HomeMy WebLinkAboutCO 35 " Change Order #035
Contract Number: CAG-11-192 Federal Aid Number: STPUL-CM0167(048)
Contract Title: Rainier Ave S Improvements
Change Order Number: 035
Prime Contractor: Johansen Excavating
Ordered by Engineer under the terms of Section 1-04.4 of the Standard Specifications
Change proposed by Contractor
Endorsed by Surety Consent
194= Ile
Contractor Attorney on Fact
/2 - 7-0
Date Date
Original Contract Amount: $16,032,772.44
Current Contract Amount: $ 16,918,504.30
Estimated Net Change This Order: $665,236.83
Estimated Contract Total After Change: $17,583,741.13
j�Approval Recommended ❑Approval Recommended
1 -R—
esident Engineer
Date Date
Ap I Recommended v
City of Renton-[Project Manager Name] o Rento be ans ,PE Date
/Z`Z o/' Transportation Systems Division
Date T— Representing
You are ordered to perform thefollowing described work upon receipt of an approved copy of the change order:
Page 1 of 1
ORainier Ave File Structure1700 Construction Admin-Project Control1715 Change Orderst715.2 Individual Change Orderst715 2,OXX CO TESCIChenge Order No 35 Cover doc
Fee
Change Order #0351
Contract Number: CAG-11-192
( Federal Aid#:STPUL-CM0167(048)
Date: December 20, 2013
Page 2 of 3
THE CONTRACT IS MODIFIED AS FOLLOWS:
Background
Per the Construction Stormwater General Permit,the Contractor must properly implement an adequate Stormwater Pollution
Prevention Plan(SWPPP)for construction activity in accordance with the requirements of the General Permit.The initial
SWPPP prepared by the Contractor, based on the Contract Documents:Site Preparation&TESC Plan,Sheet 69 through 80,
was deemed inadequate by the Washington State Department of Ecology(DOE)to prevent violations of surface water quality
and/or sediment management standards.A notice for corrections was issued by the DOE on June 11,2012. It was
recommended that all construction stormwater from disturbed areas be conveyed through sediment pond(s)or other
appropriate sediment removal Best Management Practices(BMP's),per General Permit Condition S9-D4. Based on this
recommendation and agreement by the City and Contractor,the SWPPP was modified to include portable treatment facilities
that would minimize sediment discharges from the site.
Description of Work
Work shall include the mobilization,operation,maintenance,and demobilization of portable treatment facilities within the
project limits including all associated pumping equipment,temporary piping and appurtenances,and personnel as required
for maintenance and operation as shown in the contractor's SWPPP dated May 2012.
Description of Change
Lump sum bid item"A275—portable stormwater treatment facilities"shall be added to schedule A to capture the work
described above.
Material
No new material shall be incorporated into the project due to this change.
Plans/Specifications
No specification or plan changes were made as a result of this change.
Timeline
A total of,0_additional working days will be included with this change order.
At this time, no critical path impacts have been realized due to the implementation of the Best Management Practices being
utilized on the project and as described in the Change Order. If the Contractor experienced delays to the critical path work,
due to this Change,Contractor shall prepare a Time Impact Analysis(TIA)illustrating the influence of the delay on the
Contract Completion Date or milestones.The most recent monthly updated Type B schedule accepted by the Engineer shall
be used to display the impacts of the change.Any cost associated with delays will be addressed in a future change order.
Measurement&Payment
Measurement and Payment shall be made by the following:
Contract Number: CAG 11-192
STPUL-CM0167(048) '""" 3
Previo
Bid us New Qty.
item Description Unit Qty- City. Chane Unit Price Change Amount
A275 Portable stormwater treatment facilities LS 0 1 1 $665,236.83 $665,236.83
TOTAL CONTRACT ADD—CHANGE
ORDER 035: $665,236.83