CITY OF RENTON
CONTRACT CHANGE ORDER AGREEMENT NO. _ 1
Project Title: SW Grady Way Overlay Project
CAG-14-151/Fed Aid#STPUL-1 288(004)
Contractor Name and Address: Lakeside Industries,Inc.
Attn:Craig Nickel,Project Manager
18808 SE 256th Street
Covington,WA 98042
The Contractor is hereby directed to make the changes to the Contract as descriibed.herein. This document and all attachments are a
supplement to the contract. Allwork,materials and measurements for the type of construction involved shall be in accordance with
the contract documents of the above named project unless stated otherwise in this change order.
Summary of Proposed Changes:
After meetings with the designer,concrete subcontractor&electrical subcontractor it was determined the
ramps could not be constructed with the monolithic pour as indicated in the plans.This change drastically
increased the necessary time for survey and layout,along with the concrete installation. The curb and
gutter had to be installed first to establish the elevation control points fiat the pedestrian push button pole
bases. Once these were installed, then the ramps and sidewalk could be completed. This required
sequence of events needed 3 separate concrete pours at each ramp location. Lakeside is requesting
additional working days for each ramp at no cost.This request meets the criteria of section 1-08.8 part Sa;
"In Section 1-04.4 if a change increases the time to do any of the Work including unchanged Work.".
Section 1-04.4 part 4"Altering the way the Work is to be done."addresses this specific situation.
The Contract time is extended by 17 days.
Sales
Item Sch. Sec.No. Item Description Quantity Units Unit Price Total Price Tax
(+1-) ($) (+/-) (Y/N)
COI 1-08.5 Time Extension 1 $0.00 $0.00 N
- -. - -- 1----
_ Subtotal $0.00
Washington State Sales Tax(8.8%)on applicable items $0.00
TOTAL $0.00
Base Amount Taal niter.T
1. Total Cast this CIQ _ $000 10,00
2. total Cost Previous co $0000 ;t%0o
3. Original Coosa Amount $ 84733 50 y 3 . 847„338.50
4. Raved Contract Amount $ 841.338.50 $ 84733850`
This change order constitutes lull and complete compensation for all labor,equipment,materials,overhead,profit,any and all
indirect costs,and time adjustment to perform the above described changes. AIS other costs are non compensible.
Contractor: ctA; `� •{ ►` `a0i'S
Resident Engineer„ ,, nl% g rr$e10
PrO jWr M 1101? I �� / 2
p ens i /VI fruitier: 4l!' • , Debt
i f�
Pw /+d l' i u-i & rerrnr ✓. 6
FLAKESIDE iNDUSTRIESINC.
KENT DIVISION
November 11,2015
Ronnie Bennett
Senior Construction Manager
1019—39t1 Avenue SE,Suite i
Puyallup WA 98374
Re: SW Grady Way Overlay Project
Extension of Time
Lakeside Industries requests an extension of time for this project per WSDOT
specification 1-08.8. After meetings,with the designer,concrete subcontractor&
electrical subcontractor it was determined the ramps could not be constructed with the
monolithic pour as indicated in the plans. This change drastically increased the necessary
time for survey and layout,along with the concrete installation.
The curb and gutter had to be installed first to establish the elevation control points for
the pedestrian push button pole bases. Once these were installed,then the ramps and
sidewalk could be completed. This required sequence of events needed 3 separate
concrete pours at each ramp location.
Lakeside is requesting an additional 1.5 working days for each ramp;this totals an
additional 24 working days. This request meets the criteria of section 1-08.8 part 5a;"In
Section 1-04.4 if a change increases the time to do any of the Work including unchanged
Works'. Section 1-04.4 part 4"Altering the way the Work is to be done" addresses this
specific situation.
While this delay was originally discussed in mid June,when direction was given by the
City of Renton not requiring the monolithic pour;Lakeside is now submitting a formal
request for an extension of time.
Please contact me withany questions,
Sincerely,
Craig Nickel
Project Manager