CHANGE ORDER NO. 5
CONTRACT CHANGE ORDER AGREEMENT
CONTRACT: South Lake WA Roadway Improvements (Garden Ave. Widening) CAG -12 -021
CONTRACTOR: ICON Materials
SUMMARY OF PROPOSED CHANGE:
Reason /Justification: This change was initiated due to the lack of working /pedestrian space in Stage 1A and the need to construct a
pedestrian access route throught Boeing property in the NW corner of Lake WA Blvd. /Logan Ave. N. intersection.
Contract Change: This no -cost change is for additional working days only in accordance with September 21, 2012 letter from ICON
Materials. The Contractor's labor, equipment and material to construct and maintain this route has been tracked and paid via force
account. No extra field overhead will be compensated for with this change order. This approach will continue until the pedestrian route
is no longer needed and is dismantled. An additional 5 working days will be added to the Contract for this change for time spent
constructing and maintaining the route (through September 21, 2012) and extra time spent on demo of Stage 1A west due to having
the work out of sequence (in reverse order of planned demolition), in addition to a lost shift on 6/13/12 due to lack of working space in
the NW corner. Additional working days may be requested.
Working Days:
5 Additional Working Days are Granted to complete this work
All work, materials and measurement to be in accordance with the provisions of the Standard Specifications
and Special Provisions for the type of construction involved.
ORIGINAL CONTRACT
AMOUNT
CURRENT CONTRACT
AMOUNT
ESTIMATE NET CHANGE
THIS ORDER
ESTIMATED CONTRACT
TOTAL AFTER CHANGE
$1,968,690.65
$1,973,812.57
$0.00
$1,973,812.57