CITY OF RENTON Page 1 of 1
Public Works Department
CHANGE ORDER NO.7
CONTRACT CHANGE ORDER AGREEMENT
CONTRACT: South Lake WA Roadway Improvements (Garden Ave. Widening) CAG -12 -021
CONTRACTOR: ICON Materials
DATE: November 16, 2012
SUMMARY OF PROPOSED CHANGE:
Reason /Justification: This change adding 10 working days is based on double the estimated effort necessary for utility potholing.
With overhead accounted for in force account markups this is a no cost time only contract change.
Contract Change: Ten working days are awarded with this change as requested by an October 3, 2012 letter from ICON Materials.
Add the followino bid items and ouantities to the schedule of prices
Approx
Item No. I Qty Units Description Unit Price I Amount
5A 1 LS Pothole Delay $0.00 $0.00
Washington State Sales Tax (9.5 %): $0.00
Total this Change Order (Subtotal Plus Sales Tax): $0.00
10 Additional Working Days are Granted to complete this work
All work, materials and measurement to be in accordance with the provisions of the Standard Specifications
and Special Provisions for the type of construction involved.
ORIGINAL CONTRACT CURRENT CONTRACI
AMOUNT AMOUNT
ESTIMATE NET CHANGE
THIS ORDER
ESTIMATED CONTRACT
TOTAL AFTER CHANGE
$1,968,690.65
$1,984,215.07
$0.00
$1,984,215.07