HomeMy WebLinkAboutCO 2 CITY OF RENTON Public Works Department CONTRACT CHANGE ORDER AGREEMENT CONTRACT: CAG 11-127 C.O.# 2 Cascade Interceptor Rehabilitation CONTRACTOR: SunCoast Environmental NW. SUMMARY OF PROPOSED CHANGE: Provide all labor, equipment, subcontracting, bonding, insurance for the complete work required for the extra work as outlined below: Additional Items Under This Change Order Unit Quantity Unit Price Total Price NEW REM A13:Additional cost to provide point repairs and lining of LS 1 $19,337.43 $19,337.43 damaged sewer main laterals connecting to manhole 5321-012 Sub Total $19,337.43 Sales Tax(9.5%) $1,837.06 Total Additional Work $21,174.49 ORIGINAL CONTRACT CURRENT CONTRACT ESTIMATED NET CHANGE ESTIMATED CONTRACT TOTAL AMOUNT AMOUNT THIS ORDER AFTER CHANGE $148,256.43 $149,625.18 $21,174.49 $170,799.67 SIGNATURES: Contractor: Date: Project Engineer: Date: Approved By: Date: J ( tilities S tern Director) I, H:FileSys\W W P-W astewater\W W P-27-3f588\CO-2-Cascade Interceptor Rehabilitation/MB