HomeMy WebLinkAboutCO 2 CITY OF RENTON
Public Works Department
CONTRACT CHANGE ORDER AGREEMENT
CONTRACT: CAG 11-127 C.O.# 2
Cascade Interceptor Rehabilitation
CONTRACTOR: SunCoast Environmental NW.
SUMMARY OF PROPOSED CHANGE:
Provide all labor, equipment, subcontracting, bonding, insurance for the complete work required for the extra
work as outlined below:
Additional Items Under This Change Order Unit Quantity Unit Price Total Price
NEW REM A13:Additional cost to provide point repairs and lining of LS 1 $19,337.43 $19,337.43
damaged sewer main laterals connecting to manhole 5321-012
Sub Total $19,337.43
Sales Tax(9.5%) $1,837.06
Total Additional Work $21,174.49
ORIGINAL CONTRACT CURRENT CONTRACT ESTIMATED NET CHANGE ESTIMATED CONTRACT TOTAL
AMOUNT AMOUNT THIS ORDER AFTER CHANGE
$148,256.43 $149,625.18 $21,174.49 $170,799.67
SIGNATURES:
Contractor: Date:
Project Engineer: Date:
Approved By: Date:
J ( tilities S tern Director)
I,
H:FileSys\W W P-W astewater\W W P-27-3f588\CO-2-Cascade Interceptor Rehabilitation/MB