�N g T� Chan a Order #028
Contract Number: CAG-11-192 Federal Aid Number: STPUL-CM0167(048)
Contract Title: Rainier Ave S Improvements
Change Order Number: 028
Prime Contractor: Johansen Excavating
_X_ Ordered by Engineer under the terms of Section 1-04.4 of the Standard Specifications
Change proposed by Contractor
Endorsed by Surety Consent
=4 ,/ 4,
Contractor Attorney on Fact
(v - Z L - Zo %3
Date Date
Original Contract Amount: $16,032,772.44
Current Contract Amount: $16,811,568.51
Estimated Net Change This Order: $22,551.21
Estimated Contract Total After Change: $16,834,125.72
Approval Recommended ❑Approval Recommended
sident Engineer
Date Date
Appr I Recommended ed
City of Renton—(Project Manager Name] Ity of Renton= 66ert FW6n,PE Date
3����3 Transportation Systems Division
Date Representing
You are ordered to perform the following described work upon receipt of an approved copy of the change order.
Page 1 of 2
IARainier Ave File Structure\700 Construction Admin-Project Control\715 Change Orders\715.2 Individual Change Orders\715.2.028 CO 028 Planter Depth\Change Order No 028
Cover-Planter Depth.docx
a' r�y1 Change Order #028
Contract Number: CAG-11-192
�•e
Federal Aid#:STPUL-CM0167(048)
Date:June 12, 2013
Page 2 of 2
THE CONTRACT IS MODIFIED AS FOLLOWS:
Background
Per Request for Information 088,the Contractor needed clarification due to the Contract plans having conflicting information
regarding the planter subgrade depth. In a meeting held on April 24,2013,The City,engineering team,and the Contractor
agreed that the Contract Documents were sufficiently ambiguous with regards to the planter's depth and that the
Contractor's bidding error was justified to a degree.This excavation of landscape planters was a slower labor production rate
and required different equipment than the standard excavation bid items for this Contract.Therefore,the City shall
compensate the Contractor for the actual of work performed based on Johansen timecards and certified payrolls. No
overhead,profit or any other additional compensation shall be granted for this work per the meeting's negotiations.
Description of Change
Additional excavation depth is required for the planter areas to meet the clarification provided in RFI 088,to a depth of 14"
from 8". The change in construction methods for this type of work,due to the state of project completion at the time of the
clarification,required.additional labor and equipment to satisfy the contract requirements.
New Material
No new material shall be incorporated into the project via this Change Order.
p P 1 g
Timeline
A total of 0 additional working days will be included for this Change Order.
Measurement&Payment
Measurement and Payment shall be made by the following:
Bid Previous New Qty.
Item Description Unit Qty- Qty- Change Unit Price Change Amount
Planter Depth Excavation per Change
A258 Order 028 LS 0 1 1 $22,551.21 $22,551.21.
Total ADD To Contract: $22,551.21