Loading...
HomeMy WebLinkAboutCO 2 +trrw '%W CAG-13-003 , CO #2-14 CHANGE ORDER OWNER ARCHITECT CITY OF RENTON CONTRACTOR� II!T, Project Name Public Works Shops Bldg.D Remodel Project Address 3656 NE 2nd Renton,WA 98056 Date: 411012013 Change order No.: 2 Contractor Name: Northern Pacific Construction &Address 15310 SE 21 CDR Project No.: CAG-13-003 Bellevue,WA 98007 The Contract is hereby amended as follows: 1)Provide for 10 quick connect air outlets and associated piping. Add $2,998.05 TOTAL CONSTRUCTION COST IMPACT OF THIS CHANGE ORER Add $2,998.05 The change order shall Include all Contractor(s)labor,material,overhead,profit,and all direct and/or indirect costs allocated with the Change in Scope of Work. Excluding Bond Premiums. This Change Order is not valid unless signed by the Owner and Contractor The original Contract Sum was..................................................................................... $86,321.00 Net Change by previously authorized Change Order(s)was............................................. $2,381.65 The Contract Sum prior to this Change Order was........................................................... $88,702.66 The Contract Sum will be revised by this Change Order in the amount of............................. $2,998.05 The new Contract Sum Incorporating this Change Order will be........................................ $91,700.70 The Contract Time will be changed by .......................................................................... 5 days The Substantial Completion Date Including this Change Order is...................................... May 2,2013 NOTE:The above summary does not Include any changes in the Contract Sum or Contract Time which have been approved by Construction Change Directive or Field Directive forms. ARCHITECT CONTRACTOR OWNER Wagner Architects Northern Pacific Construction City of Renton 1916 Pike Place 15310 SE 21 Community Services Dept Seattle,WA 98101 Bellevue,WA 98007 1055 South Grady way Renton,Washington 98055 Date Date Date