HomeMy WebLinkAboutCO 1CITY OF RENTON Public Works Department CONTRACT CHANGE ORDER AGREEMENT CONTRACT: NE 10th and Anacortes Ave NE Detention Pond Retrofit (CAG -13 -1433) C.O.# 1 CONTRACTOR: CCT Construction, Inc. SUMMARY OF PROPOSED CHANGE: New Item 23. This change authorizes the Contractor to load, haul and dispose of unanticipated contaminated organic material. Based on the soils report, the contract assumed the excavated material to be removed from the pond to be composed of glacial till. During preparation for excavation of the pond, an approximate 18" layer of dark, organic material with a strong odor was uncovered at the bottom of the pond when the pond was dewatered. The material was clearly of a different composition than the native material identified in the soils report. The contractor had the material tested and it was found to have high concentrations of fecal matter which required disposal at a certified disposal site. The cost breakdown for this item is listed below and is full compensation for all work described above: • Labor, equipment and materials for sampling and environmental testing of organic material. • Labor, equipment to dispose of 228 tons of contaminated organic material. • Labor and equipment to haul contaminated organic material. • Equipment to load contaminated material for disposal. A copy of the Contractor's cost summary sheet is attached. Bid Item Description Ouanti Unit Unit Cost Cost 23 Load, Haul and Dispose of Organic 1 Lump Sum $2,379.77 $2,379.77 Contaminated Material. Sales Tax $0.00 Total $2,379.77 ORIGINAL CONTRACT CURRENT CONTRACT ESTIMATED NET CHANGE ESTIMATED CONTRACT AMOUNT AMOUNT THIS ORDER TOTAL AFTER CHANGE $135,185.00 $135,185.00 $2,379.77 $137,564.77 SIGNATUR >~ c Contractor: Project Engi Approved B Date: (/ Date: Date: / 3 H:\File Sys \SWP - Surface Water Projects \SWP -27 - Surface Water Projects (CIP)\27 -3645 NE 10th - Anacortes RD Pond Retrofit \Construction\Pay Estimates \Change Orders \CHG -ORD1 Contaminated Soils.DOCWQtp