WA
Owner
City of Renton
Estimated By:
Date:
ITEM
NO.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
SPEC
SECTION
1-09
2-01
2-02
2-02
2-02
2-02
2-02
2-03
2-03
2-09
2-09
4-04
4-04
5-04
5-04
7-04
7-04
7-05
7-05
8-01
8-01
8-02
8-04
8-06
8-14
8-21
M. Kendall
12/12/16
DESCRIPTION
SCHEDULE C - SIDEWALK EXTENSION NORTH OF 4TH
Mobilization
Clearing and Grubbing
Removing Storm Sewer Pipe/Culvert
Removing Cement Conc. Curb and Gutter
Removing Cement Conc. Sidewalk
Removing Asphalt Conc. Pavement
Removal of Structure and Obstruction
Roadway Excavation Incl. Haul
Gravel Borrow Incl. Haul
Structure Excavation Class B Incl. Haul
Gravel Backfill for Pipe Zone Bedding
Crushed Surfacing Base Course
Infiltration Base Rock, Incl. Haul
HMA CL 1/2 In. PG 64-22
HMA CL 1/2 In. PG 64-22 - Driveway Repair
Corrugated Polyethylene Storm Sewer Pipe 12 In. Diam.
Testing Storm Sewer Pipe
Catch Basin Type 1
Connection to Drainage Structure
Total of all TESC Related Items
Seeding, Fertilizing, and Mulching
Topsoil Type A
Cement Conc. Traffic Curb and Gutter
Cement Conc. Driveway Entrance Type 1
Pervious Cement Conc. Sidewalk
Permanent Signing
Project No.
214-1779-045
Checked By:
Date:
QTY
1
1
35
10
2
170
1
25
80
30
30
42
13
14
30
22
22
1
1
1
2.04315886134068E-02
6
139
24
102.777777777778
1
Construction Cost
20% Contingency
TOTAL COST
C.Schott
UNIT
LS
LS
LF
LF
SY
SY
LS
CY
TON
CY
CY
TON
TON
TON
TON
LF
LF
EA
EA
LS
AC
CY
LF
SY
SY
LS
Date
12/29/2016
UNIT PRICE
3000
2000
8
5
10
7.5
2000
35
20
15
35
25
30
95
110
55
5
1900
500
3000
5000
45
20
40
60
1000
TOTAL COST
3000
2000
280
50
20
1275
2000
875
1600
450
1050
1050
390
1330
3300
1210
110
1900
500
3000
102.1579
270
2780
960
6166.6667
1000
36668.8246
7333.7649
44002.5895
sf
600 CY
0.1
$100 day
new pavement
36537
0.3
QTY
1
1620
30
400
1
467
21
NOTES
sawcutting
See DE surfaces
See DE surfaces
storm line (24" wide x 4' deep), CBs (5' x 4' x 6' deep), for wall (2' wide, 1' deep)
2' deep x 2' wide over pipe zone bedding for storm
7" under full depth per geotech (11 TON), 9" under curb and gutter (11 TON), 6" under driveways (20 TON)
4" under pervious sidewalk
8" full depth per geotech (278 sf)
assumes 8" full depth, 574 sf
5.0% of construction cost based on previous projects
Based on cut/fill lines behind back of walk
Based on cut/fill lines behind back of walk
1 commercial entrances per std plan 104, area behind back of walk separate, 10" deep concrete (213 sf)
4" 4000psi concrete per std plan 102, new 5' width on west side, omit driveway (550 sf)
10th to Sunset Illumination
Item
Foundation/pole/luminaire/arm
Junction Boxes
Wire
Conduit
Service Cabinet
Remove existing standards
Total
S of 10th
Item
Foundation/pole/luminaire/arm
Junction Boxes
Wire
Conduit
Service Cabinet
Total
Unit
EA
EA
LF
LF
EA
EA
Unit
EA
EA
LF
LF
EA
Quantity
30
31
2150
6450
1
3
Quantity
4
4
900
300
0
Unit Cost
8000
600
2
10
8000
500
Unit Cost
8000
600
2
10
8000
Total Cost
240000
18600
4300
64500
8000
1500
336900
Total Cost
32000
2400
1800
3000
0
39200
10th to Sunset
Removal of Structure and Obstruction
Item
Remove Tree
Remove block wall
Remove board fence
Remove gate and posts
Remove wood posts
Sawcutting
Quantity
5
121
212
1
2
Unit
EA
LF
LF
EA
EA
Notes
In front of church, 1-3' tall
6' board and 4' wood rail
S of 10th
Item
Catch Basin Type 1
Connection to Drainage Structure
Biofiltration Vault 4x6
Corrugated Polyethylene Storm Sewer Pipe 24 In. Diam.
Corrugated Polyethylene Storm Sewer Pipe 8 In. Diam.
Corrugated Polyethylene Storm Sewer Pipe 12 In. Diam.
Treatment not included
Biofiltration Vault 4x6
Walls
ROW Needed?
10th to 12th
Item
Catch Basin Type 1
Connection to Drainage Structure
Biofiltration Vault 4x6
Corrugated Polyethylene Storm Sewer Pipe 24 In. Diam.
Corrugated Polyethylene Storm Sewer Pipe 12 In. Diam.
Treatment not included
Biofiltration Vault 4x6
Walls
ROW Needed?
12th to Sunset
Item
Catch Basin Type 1
Connection to Drainage Structure
Biofiltration Vault 4x6
Corrugated Polyethylene Storm Sewer Pipe 24 In. Diam.
Corrugated Polyethylene Storm Sewer Pipe 12 In. Diam.
Treatment not included
4'x6' TBBU
Walls
ROW Needed?
N of 4th
Item
Catch Basin Type 1
Connection to Drainage Structure
Biofiltration Vault 4x6
Corrugated Polyethylene Storm Sewer Pipe 24 In. Diam.
Corrugated Polyethylene Storm Sewer Pipe 12 In. Diam.
Treatment not included
Biofiltration Vault 4x6
Walls
ROW Needed?
Number
1
1
0
0
271
0
2
80
NO
Number
6
0
3
0
1097
1
30
NO
Number
4
3
0
57
630
4
120
YES
Number
1
1
0
0
22
0
0
NO
Unit
EA
EA
EA
LF
LF
EA
SF
Unit
EA
EA
EA
LF
LF
EA
SF
Unit
EA
EA
EA
LF
LF
EA
SF
Unit
EA
EA
EA
LF
LF
EA
SF
Price
1900
500
19890
110
55
19890
Price
1900
500
19890
110
55
19890
Price
1900
500
19890
110
55
19890
Price
1900
500
19890
55
19890
Total
1900
500
0
0
0
39780
0
Total
11400
0
59670
0
60335
19890
0
Total
7600
1500
0
6270
34650
79560
0
Total
1900
500
0
0
1210
0
0
Item
Structure Excavation Class B Incl. Haul
Gravel Backfill for Pipe Zone Bedding
Item
Structure Excavation Class B Incl. Haul
Gravel Backfill for Pipe Zone Bedding
Item
Structure Excavation Class B Incl. Haul
Gravel Backfill for Pipe Zone Bedding
Item
Structure Excavation Class B Incl. Haul
Gravel Backfill for Pipe Zone Bedding
12" SD (CY)
0
0
Total
7.5
12" SD (CY)
1097
720
Total
585
12" SD (CY)
630
410
Total
367.5
12" SD (CY)
22
20
Total
22.5
CBType1 (CY)
1
10
Unit
CY
CBType1 (CY)
6
40
Unit
CY
CBType1 (CY)
4
30
Unit
CY
CBType1 (CY)
1
10
Unit
CY
Filterra (CY)
0
0
Filterra (CY)
3
20
Filterra (CY)
0
0
Filterra (CY)
0
0
24" SD (CY)
0
0
24" SD (CY)
0
0
24" SD (CY)
57
50
24" SD (CY)
0
0
Total
10
Total
780
Total
490
Total
30
Unit
CY
Unit
CY
Unit
CY
Unit
CY
Price
15
Price
15
Price
15
Price
15
Total
150
Total
11700
Total
7350
Total
450
S of 10th
Item
Seeding, Fertilizing, and Mulching
Topsoil Type A
Landscaping, LS
Bark Mulch
10th to 12th
Item
Seeding, Fertilizing, and Mulching
Topsoil Type A
Landscaping, LS
Bark Mulch
12th to Sunset
Item
Seeding, Fertilizing, and Mulching
Topsoil Type A
Landscaping, LS
Bark Mulch
N of 4th
Item
Seeding, Fertilizing, and Mulching
Topsoil Type A
Landscaping, LS
Bark Mulch
*quantities taken from LS sheets, 12-12-16
Number
1.10192837465565E-02
2.96296296296296
0
0
*quantities taken from LS sheets, 12-12-16
Number
6.51974288337925E-02
141.271604938272
3341
20.6234567901235
*quantities taken from LS sheets, 12-12-16
Number
0
65.5555555555556
1770
10.9259259259259
*quantities taken from LS sheets, 12-12-16
Number
2.04315886134068E-02
5.49382716049383
0
0
Unit
AC
CY
SF
CY
Unit
AC
CY
SF
CY
Unit
AC
CY
SF
CY
Unit
AC
CY
SF
CY
Price
5000
40
5
45
Price
5000
40
5
45
Price
5000
40
5
45
Price
5000
40
5
45
Total
55.0964
118.5185
0
0
Total
325.9871
5650.8642
16705
928.0556
Total
0
2622.2222
8850
491.6667
Total
102.1579
219.7531
0
0
3.62962962962963
158106.666666667
$/SF
$/ACRE
*Poulsbo Central Business District Shrub Price mix