HomeMy WebLinkAboutCO 2 CITY OF RENTON Public Works Department CONTRACT CHANGE ORDER AGREEMENT CONTRACT: CAG 13-178 Misty Cove Lift Station Replacement C.O.# 2 CONTRACTOR: Gary Harper Construction, Inc. SUMMARY OF PROPOSED CHANGE: Provide all labor, equipment, subcontracting, bonding, insurance for the complete work required for the extra work as outlined below: ITEM Additional Quantities Under This Change Order Unit Quantity Unit Price Total Price 026. NEW ITEM: Additional time and materials to provide additional shoring and LS 1 $12,287.75 $12,287.75 Dewatering for Wetwell installation. 027. NEW ITEM:Additional time and materials to replace extruded curbs that were LS 1 $904.61 $904.61 not in the original contract. 028. NEW ITEM:Additional labor and equipment costs for painting soffits and facia of LS 1 $671.79 $671.79 control building. 029. NEW ITEM:Additional labor, equipment,and material costs to upgrade proposed LS 1 $896.00 $896.00 garbage enclosure swing-gates with a roller gate. 030. NEW ITEM:Additional labor,equipment, and material costs to pothole, locate LS 1 $4,756.79 $4,756.79 and replace the existing force main 031. DELETED ITEM: Credit for elimination of one electrical handhold box. LS 1 ($964.00) ($964.00) Sub Total $18,552.94 Sales Tax (9.5%) $1,762.53 Total $20,315.47 ORIGINAL CONTRACT CURRENT CONTRACT ESTIMATED NET CHANGE ESTIMATED CONTRACT TOTAL AMOUNT AMOUNT THIS ORDER AFTER CHANGE $820,877.70 $830,119.03 $20,315.47 $850,434.50 SIGNATURES: x7' Contractor: 11; / ,� , � � Date: 4P 7// Project Engineer: _f Date: 7 I / Approved By: Wde Date: . stem Director) H:FileSys\WWP-Wastewater\WWP-27-3627\CO-2 Misty Cove Lift Station Repl/JDH