CHANGE ORDER NO. 2 Page 1 of 2
AIRPORT: Renton Municipal Airport(RNT) DATE: September 18, 2014
LOCATION: Renton,WA CITY PROJECT NO.: CAG 13-212
CONTRACTOR:3 Kings Environmental, Inc.
You are requested to perform the following described work upon receipt of an approved copy of this document
or as directed by the Owner:
ITEM SPEC UNIT
NO. NO. DESCRIPTION UNIT PRICE OTY. AMOUNT
COP#3 - Additional Perimeter Fencing LS $2,078.60 1 $2,078.60
Subtotal $2,078.60
Sales Tax (9.5%) $ 197.47
Original Contract Amount(with 9.5%Sales Tax) $277,490.90
Total This Change Order(with 9.5% Sales Tax) $2,276.07
Total Previous Change Orders $ 11,932.76
REVISED CONTRACT TOTAL $291,699.73
No additional working days will be allowed fo pletion of work associated with this change order. An
approved copy of this document will serve as th a to proceed.This document shall become an amendment
to the contract and all provisions of the ont t i apply.
Recommended By: gh Y
Engineer–WHPacific, Inc. Date
Approved By: t--� 4
Owner Cit of Renton D td e � —
Accepted By:
C n ra or–3 Kings Environmental ate
CMsers WHolden.WHPACIFIC'Oesklop`Renlon 8201Change Order No 24hange Order No 2 docs
**.►"
Page 2 of 2
CITY PROJECT NO.: CAG 13-212 CHANGE ORDER NO. 2
AIRPORT: Renton Municipal Airport (RNT) LOCATION: Renton, WA
JUSTIFICATION FOR CHANGE
1. Brief description of proposed contract changes and locations.
COP#3: Additional Perimeter Fencing
This change will modify the overall layout of the final airport perimeter fence around the removed 820
Building site.
2. Reason for the changes.
The revised layout of the perimeter fence will provide access to the existing 800 Building PSE gas meter
and pedestrian door, and better suit the needs of the airport.
3. Justification for unit prices or total cost.
The Contractor submitted a change order proposal with a lump sum price to complete the work. This
cost was reviewed by the project team and found to be acceptable for the work required. The quantity
of additional perimeter fence beyond plan quantity was measured in the field and verified. The
proposed price was compared with at least two contractors, and is in line with market value for the type
of fence and quantity installed.
C:\Users\WHolden.WHPACIFIC\Oesklop\Renton MChange Order No.2\Change Order No.2.docx
N%W�.
� KINGS
11
THIS IS A CHANGE ORDER PROPOSAL (COP)
COP#: 3 Proj ect: Renton
Contractor: 3 Kings Environmental Inc. Date Submitted: # 9/10/2014
Contract#: Reply By:
Job#: 214037 Description: Addl Fencing
DESCRIPTION:
Additional Fencing from what was shown on the plans
See Attached Pricing From C and P fence
REASON FOR MODIFICATION:
Work laid out by engineer in the field was more than shown on the plan
Attach completed Cost Summary to this document.
Net Amount of This Proposed Change:
(Add) r 52,078.60 (Deduct) (No Change)
Net Change in Working Days Due to this Pro osed Change:
(Add) (Deduct) n (No Change) Working Days 0
QSubmitted By: Date: l 0-Sep-14
3 Kings Environm nt 1 c.
Contractor
Acknowledgement of Receipt
Date:
By:
Title:
111111111100
C & P Fencing
1516 Chinook Ave
Enumclaw, Wa. 98022
Ph 360 802-1059, Fax 360 450-5464
License#CPFENPF882ME
Date: 8/25/2014
COR cp001
3 Kings Environmental
Project: Renton Municipal Airport 820 Bldg. Demolition
Renton, WA
Attention: Allen
We hereby propose to fumish the materials and perform the labor necessary for the completion of
this project:
The total cost of this Estimate is: $ -
Scope of work to be completed
BID# DESCRIPTION QTY UNIT PRICE EXTENSION
Additional Footage of Permanent AOA Fence over the
footage as shown on plan sheet C4(347 If)
COR 7 FT+3 Black Coated Chain Link Fence 73 $ 24.76 $ 1,807.48
2/�1 y.Go
Exclusions:Insurance premiums for Waiver of Subrogation or primary wording,cleating and grading,concrete saw cutting and core drilling,bonding,
surveys,signs,electrical grounding of fences,traffic control,painting/staining,permits,surveying,labor agreements,staking the fence line,hazardous
waste training or removal,temporary fence,concrete mowing strips,post sleeves/setting of post sleeves,damage to irrigation lines,padlocks,knox box,
fence removal,use tax/sales tax.
SUBMITTALS MUST BE APPROVED AND RETURNED PRIOR TO ORDERING MATERIAL
THIS ESTIMATE IS TO BE INCLUDED AS AN EXHIBIT IN THE CONTRACT
All material costs over 52.500.00 will be subject to a Joint check agreement provided by our supplier
C 8 P Fencing requests that retainage be paid 30 days after their work has been completed,provided that all paperwork,warranties,payroll reports,
releases,etc.have been satisfied.
'Quote good for 25 days.Materials must be ordered and shipped immediately in order to guarantee price.Material orders not received immediately are
subject to any price increase initiated by our suppliers.
IN WITNESS OF WHEREOF,the parties have hereunto caused this Agreement to be executed.
Respectfully Submitted: �— �� Date: 8/25/2014
By:Paul Pohlman, Cell No.253 740-5841,ppohiman@comcast.net
Note: This proposal may be withdrawn by us if not accepted within 25 Days.
Accepted Date:
Title: