HomeMy WebLinkAboutCO 3 CITY OF RENTON Public Works Department CONTRACT CHANGE ORDER AGREEMENT CONTRACT: CAG 12-159 Wells PW-8, PW-9 & EW-3 Primary Disinfection Project C.O.# 3 CONTRACTOR: R. L. Alia Company SUMMARY OF PROPOSED CHANGE: Provide all labor, equipment, subcontracting, bonding, insurance for the complete work required for the extra work as outlined below: Additional Items Under This Change Order Unit Quantity Unit Price Total Price ITEM 028: Change Order#3 Replace chlorine analyzer taps and supply piping with copper fittings LS 1 $6,917.01 $6,917.01 and pipe, includes park restoration. Split conduit delivery and restock fee. For repair of medium voltage LS 1 $1,814.51 $1,814.51 conductors. Replace existing damaged valve box and set exitsting valve cans to LS 1 $1,188.18 $1,188.18 grade. Total ITEM 028 $9,919.70 Sales Tax(9.5%) $942.37 Total Additional Work $10,862.07 ORIGINAL CONTRACT CURRENT CONTRACT ESTIMATED NET CHANGE ESTIMATED CONTRACT TOTAL AMOUNT AMOUNT THIS ORDER AFTER CHANGE $874,889.67 $898,811.96 $10,862.07 $909,674.03 SIGNATURES: Contractor: / ''-� P, Date: Project Engineer: q Date: O 1 )-O 1 Approved By: Date: �! J S I�4� 1l13 NJ V tilities System Director) H:\File Sys\WTR-Drinking Water Utility\WTR-27-Water Project Files\WTR-27-3582 Primary Disinfection Installation 2012\Contractor Payment\CO#3.doc