HomeMy WebLinkAboutCO 22 REV CAG-12-021, CO #22-14REV CO# 22REV CITY OF RENTON Page 1 of 1 Public Works Department CRACKED CONC.PANEL REPL.COST REVERSAL CONTRACT CHANGE ORDER 22REV CONTRACT: South Lake WA Roadway Improvements(Garden Ave.Widening) CAG-12-021 CONTRACTOR: ICON Materials DATE: June 22,2015 SUMMARY OF PROPOSED CHANGE: Reversal of CO#22 which deducted$12,178.59 for concrete panels due to subsequent determination that contractor was not responsible for the damage. Locations: 42+10 15'x 13.5' panel 44+25 15'x 13.5' 45+10 15'x 13.5' 46+50 13'x7.5' Contract Change: Add the following quantities to bid item plan quantities in the schedule of prices. Item Approx Units Description Unit Price Amount No. Quantity 19 152 LF Sawcutting $ 3.00 $ 456.00 20 100.00 SY Removing Cement Conc.Pavement $ 16.00 $ 1,600.00 28 32.50 TON Crushed Surfacing Base Course $ 30.00 $ 975.00 34 27.50 CY Cement Conc.Pavement $ 210.00 $ 5,775.00 35 96.00 EA Corrosion Resistent Dowel Bar $ 14.00 $ 1,344.00 36 54.00 EA Tie Bar Drill Hole $ 18.00 $ 972.00 Subtotal: $ 11,122.00 Washington State Sales Tax(9.5%): $ 1,056.59 Total this Change Order(Subtotal Plus Sales Tax): $ 12,178.59 Working Days: None(no additional days) All work,materials and measurement to be in accordance with the provisions of the Standard Specifications and Special Provisions for the type of construction involved. ORIGINAL CONTRACT CURRENT CONTRACT ESTIMATE NET CHANGE ESTIMATED CONTRACT AMOUNT AMOUNT THIS ORDER TOTAL AFTER CHANGE $1,968,690.65 $2,190,391.80 $12,178.59 $2,202,570.39 SIGNATURES: /,,�//�/��A /�7 Contractor: 900.4 /— Date: C7�/ I /i_c Project Manager: �Of i I Date: L'/fU 2-C.) /5 Approved By: .% Date: 21//►//�'� (Transportation Design Manager) g��� Approved By: Al ; .14 Date: 8/8/2-Di"-- Approved Y41 ' 011 (Deputy Public Works Administrator-Transportation) /Approved By: //////��� 3:07'..i........ Date: '5 I J 2./• (Public Works Administrator)