SUMMARY OF PROPOSED CHANGE:
ITEM Unit Qty. Unit Price Total Price
A62.EA 2.00 $1,300.00 $2,600.00
A63.EA 20.00 $850.00 $17,000.00
Sub Total (Schedule A - Sewer)
Sales Tax (10.1%)
APPROVAL SIGNATURES:
Approved By: Date:
Jesse Newman, Project Manager
Approved By: Date:
Anne Rasmussen, Laser Underground and Earthworks, inc.
Approved By: Date:
Ronald Straka, Utility Systems Director
Approved By: Date:
Martin Pastucha, PW Administrator
Approved By: Date:
Cheryl Beyer, Renton City Attorney
ESTIMATED NET CHANGE
THIS ORDER
$21,579.60
ORIGINAL CONTRACT AMOUNT CURRENT CONTRACT AMOUNT
$2,052,252.99 $2,052,252.99
NEW ITEM:
ESTIMATED CONTRACT TOTAL AFTER CHANGE
$19,600.00
$1,979.60
$21,579.60
Removal of tree clusters, where plans call out for individual
trees to be removed. Cost includes extra labor and
equipment to remove each tree cluster.
CITY OF RENTON
Additional Quantities Under This Change Order
Public Works Department
CONTRACT CHANGE ORDER AGREEMENT
CONTRACT:
CONTRACTOR:
Thunder Hills Sewer Interceptor Rehabilitation CAG-23-048
Laser Underground and Earthworks, inc.
Provide all labor, equipment, subcontracting, bonding, insurance for the complete work required for
the extra work as outlined below:
$2,073,832.59
Total (Schedule A - Sewer)
NEW ITEM:
Removal of additional trees found within clearing limits.
H:\File Sys\WWP - WasteWater\WWP-27-03921 Thunder Hills Sewer Interceptor Rehabilitation\110 - Construction\110.12 - Change Orders\CO #1 - Extra Tree Removal\Backup\CAG-23-048_CO#1 - THSIR 1 of 1