CITY OF RENTON Page 1 of 1
Public Works Department
CONTRACT CHANGE ORDER AGREEMENT
CONTRACT: 2013 Street Patch and Overlay with Curb Ramps CAG-13-103
CONTRACTOR: Lakeside Industries
SUMMARY OF PROPOSED CHANGE:
Reason/Justification: The contract called for 3 loops to be installed on NE 10th St.. After the contract was awarded,it was noticed that the
home runs from the loops on Sunset Blvd NE were cut during the grinding of NE 10th St. Also after the contract was awarded,a thin King County
overlay on Renton Ave S has started to delaminate and is in need of a grind and overlay. Lakeside has agreed to use the contract bid items for
these extras but requested new bid items for additional Mobilization and Traffic Control.
Contract Change:Add 7 induction loops,and add grind and overlay to a portion of Renton Ave S,including additional Mobilization and Traffic
Control.
Add the followinp quantities to bid item plan quantities in the schedule of prices.
Item Approx Units Description Unit Price Amount
No. Quantity
22 7 EACH Induction Loops $750.00 $5,250.00
3 39 TON HMA Cl.1/2 IN.PG 64-22 For 2"overlay $80.00 $3,120.00
5 342 SQ YD. Removing Asphalt Concrete Pavement b Cold Planin $8.50 $2,907.00
Total $11,277.00
Add costs for additional work
Item Approx Units Description Unit Price Amount
No. Quanti
43 1 LS Additional Mobilization $7,000.00 $7,000.00
44 1 LS Additional Traffic Control $8,000.00 $8,000.00
Total Lump Sum items: $16,000.00
Additional cost for increases is other quantities in Contract Change above: $11,277.00
Total for this change order: $26,277.00
All work,materials and measurement to be in accordance with the provisions of the Standard Specifications
and Special Provisions for the type of construction involved.
ORIGINAL CONTRACT CURRENTCONTRACT ESTIMATE NET CHANGE ESTIMATED CONTRACT
AMOUNT AMOUNT THIS ORDER TOTAL AFTER CHANGE
$647,177.66 $647,177.66 $26,277.00 $673,454.66
Working Days:
Two(2)additional working days are granted for the increased work due to this change