CONTRACT CHANGE ORDER AGREEMENT
CONTRACT: CAG 12-056—SE 5'h Street AC Water Main Replacement Project C.O.# 1
CONTRACTOR: B&B Utilities and Excavating, LLC
SUMMARY OF PROPOSED CHANGE: 1
Provide all labor, equipment, subcontracting, bonding, insurance for the complete work required for the
extra work as outlined below:
ITEM Additional Quantities Under This Change Order Unit Quantity Unit Total Price
C01 New unit price for paving based on reduced quantity.
REMOVE Bid item 21—%Z" PG 64-22 HMA Ton 300 . -$110.00 (-$33,000.00)
Add Change Order 1—%" PG 64-22 HMA Ton 129 $131.92 $17,017.68
Subtotal (-$15,982.32)
9.5%Sales Tax (-$1,518.32)
Total (-$17,500.64)
ORIGINAL CONTRACT CURRENT CONTRACT ESTIMATED NET ESTIMATED CONTRACT
AMOUNT AMOUNT CHANGE THIS ORDER TOTAL AFTER CHANGE
$296,821.65 $296,821.65 (-$17,500.64) $279,321.01
Cost Allocation
Water Utility 425.455596.018.595.34.63.000 $17,017.68