HomeMy WebLinkAboutCO 1 CITY OF RENTON Public Works Department 0 CONTRACT CHANGE ORDER AGREEMENT CONTRACT: CAG 11-127 C.O.# 1 Cascade Interceptor Rehabilitation CONTRACTOR: SunCoast Environmental NW. SUMMARY OF PROPOSED CHANGE: Provide all labor, equipment, subcontracting, bonding, insurance for the complete work required for the extra work as outlined below: Additional Items Under This Change Order Unit Quantity Unit Price Total Price NEW ITEM B09:Additional cost to provide point repair of infiltration 4 LS 1 $1,250.00 $1,250.00 feet upstream of manhole 5321-029 Sub Total $1,250.00 Sales Tax(9.5%) $118.75 Total Additional Work $1,368.75 i ORIGINAL CONTRACT CURRENT CONTRACT ESTIMATED NET CHANGE ESTIMATED CONTRACT TOTAL AMOUNT AMOUNT THIS ORDER AFTER CHANGE $148,256.43 $148,256.43 $1,368.75 $149,625.18 SIGNATURES. Contractor. L. �AA trj, , Date: 2ra-I't- Project Engineer: �'� p Date: ,Z - - Approved By: Date: U �-- (Utiliti6g System Director) H:FileSys\W W P-Wastewater\W W P-27-3588\CO-1-Cascade Interceptor Rehabilitation/MB