HomeMy WebLinkAboutCO 2 yrr►'
CITY OF RENTON
Public Works Department
CONTRACT CHANGE ORDER AGREEMENT
CONTRACT: CAG-11-115, Lake Ave S/Rainier Ave S Storm System Project C.O.# 2
CONTRACTOR: James W Fowler Company
SUMMARY OF PROPOSED CHANGE:
CO-2A Boring#1,Sand Fill for Casing Pipe per LS
This change order is to fill the 42-inch steel casing pipe for boring#1,from C13-4 to C13-3.5,with blown sand.
The work includes installing welded angle irons posts and rails on the inside of the 42-inch steel casing, setting
the rails to design grade for the 34-inch carrier pipe, plugging both ends of the 42-inch casing with bricks and
grout, installing vent pipes, plugging and filling the 34-inch carrier pipe with water, and blowing sand into the
annular space between the 42-inch casing pipe and 34-inch pipe so the 34-inch pipe is supported by sand for
its entire length. The wood skids in the original design are deleted and a credit for the deleted work and
materials is included in the JWFowler Change Order Proposal.
The change order includes all labor,equipment, materials, and taxes needed to accomplish the work. The cost
is based on the JWFowler Change Order Proposal COP-010.01, dated 12/7/11, and attached to this change
order.
Measurement for payment will be prorated as the work is accomplished. The unit contract price shall be full
payment for all Work needed to complete the sand fill in the steel casing pipe.
Cost= $5,486.05 per LS= $5,486.05
CO-2B Additional Water Tests and Analysis per Force Account
The King County Wastewater Program Discharge Authorization permit to allow groundwater from the
dewatering system to be discharged to the sanitary sewer was received after the project was awarded. The
Discharge Authorization required sampling and testing for different water parameters than were included in
the project bid document.
This change order provides for all additional costs including labor, lab costs,equipment, materials, markup,
and taxes needed for the additional water sampling and analysis. The costs are based on the Libby
Environmental lab costs and the JWFowler Change Order Proposal COP-013, dated 12/1/11, and attached to
this change order.
All testing costs will have a markup of 21%added per WSDOT Standard Specification section 1-09.6 Force
Account for Services, and the applicable Contractor's markup (12%)and taxes.The costs for the different
water testing parameters by Libby Environmental are listed below:
Parameter Lab Cost WSDOT Services WSDOT Contrct Cost per test
Markup(21%) Markup(12%)
BTEX $60.00 $12.60 $8.71 $81.31
FOG(fats,oil,grease) $70.00 $14.70 $10.16 $94.86
Settleable Solids $25.00 $5.25 $3.63 $33.88
pH $20.00 $4.20 $2.90 $27.10
Metals,if required
MTCAS $100.00 $21.00 $14.52 $135.52
4 Metals $75.00 $15.75 $10.89 $101.64
Cyanide $60.00 $12.60 $8.71 $81.31
For Rush Orders in Lab
FOG (fats,oil,grease) $90.00 $18.90 $13.07 $121.97
Settleable Solids $40.00 $8.40 $5.81 $54.21
pH $30.00 $6.30 $4.36 $40.66
The Contractor shell provide written copies of all water testing and analysis results to the City. The City may
revise the sampling and analysis program as needed to comply with the requirements of the discharge
authorization,and ongoing test results. Additional tests for different parameters may be added by the City at
mutually agreed upon costs between the City and the Contractor. The actual number of tests needed and
frequency of sampling may be changed by the City based on the analysis results and permit requirements. No
additional costs shall be claimed for any changes in the sampling and analysis program.
Measurement for this item will be based on the actual number and type of tests performed. Payment will be
per the unit costs for each different type of test performed, plus applicable WSDOT markups and taxes. The
unit contract price for testing shall be full payment for all Work needed for this item including collecting
samples,analyzing the samples for the various parameters,and providing the written test results to the City.
Estimated Cost=Approx. 120 tests x average$90.00 per test= $10,800.00
ESTMATED TOTAL CHANGE ORDER COST= $16,286.05
Additional Working Days added to the Contract for this Change Order: 2 days
ORIGINAL CONTRACT AMOUNT CURRENT CONTRACT AMOUNT ESTIMATED NETCHANGE ESTIMATED CONTRACT
THIS ORDER TOTAL AFTER CHANGE
$994,925.00 $1,001,555.00 $16,286.05 $1,017,841.05
SIGNATURES:
Contractor: Date:
Project Engineer: Date:
Approved By: '�t, " ° Date:
--• (Utility stems Director)
i
t
James W Fowler Co.
W13 1
General Contractors CHANGE ORDER WORKSHEET
PROJECT Lake Ave S/Rainier Ave S Project No: 2011-05 1 Date: 12/7/2011
OWNER: City of Renton
Work Description: REF#'s COP 010.01
Bore#1 sand filled casing pipe CC# 999000-010
LABOR COSTS HOURS RATE TOTAL
CLASSIFICATION REGULAR OVERTIME REGULAR OVERTIME COST
Laborer Credit for wood skids (45.00) - 44.93 - (2,022.02)
Welder Labor for adding 3/4"angle iron skids 38.00 - 56.56 2,149.39
Laborer Grout ends for seals 16.00 - 44.93 - 718.94
Laborer Blow sand in pipe 12.00 - 44.93 - 539.20
Laborer Fill 36_pi a w/water 16.00 - 44.93 -_ 718.94
TOTAL LABOR COST 37.00 - 2,104.45
LABOR MARKUP 29% 610.29
GRAND TOTAL LABOR 2,714.74
EQUIPMENT COSTS HOURS RATE TOTAL
DESCRIPTION UNIT NO. REGULAR OT REGULAR OT Rate COST
Welder 24.00 16.00 - 17.05 - 272.80
Small Tools 4.00 37.00 - 12.00 - 444.00
2)36"Pipe Plugs - 1.00 Week - 400.00
TOTAL EQUIPMENT 1,116.80
EQUIPMENT MARKUP 21% 234.53
Tax 9.50% 128.38
GRAND TOTAL EQUIPMENT 1,479.71
MATERIALS&RENTAL COSTS TOTAL
Material for skids,pressure treated lumber and SS Straps 1.00 LS (975.00) (975.00)
Material for angle iron skids 1.00 LS 350.00 350.00
Grout for end seals w/pipe connections 2.00 EA 400.00 800.00
Dried Tunnel bore sand 12.00 Ton 35.00 420.00
TOTAL MATERIALS&RENTALS 595.00
MATERIALS&RENT.MARKUP 21% 125.00
Tax 9.50% 68.40
GRAND TOTAL MATERIALS&RENTALS 788.40
SUBCONTRACTOR TOTAL
DESCRIPTION QUANTITY I UNITS I UNIT PRICE COST
Trucking for Blowing sand in casing pipi 1.00 LS 449.20 449.20
TOTAL SUBCONTRACTOR 449.20
SUBCONTRACTOR MARKUP 0-25K 12% 54.00
SUBCONTRACTOR MARKUP 25K-100K 10%
GRAND TOTAL SUBCONTRACTOR 503.20
TOTAL EQUIPMENT,MATERIAL,&SUBCONTRACTS 5,486.05
LOP,Contingency and Inefficiencies unforeseen 0% -
SUB TOTAL»» 5,486.05
TOTAL i $ 5,486.05
12/7/2011 COP 010.1
James W Fowler Co.
General Contractors CHANGE ORDER WORKSHEET
PROJECT Lake Ave S/Rainier Ave S I Project No: 2011-OS Date: 12/1/2011
OWNER: City of Renton
Work Description: REF#'s COP 013.00
Settleable Solids,FOG and Btex testing CC# 999000-010
LABOR COSTS HOURS RATE TOTAL
CLASSIFICATION REGULAR OVERTIME REGULAR OVERTIME COST
TOTAL LABOR COST - -
LABOR MARKUP 29% -
GRAND TOTAL LABOR
EQUIPMENT COSTS HOURS RATE TOTAL
DESCRIPTION UNIT NO. REGULAR OT REGULAR OT Rate COST
TOTAL EQUIPMENT
EQUIPMENT MARKUP 21% -
Tax 9.50% -
GRAND TOTAL EQUIPMENT -
MATERIALS&RENTAL COSTS TOTAL
EA -
TOTAL MATERIALS&RENTALS -
MATERIALS&RENT.MARKUP 21% -
Tax 9.50% -
GRAND TOTAL MATERIALS&RENTALS -
SUBCONTRACTOR TOTAL
DESCRIPTION QUANTITY UNITS UNIT PRICE COST
BTEX 41.00 EA 72.60 2,976.60
FOG 41.00 EA 84.70 3,472.70
Settleable Solids 41.00 EA 30.24 1,239.64
TOTAL SUBCONTRACTOR 7,688.94
SUBCONTRACTOR MARKUP 0-25K 12% 922.67
SUBCONTRACTOR MARKUP 25K-100K 10%
GRAND TOTAL SUBCONTRACTOR 8,61 1.61
TOTAL EQUIPMENT,MATERIAL,&SUBCONTRACTS 8,611.61
LOP,Contingency and Inefficiencies unforeseen 0% -
SUB TOTAL»» 8,611.61
TOTAL $ 8,611.61
1217/2011 COP 010.0