HomeMy WebLinkAbout6-20-23 Central Maintenace FacilityConstruction Stormwater Site Inspection Form Page 1 Project Name King County Parks Central Maintenance Facility Permit # WAR310106 Inspection Date 6/20/23 Time 2:00 PM Name of Certified Erosion Sediment Control Lead (CESCL) or qualified inspector if less than one acre Print Name: Alexis Lamrouex Approximate rainfall amount since the last inspection (in inches): 0.53 Approximate rainfall amount in the last 24 hours (in inches): 0.15 Current Weather Clear Cloudy x Mist Rain Wind Fog A. Type of inspection: Weekly x Post Storm Event Other B. Phase of Active Construction (check all that apply): Pre Construction/installation of erosion/sediment controls Clearing/Demo/Grading Infrastructure/storm/roads Concrete pours Vertical Construction/buildings x Utilities Offsite improvements Site temporary stabilized Final stabilization C. Questions: 1. Were all areas of construction and discharge points inspected? Yes x No 2. Did you observe the presence of suspended sediment, turbidity, discoloration, or oil sheen Yes No x 3. Was a water quality sample taken during inspection? (refer to permit conditions S4 & S5) Yes No x 4. Was there a turbid discharge 250 NTU or greater, or Transparency 6 cm or less?* Yes No x 5. If yes to #4 was it reported to Ecology? Yes No x 6. Is pH sampling required? pH range required is 6.5 to 8.5. Yes No x If answering yes to a discharge, describe the event. Include when, where, and why it happened; what action was taken, and when. *If answering yes to # 4 record NTU/Transparency with continual sampling daily until turbidity is 25 NTU or less/ transparency is 33 cm or greater. Sampling Results: PH Turbidity Date: 6/20/23 Construction Stormwater Site Inspection Form Page 2 D. Check the observed status of all items. Provide “Action Required “details and dates. Element # Inspection BMPs Inspected BMP needs maintenance BMP failed Action required (describe in section F) yes no n/a 1 Clearing Limits Before beginning land disturbing activities are all clearing limits, natural resource areas (streams, wetlands, buffers, trees) protected with barriers or similar BMPs? (high visibility recommended) x 2 Construction Access Construction access is stabilized with quarry spalls or equivalent BMP to prevent sediment from being tracked onto roads? x Sediment tracked onto the road way was cleaned thoroughly at the end of the day or more frequent as necessary x 3 Control Flow Rates Are flow control measures installed to control stormwater volumes and velocity during construction and do they protect downstream properties and waterways from erosion? x If permanent infiltration ponds are used for flow control during construction, are they protected from siltation? x 4 Sediment Controls All perimeter sediment controls (e.g. silt fence, wattles, compost socks, berms, etc.) installed, and maintained in accordance with the Stormwater Pollution Prevention Plan (SWPPP). x Sediment control BMPs (sediment ponds, traps, filters etc.) have been constructed and functional as the first step of grading. x Stormwater runoff from disturbed areas is directed to sediment removal BMP. x 5 Stabilize Soils Have exposed un-worked soils been stabilized with effective BMP x Construction Stormwater Site Inspection Form Page 3 to prevent erosion and sediment deposition? Construction Stormwater Site Inspection Form Page 4 Element # Inspection BMPs Inspected BMP needs maintenance BMP failed Action required (describe in section F) yes no n/a 5 Stabilize Soils Cont. Are stockpiles stabilized from erosion, protected with sediment trapping measures and located away from drain inlet, waterways, and drainage channels? x Have soils been stabilized at the end of the shift, before a holiday or weekend if needed based on the weather forecast? x 6 Protect Slopes Has stormwater and ground water been diverted away from slopes and disturbed areas with interceptor dikes, pipes and or swales? x Is off-site storm water managed separately from stormwater generated on the site? x Is excavated material placed on uphill side of trenches consistent with safety and space considerations? x Have check dams been placed at regular intervals within constructed channels that are cut down a slope? x 7 Drain Inlets Storm drain inlets made operable during construction are protected. x Are existing storm drains within the influence of the project protected? x 8 Stabilize Channel and Outlets Have all on-site conveyance channels been designed, constructed and stabilized to prevent erosion from expected peak flows? x Is stabilization, including armoring material, adequate to prevent erosion of outlets, adjacent stream banks, slopes and downstream conveyance systems? x 9 Control Pollutants Are waste materials and demolition debris handled and disposed of to prevent contamination of stormwater? x Has cover been provided for all chemicals, liquid products, petroleum products, and other material? x Has secondary containment been provided capable of containing 110% of the volume? x Were contaminated surfaces cleaned immediately after a spill incident? x Construction Stormwater Site Inspection Form Page 5 Were BMPs used to prevent contamination of stormwater by a pH modifying sources? x Element # Inspection BMPs Inspected BMP needs maintenance BMP failed Action required (describe in section F) yes no n/a 9 Cont. Wheel wash wastewater is handled and disposed of properly. x 10 Control Dewatering Concrete washout in designated areas. No washout or excess concrete on the ground. x Dewatering has been done to an approved source and in compliance with the SWPPP. x Were there any clean non turbid dewatering discharges? x 11 Maintain BMP Are all temporary and permanent erosion and sediment control BMPs maintained to perform as intended? x 12 Manage the Project Has the project been phased to the maximum degree practicable? x Has regular inspection, monitoring and maintenance been performed as required by the permit? x Has the SWPPP been updated, implemented and records maintained? x 13 Protect LID Is all Bioretention and Rain Garden Facilities protected from sedimentation with appropriate BMPs? x Is the Bioretention and Rain Garden protected against over compaction of construction equipment and foot traffic to retain its infiltration capabilities? x Permeable pavements are clean and free of sediment and sediment laden- water runoff. Muddy construction equipment has not been on the base material or pavement. x Have soiled permeable pavements been cleaned of sediments and pass infiltration test as required by stormwater manual methodology? x Heavy equipment has been kept off existing soils under LID facilities to retain infiltration rate. x Construction Stormwater Site Inspection Form Page 6 E. Check all areas that have been inspected. All in place BMPs x All disturbed soils x All concrete wash out area x All material storage areas x All discharge locations x All equipment storage areas x All construction entrances/exits x F. Elements checked “Action Required” (section D) describe corrective action to be taken. List the element number; be specific on location and work needed. Document, initial, and date when the corrective action has been completed and inspected. Element # Description and Location Action Required Completion Date Initials Eco pan West corner next to concrete waste bin Empty out G. Corrective action taking place. Description of action Completion Date Initials Sign the following certification: “I certify that this report is true, accurate, and complete, to the best of my knowledge and belief” Inspected by: (print) Alexis Lamrouex (Signature) Alexis Lamrouex Date: 6/20/23 Title/Qualification of Inspector: CESCL