HomeMy WebLinkAboutCO 03CITY OF RENTON
Public Works Department
CHANGE ORDER NO.3
CONTRACT CHANGE ORDER AGREEMENT
CONTRACT: South Lake WA Roadway Improvements (Garden Ave. Widening)
CONTRACTOR: ICON Materials
SUMMARY OF PROPOSED CHANGE:
CAG -12 -021
Reason /Justification: During the initial saw cutting operations it was noted that the existing asphalt pavement was between 9 and 12
inches in depth. The contractor had estimated the depth at 6 inches from the boring logs presented in Appendix C of the Contract Special
Provisions. This existing condition presented the Contractor (Icon Materials) with additional charges for the saw cutting , removal and
disposal of the existing asphalt concrete pavement.The additional compensation was negotiated with1con Materials and verified using the
State Bid Comparison work sheets.
C.O. #3
Page 1 of 1
Contract Change: Compensate the Contractor (Icon Materials) for the additional depth saw cutting in the existing asphalt roadway sections
that were called out for saw cutting by creating a new Bid Item No. 19A "Extra Depth Asphalt Saw Cutting ". Compensate the Contractor
(Icon Materials) for the removal and disposal of the additional depth asphalt by creating a new Bid Item No. 21 A" Removing Extra Depth
Asphalt Concrete Pavement ". This additional work includes all equipment, labor, trucking, disposal, contractors markup and coordination
for the work described by this Change Order.
Add the following quantities to existing bid item plan quantities in the schedule of prices.
Item
Approx
Units
ESTIMATED CONTRACT
TOTAL AFTER CHANGE
Unit Price
Amount
No.
Quantity
Description
19A
1300
LF
Extra Depth Asphalt Concrete Saw Cutting
$3.00
$3,900.00
21A
550
SY
Removing Extra Depth Asphalt Concrete Pavement
$5.00
$2,750.00
Total this Change Order: $6,650.00
Washington State Sales Tax (9.5 %) $631.75
Working Days: Total With Sales Tax $7,281.75
3 Additional Working Days were added for this work
All work, materials and measurement to be in accordance with the provisions of the Standard Specifications
and Special Provisions for the type of construction involved.
ORIGINAL CONTRACT
AMOUNT
CURRENT CONTRACT
AMOUNT
ESTIMATE NET CHANGE
THIS ORDER
ESTIMATED CONTRACT
TOTAL AFTER CHANGE
$1,968,690.65
$1,957,120.88
$7,281.75
$1,964,402.63