HomeMy WebLinkAboutCO 22 REV CAG-12-021, CO #22-14REV
CO# 22REV
CITY OF RENTON Page 1 of 1
Public Works Department
CRACKED CONC.PANEL REPL.COST REVERSAL
CONTRACT CHANGE ORDER 22REV
CONTRACT: South Lake WA Roadway Improvements(Garden Ave.Widening) CAG-12-021
CONTRACTOR: ICON Materials
DATE: June 22,2015
SUMMARY OF PROPOSED CHANGE: Reversal of CO#22 which deducted$12,178.59 for concrete panels due to
subsequent determination that contractor was not responsible for the damage.
Locations:
42+10 15'x 13.5' panel
44+25 15'x 13.5'
45+10 15'x 13.5'
46+50 13'x7.5'
Contract Change:
Add the following quantities to bid item plan quantities in the schedule of prices.
Item Approx Units Description Unit Price Amount
No. Quantity
19 152 LF Sawcutting $ 3.00 $ 456.00
20 100.00 SY Removing Cement Conc.Pavement $ 16.00 $ 1,600.00
28 32.50 TON Crushed Surfacing Base Course $ 30.00 $ 975.00
34 27.50 CY Cement Conc.Pavement $ 210.00 $ 5,775.00
35 96.00 EA Corrosion Resistent Dowel Bar $ 14.00 $ 1,344.00
36 54.00 EA Tie Bar Drill Hole $ 18.00 $ 972.00
Subtotal: $ 11,122.00
Washington State Sales Tax(9.5%): $ 1,056.59
Total this Change Order(Subtotal Plus Sales Tax): $ 12,178.59
Working Days:
None(no additional days)
All work,materials and measurement to be in accordance with the provisions of the Standard Specifications
and Special Provisions for the type of construction involved.
ORIGINAL CONTRACT CURRENT CONTRACT ESTIMATE NET CHANGE ESTIMATED CONTRACT
AMOUNT AMOUNT THIS ORDER TOTAL AFTER CHANGE
$1,968,690.65 $2,190,391.80 $12,178.59 $2,202,570.39
SIGNATURES: /,,�//�/��A /�7
Contractor: 900.4 /— Date: C7�/ I /i_c
Project Manager: �Of i I Date: L'/fU 2-C.) /5
Approved By: .% Date: 21//►//�'�
(Transportation Design Manager)
g���
Approved By: Al ; .14 Date: 8/8/2-Di"--
Approved
Y41
' 011 (Deputy Public Works Administrator-Transportation) /Approved By: //////��� 3:07'..i........ Date: '5 I J 2./• (Public Works Administrator)