Loading...
HomeMy WebLinkAboutCO 28 Cd + � + �N g T� Chan a Order #028 Contract Number: CAG-11-192 Federal Aid Number: STPUL-CM0167(048) Contract Title: Rainier Ave S Improvements Change Order Number: 028 Prime Contractor: Johansen Excavating _X_ Ordered by Engineer under the terms of Section 1-04.4 of the Standard Specifications Change proposed by Contractor Endorsed by Surety Consent =4 ,/ 4, Contractor Attorney on Fact (v - Z L - Zo %3 Date Date Original Contract Amount: $16,032,772.44 Current Contract Amount: $16,811,568.51 Estimated Net Change This Order: $22,551.21 Estimated Contract Total After Change: $16,834,125.72 Approval Recommended ❑Approval Recommended sident Engineer Date Date Appr I Recommended ed City of Renton—(Project Manager Name] Ity of Renton= 66ert FW6n,PE Date 3����3 Transportation Systems Division Date Representing You are ordered to perform the following described work upon receipt of an approved copy of the change order. Page 1 of 2 IARainier Ave File Structure\700 Construction Admin-Project Control\715 Change Orders\715.2 Individual Change Orders\715.2.028 CO 028 Planter Depth\Change Order No 028 Cover-Planter Depth.docx a' r�y1 Change Order #028 Contract Number: CAG-11-192 �•e Federal Aid#:STPUL-CM0167(048) Date:June 12, 2013 Page 2 of 2 THE CONTRACT IS MODIFIED AS FOLLOWS: Background Per Request for Information 088,the Contractor needed clarification due to the Contract plans having conflicting information regarding the planter subgrade depth. In a meeting held on April 24,2013,The City,engineering team,and the Contractor agreed that the Contract Documents were sufficiently ambiguous with regards to the planter's depth and that the Contractor's bidding error was justified to a degree.This excavation of landscape planters was a slower labor production rate and required different equipment than the standard excavation bid items for this Contract.Therefore,the City shall compensate the Contractor for the actual of work performed based on Johansen timecards and certified payrolls. No overhead,profit or any other additional compensation shall be granted for this work per the meeting's negotiations. Description of Change Additional excavation depth is required for the planter areas to meet the clarification provided in RFI 088,to a depth of 14" from 8". The change in construction methods for this type of work,due to the state of project completion at the time of the clarification,required.additional labor and equipment to satisfy the contract requirements. New Material No new material shall be incorporated into the project via this Change Order. p P 1 g Timeline A total of 0 additional working days will be included for this Change Order. Measurement&Payment Measurement and Payment shall be made by the following: Bid Previous New Qty. Item Description Unit Qty- Qty- Change Unit Price Change Amount Planter Depth Excavation per Change A258 Order 028 LS 0 1 1 $22,551.21 $22,551.21. Total ADD To Contract: $22,551.21 I i I II