HomeMy WebLinkAboutMisc_Week_Lookahead_ScheduleJob#LEGEND
Contract #BEGINNING:February 26, 2023 X Day ?TenativeProject Name:Rainier Ave S - Phase 4 ENDING:April 1, 2023 N Night M Material
sun mon tue wed thu fri sat sun mon tue wed thu fri sat sun mon tue wed thu fri sat sun mon tue wed thu fri sat sun mon tue wed thu fri sat sun mon tue wed thu fri sat
2/19 2/20 2/21 2/22 2/23 2/24 2/25 2/26 2/27 2/28 3/1 3/2 3/3 3/4 3/5 3/6 3/7 3/8 3/9 3/10 3/11 3/12 3/13 3/14 3/15 3/16 3/17 3/18 3/19 3/20 3/21 3/22 3/23 3/24 3/25 3/26 3/27 3/28 3/29 3/30 3/31 4/1
1 Renton Preconstruction Meeting X2RentonReceive Notice to Proceed X3RentonUtility Preconstruction Meeting ?45 Mobilization6Pivetta Setup/Install Temporary Field Offices Laydown X X X X X X X X X X7PivettaSetup School Yard Laydown Area School Laydown
8 PSE PSE Energize Power Laydown ????
9 Pivetta Install Project Signs Project M X
10 North Peak Survey Existing Topography (Flyover)Project X X
11 Pivetta Setup GPS Project X
12 North Peak Stake Control Points Project X X
13 Utilities Utility Locates Project X X X X X
14 Pivetta Perform Existing Condition Survey Project X X X X X X X X X X
15 Pivetta TBD - Lanes Utility Potholing - Day Project X X X X X X X X X X X X X X X16Pivetta TBD - Lanes Utility Potholing - Night Project N N N N N N N N1718Pivetta Setup Business Signs Project M Setup As Needed19Pivetta TBD - Lanes Install Catch Basin Filters Project X20Pivetta Install Silt Fence/Tree Protection Stage 1 X2122Stage 1 Channelization23EvergreenTCP #1 Sawcut Median Rainier/3rd Ave N24PivettaTCP #1 Remove Median (STA 14+00 to STA 15+50) & Temp HMA Rainier/3rd Ave N N N25PivettaIn Work Layout for Temp Striping/Channelization Project N N2627Golden Gate Pull wire for temp camera signal installation Project X X X X X28Golden Gate Stage Portable Signal System Rainier/S 2nd St X29SPMIn Work Install Temp Striping for Stage 1 Rainier/S 2nd St N N N30Golden Gate In Work Adjust Signal Cameras and Install Temp Cameras 3rs st/2nd st/Airport N N N31Golden Gate Install Portable Signal System Rainier/S 2nd St N32PivettaInstall Barrier at Signal System Rainier/S 2nd St N
33 Stage 1 Channelization Complete X X
34
35 Removals
36 Pivetta Fence Removal Rainier/3rd Ave Fill In Work - As Time Allows
37 Pivetta/COR Tag Trees for Removal Project X X X
38 Pacific Tree In Work Remove Trees Project N N N N
39 Pivetta In Work Remove East Sidewalk not ADA Compliant (Patch with HMA)East 21+00 to 28+00 N N N
404142 Joint Utility Trench43North Peak Stake Utility Structures Project X X X44PivettaProvide Request for Structures and Conduit Project X4546UtilitiesReceive Utility Structures 2nd St X-ing X X47EvergreenTCP 4 & 5, TBD Sawcut for JUT 2nd St X-ing N N48PivettaInstall JUT Vaults for 2nd St Crossing 2nd St X-ing N N N N49Golden Gate TCP 4 & 5, TBD Install JUT Conduit 2nd St X-ing N N5051UtilitiesReceive Utility Structures 15+25 to 18+40 X X52PivettaInstall JUT Utility Structures 15+25 to 18+40 X X53Golden Gate Install JUT Conduit 15+25 to 18+405455Sewer Line56InsituformClean and Video Existing Sewer Project57
58
Submitted By Description of Material
59
60
61
62
63
64
Submitted By Description of Submittal6566
Past Week Look Ahead Week 1 Look Ahead Week 2 Look Ahead Week 3 Look Ahead Week 4
5 WEEK LOOKAHEAD SCHEDULE2022-148
CAG-22-163
Date Submitted
Date Submitted
Submittals/material Procurement Needed
RFI's Pending
Responsibility TC REQ.TESTING / INSP. ActivityLine No.Location
Current Week
2.27.23 5-week Look-ahead
2/28/2023 1 of 1