CITY OF RENTON
Public Works Department
CHANGE ORDER NO.2
CONTRACT CHANGE ORDER AGREEMENT
CONTRACT: 2012 Steet Patch and Overlay with Curb Ramps CAG-12-081
CONTRACTOR: Lakeside Industries Inc.
SUMMARY OF PROPOSED CHANGE:
Reason/Justification: Work was performed in schedule A that resulted in removing asphalt concrete pavement by cold planing to a depth of 4"and
installing Hot mix asphalt for pavement repair for the 4"patch.
Contract Change: Add items for for removing asphalt concrete pavement(by cold planing 4").Add item for HMA pavement repair for 4"patch.
Add new bid items to the schedule of prices(Schedule A).
Item Approx Units Unit Price Amount
No. Quantity Description
19 2809 SY Removing Asphalt Concrete Pavement(by Cold Planing 4") $ 6.20 $ 17,415.80
20 346.38 TON HMA for Pavement repair for 4"Patch $ 95.00 $ 32,906.10
Total this Change Order: $ 50,321.90
Working Days:
None(no additional days)
All work,materials and measurement to be in accordance with the provisions of the Standard Specifications
and Special Provisions for the type of construction involved.
ORIGINAL CONTRACT CURRENT CONTRACT ESTIMATE NET CHANGE ESTIMATED CONTRACT
AMOUNT AMOUNT THIS ORDER TOTAL AFTER CHANGE
$1,272,052.20 $1,126,125.71 $50,321.90 $1,176,447.61