HomeMy WebLinkAboutCO 2 CITY OF RENTON
Public Works Department
CONTRACT CHANGE ORDER AGREEMENT
CONTRACT: NE loth St. and Anacortes Ave NE Detention Pond Retrofit(CAG-13-143) C.O.# 2
CONTRACTOR: CCT Construction,Inc.
SUMMARY OF PROPOSED CHANGE:
New Item 24. This change authorizes the Contractor to dewater the pond into the sanitary sewer and dispose of
excavated material that had become saturated as a result of exceptionally heavy rainfall in late September, 2013. In
order to dewatering into the sanitary sewer,the contractor was required to setup and maintain traffic control,hoses
and pumps. Since the City has already paid the contractor for disposing of the dry excavated material per the unit
bid price for Bid Item No. 10,this change order covers the cost difference between the dry and wet disposal fee
charged by the disposal site. The cost breakdown for this item is listed below and is full compensation for all work
described above:
• Labor and equipment to setup and maintain traffic control required for dewatering to sanitary sewer.
• Labor, equipment to setup and maintain pumps and hoses used to pump from pond to sanitary sewer.
• Disposal Fee for saturated material.
• Equipment to load wet material for disposal.
A copy of the Contractor's cost summary sheet is attached.
Bid Item Description Ouantity Unit Unit Cost Cost
24 Costs to dewater pond into sanitary l Lump Sum $6,822.62 $6,822.62
sewer and disposal fee for saturated
material excavated from the pond.
Sales Tax $0.00
Total $6,822.62
ORIGINAL CONTRACT CURRENT CONTRACT ESTIMATED NET CHANGE ESTIMATED CONTRACT
AMOUNT AMOUNT THIS ORDER TOTAL AFTER CHANGE
$135,185.00 $137,564.77 $6,822.62 $144,387.39
SIGNATURES: /
Contractor:`— AA - Date: 12 ZZ
Project Engineer: Date: 1'2 13 LO
Approved By: Date:
(Utility Systems Director)
i