Public Works Department
CONTRACT CHANGE ORDER AGREEMENT
CONTRACT: CAG 11-127 C.O.# 3.
Cascade Interceptor Rehabilitation
CONTRACTOR: SunCoast Environmental NW.
SUMMARY OF PROPOSED CHANGE:
Provide all labor, equipment, subcontracting, bonding, insurance for the complete work required for the extra
work as outlined below:
Additional Items Under This Change Order Unit Quantity Unit Price Total Price
NEW ITEM A14:Additional cost to rehabilitate 0 to 12'deep manhole Each 1 $745.00 $745.00
that is 60"diameter(base cost for 48"diam paid under Item A07).
NEW ITEM A15:Additional cost to rehabilitate 13'to 19'deep manhole Each 1 $945.75 $945.75
that is 60"diameter(base cost for 48"diam paid under Item A08).
NEW ITEM A16:Additional cost to rehabilitate 20'to 25'deep manhole Each 1 $2,230.00 $2,230.00
that is 72"diameter(base cost for 48"diam paid under Item A09).
NEW ITEM B12:Additional cost to rehabilitate 13'to 19'deep manhole Each 1 $945.75 $945.75
that is 60"diameter(base cost for 48"diam paid under Item B08).
Sub Total $4,866.50
Sales Tax(9.5%) $1462.32
Total Additional Work $5,328.82
ORIGINAL CONTRACT CURRENT CONTRACT ESTIMATED NET CHANGE ESTIMATED CONTRACT TOTAL
AMOUNT AMOUNT THIS ORDER AFTER CHANGE
$148,256.43 $170,799.67 $5,328.82 $176,128.49
SIGNATURES:
Contractor: Date:
Project Engineer: Date:
Approved By: Date: 5-/f 0 r 7
(Utilities System Director)