HomeMy WebLinkAboutCO 2 CITY OF RENTON
Public Works Department
CONTRACT CHANGE ORDER AGREEMENT
CONTRACT: CAG 13-178 Misty Cove Lift Station Replacement C.O.# 2
CONTRACTOR: Gary Harper Construction, Inc.
SUMMARY OF PROPOSED CHANGE:
Provide all labor, equipment, subcontracting, bonding, insurance for the complete work required for the extra
work as outlined below:
ITEM Additional Quantities Under This Change Order Unit Quantity Unit Price Total Price
026. NEW ITEM: Additional time and materials to provide additional shoring and LS 1 $12,287.75 $12,287.75
Dewatering for Wetwell installation.
027. NEW ITEM:Additional time and materials to replace extruded curbs that were LS 1 $904.61 $904.61
not in the original contract.
028. NEW ITEM:Additional labor and equipment costs for painting soffits and facia of LS 1 $671.79 $671.79
control building.
029. NEW ITEM:Additional labor, equipment,and material costs to upgrade proposed LS 1 $896.00 $896.00
garbage enclosure swing-gates with a roller gate.
030. NEW ITEM:Additional labor,equipment, and material costs to pothole, locate LS 1 $4,756.79 $4,756.79
and replace the existing force main
031. DELETED ITEM: Credit for elimination of one electrical handhold box. LS 1 ($964.00) ($964.00)
Sub Total $18,552.94
Sales Tax (9.5%) $1,762.53
Total $20,315.47
ORIGINAL CONTRACT CURRENT CONTRACT ESTIMATED NET CHANGE ESTIMATED CONTRACT TOTAL
AMOUNT AMOUNT THIS ORDER AFTER CHANGE
$820,877.70 $830,119.03 $20,315.47 $850,434.50
SIGNATURES:
x7'
Contractor: 11; / ,�
, � � Date: 4P 7//
Project Engineer: _f Date: 7 I /
Approved By: Wde Date:
. stem Director)
H:FileSys\WWP-Wastewater\WWP-27-3627\CO-2 Misty Cove Lift Station Repl/JDH