CONTRACT CHANGE ORDER AGREEMENT
CONTRACT: CAG 12-083 Liberty Lift Station C.O.# 1
CONTRACTOR: Equity Builders, LLC.
SUMMARY OF PROPOSED CHANGE:
Provide all labor, equipment, subcontracting, bonding, insurance for the complete work required for the extra
work as outlined below:
Additional Items Under This Change Order Unit Quantity Unit Price Total Price
NEW ITEM 013:Change Order#1 (Miscellaneous items as detailed
below)
Additional cost including sawcutting, labor and equipment associated LS 1 $3,109.25 $3,109.2
with revising location of the primary power installed for the station.
Additional cost to deepen the primary power trench under existing LS 1 $1,436.98 $1,436.9
utilities in four places.
Additional cost to add elbows on gauges in valve vault. LS 1 $198.72 $198.7
Additional cost to add HOA switch on area light. LS 1 $500.00 $500.0
Credit for use of smaller block style for retaining wall. LS 1 ($700.00) ($700.00
Credit for deletion of CDF trench dam. LS 1 ($600.00) ($600.00
Credit for use of acceptable native materials for backfill in lieu of LS 1 ($1,200.00) ($1,200.00
imported backfill.
+Total NEW ITEM 013 $2,744.95
Sales Tax(9.5%) $260.77
Total Additional Work $3,005.72
ORIGINAL CONTRACT CURRENT CONTRACT ESTIMATED NET CHANGE ESTIMATED CONTRACT TOTAL
AMOUNT AMOUNT THIS ORDER AFTER CHANGE
$362,554.50 $362,554.50 $3,005.72 $365,560.22
SIGNATURES:
Contractor: -_a./1vDate: ;2013
Project Engineer- h--��� — '�—°` Date: 00/,3
Approved By: Date:
( ilities System Director)
H:FileSys\W W P-W astewater\W W P-27-3628\CO-1-Liberty Lift Station.doc/MB